U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION FISCAL MANAGEMENT INFORMATION SYSTEM
Report: FMISF71A-2
Vermont

SUMMARY PROJECT LEVEL DATA PURSUANT TO 23 U.S.C. 104(g)(3)(B) WITH AN ESTIMATED TOTAL COST OF $25,000,000 OR MORE
AS OF SEPTEMBER 30, 2023
RECIPIENT
PROJECT
NUMBER
PROJECT TITLE
TOTAL
OBLIGATIONS
ESTIMATED
TOTAL
COST
Vermont
0102016
READSBORO, VT100, BRIDGE NO. 25; SCOPING TO EVALUATE ALTERNATIVES, PENG, REPLACE BRIDGE.
$3,613,797.06
$25,750,236.32
Vermont
0134013
WATERBURY, US 2, .14ME INT/VT 100 E.84M, PENG & RECONSTRUCT HIGHWAY
$28,525,372.16
$31,992,638.20
Vermont
0193496
BRANDON, US7, BEGINNING AT MM 3.351 EXT. NORTH 1.149 MILES; PENG, ROWA, CONST., RECONSTRUCT EXISTING HIGHWAY.
$26,006,439.45
$33,313,663.11
Vermont
0281026
NORTH HERO-GRAND ISLE, US2, BRIDGE NO. 8; PENG, CONST., REPLACE BRIDGE.
$81,407,315.59
$97,087,136.28
Vermont
0283026
CABOT-DANVILLE, US 2, 3.93 MILES, PENG, ROWA, CONST., RECONSTRUCT HIGHWAY
$25,367,840.85
$27,901,212.63
Vermont
0911066
ROCKINGHAM, I-91, BRIDGE NO. 24 N&S; PENG, CONST., REHAB BRIDGES.
$46,259,424.22
$52,193,887.02
Vermont
1444060
HARTFORD, TH6, BR7; OTHER, SCOPING TO EVALUATE ALTERNATIVES. 
$7,717,571.69
$26,270,288.61
Vermont
2940001
BRATTLEBORO-NEWFANE, VT30, RESURFACING. 
$14,468,454.19
$28,567,132.29
Vermont
2971001
WILMINGTON-BRATTLEBORO, VT9, BEGINNING AT MM 7.077 IN WILMINGTON EXT. EASTERLY 12.565 MILES; PENG, RESURFACING.
$23,829,656.48
$28,306,283.85
Vermont
5000001
BURLINGTON, SO. CONN., I-189 INTERCHG. W&N, CONSTR. NEW HIGHWAY
$65,688,636.80
$74,330,647.28
Vermont
A004152
BRATTLEBORO-HINSDALE, NH, BRIDGE ST.; PENG, REPLACE CONNECTICUT RIVER BRIDGE.
$12,180,000.00
$26,720,258.73
Vermont
PS19001
MARSHFIELD-DANVILLE, US2, BEGINNING AT MM 0.987 IN PLAINFIELD EXT. EASTERLY 16.669 MILES; PENG, RESURFACING.
$9,583,207.00
$30,065,868.00
Vermont
WCRS023
MIDDLEBURY, VERMONT RAILWAY; PENG, ROWA, CONST., LOWER GRADE OF RAILS UNDER VT30/MERCHANTS ROW, TO 21-FT CLEARANCE.
$79,837,809.34
$93,167,850.49