RECIPIENT |
PROJECT NUMBER |
COUNTY |
POPULATION RANGE |
OWNERSHIP |
PROGRAM |
TYPE OF IMPROVEMENT |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|---|---|---|---|
South Carolina | Berkeley | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $16,616,181.55 |
$30,373,765.69 |
|
South Carolina | Berkeley | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,919,818.45 |
$2,428,477.39 |
|
South Carolina | Berkeley | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $752,759.62 |
||
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | $45,000,000.00 |
$83,774,144.19 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $669,282.26 |
$743,646.96 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,795,505.68 |
$6,439,450.76 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $7,200,000.00 |
$31,446,409.38 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - No Added Capacity | $8,602,577.46 |
$9,558,419.39 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,811,759.68 |
$3,124,177.41 |
|
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - No Added Capacity | $4,800,000.00 |
$16,382,922.65 |
|
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - No Added Capacity | $3,200,000.00 |
$24,817,938.34 |
|
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $3,373,158.51 |
$4,216,448.14 |
|
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Other | $1,200,871.34 |
||
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Preliminary Engineering | $1,265,651.20 |
$1,582,064.00 |
|
South Carolina | Pickens | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Utilities | $2,538,521.58 |
||
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM - COVID APP | 4R - Added Capacity | $2,829,817.25 |
$2,829,817.25 |
|
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Added Capacity | $4,000,000.00 |
||
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $2,121,661.00 |
$2,652,076.25 |
|
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Utilities | $4,706,879.08 |
||
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $17,387,816.31 |
$23,619,232.01 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $7,876,832.03 |
$9,846,040.04 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $2,785,623.54 |
$3,482,029.43 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $583,735.52 |
$729,669.41 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $114,112.00 |
$142,640.00 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Facilities for Pedestrians and Bicycles | $1,129,089.00 |
$1,411,361.25 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | 4R - Added Capacity | $6,419,382.67 |
$6,419,382.67 |
|
South Carolina | Spartanburg | >= 200,000 | State | FAST ACT NATIONAL FREIGHT | 4R - Added Capacity | $12,760,129.33 |
$12,760,129.33 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Added Capacity | $12,346,676.68 |
$12,346,676.68 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Added Capacity | $19,921,735.32 |
$19,921,735.32 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $78,619,283.56 |
$205,980,782.70 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $114,788,636.75 |
$217,936,331.44 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $32,585,583.00 |
$32,979,033.81 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $593,832.80 |
||
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $6,512,734.20 |
$6,512,734.20 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $4,341,822.80 |
$4,749,760.75 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $13,656,031.50 |
$28,067,673.15 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $11,700,000.00 |
$31,245,786.62 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $11,233,600.00 |
$16,124,392.75 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $24,766,200.00 |
$33,925,180.64 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $4,757,638.23 |
||
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,750,000.00 |
$12,206,996.46 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $728,984.92 |
$911,231.15 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $812,690.70 |
$1,015,863.38 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $802,296.52 |
$1,002,870.64 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $49,720.92 |
$62,151.15 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Right of Way | $155,862.39 |
$194,827.99 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $1,015,279.19 |
$1,269,098.99 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Bridge Replacement - No Added Capacity | $5,990.29 |
$7,487.87 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Preliminary Engineering | $346,597.05 |
$433,246.31 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Right of Way | $25,521.61 |
$31,902.01 |
|
South Carolina | Charleston | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Utilities | $2,659.55 |
$3,324.44 |
|
South Carolina | Charleston | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $9,696,085.42 |
$12,120,106.77 |
|
South Carolina | Charleston | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | $4,873,068.50 |
$6,091,335.61 |
|
South Carolina | Charleston | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,107,988.87 |
$2,634,986.10 |
|
South Carolina | Charleston | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $37,098.85 |
$46,373.57 |
|
South Carolina | Charleston | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,282,907.84 |
$1,603,634.80 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $1,960,760.69 |
$2,450,950.86 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $9,310,344.92 |
$11,637,931.10 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $2,048,128.75 |
$2,560,160.93 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $19,108.11 |
$23,885.73 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Right of Way | $52,603.85 |
$65,754.80 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $7,580.11 |
$9,475.14 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | 4R - No Added Capacity | $163,053.66 |
$203,817.08 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Bridge Replacement - No Added Capacity | $801,910.40 |
$1,002,388.00 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Construction Engineering | $18,762.27 |
$18,762.27 |
|
South Carolina | Richland | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Preliminary Engineering | $909,766.69 |
$1,138,598.23 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $66,926.12 |
$66,926.12 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $10,223,300.65 |
$10,652,664.36 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $600,944.60 |
$656,016.71 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | 4R - No Added Capacity | $1,221,590.03 |
$1,526,987.54 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Bridge Replacement - No Added Capacity | $32,899.13 |
$41,123.91 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $78,223.44 |
$97,779.30 |
|
South Carolina | Horry | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $0.01 |
$0.01 |
|
South Carolina | Horry | >= 200,000 | State | BRIDGE REP & REHAB-20% ON/OFF | Preliminary Engineering | |||
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | BRIDGE REP & REHAB-20% ON/OFF | Preliminary Engineering | $1,736,872.00 |
$2,171,090.00 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Preliminary Engineering | $364,941.79 |
$456,177.24 |
|
South Carolina | Horry | >= 200,000 | State | BRIDGE REP & REHAB-65% ON SYS | Preliminary Engineering | |||
South Carolina | Horry | >= 200,000 | State | REDISTRIBUTION OF TIFIA FUNDS | Other | |||
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | REDISTRIBUTION OF TIFIA FUNDS | Other | $10,933,032.00 |
$13,666,290.00 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $5,351,108.43 |
$6,688,885.54 |
|
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $617,314.59 |
$771,643.24 |
|
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $1,768,394.66 |
$2,210,493.32 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $26,039,233.93 |
$32,549,042.41 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $575,075.76 |
$718,844.70 |
|
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | |||
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | |||
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $111,642.11 |
$139,552.64 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $22,548.30 |
||
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $22,548.30 |
||
South Carolina | Horry | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | |||
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $32,688.56 |
$40,860.70 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | $1,191,241.07 |
$1,489,051.34 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | $404,451.15 |
$505,563.94 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | $66,851.43 |
$83,564.29 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | $603,976.95 |
$754,971.19 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | $304,688.25 |
$380,860.31 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | $653,296.40 |
$816,620.50 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | $979,944.60 |
$1,224,930.75 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | $653,296.40 |
$816,620.50 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | $1,634,809.48 |
$2,043,511.86 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Construction Engineering | $171,987.92 |
$214,984.88 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Construction Engineering | $58,393.48 |
$72,991.84 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Construction Engineering | $9,651.82 |
$12,064.77 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Construction Engineering | $87,200.44 |
$109,000.54 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 15% OFF SYST | Construction Engineering | $43,990.00 |
$54,987.49 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $17,257.81 |
$21,572.26 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $34,209.79 |
$42,762.24 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $3,786.52 |
$4,733.15 |
|
South Carolina | Statewide | N/A | N/A | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $4,742,142.71 |
$5,927,678.38 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $22,908.48 |
$28,635.60 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | $67,472.94 |
$84,341.18 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $4,361,671.27 |
$5,452,089.11 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $1,743,308.34 |
$2,179,135.42 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $2,614,962.51 |
$3,268,703.13 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $1,743,308.34 |
$2,179,135.42 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | $871,654.17 |
$1,089,567.71 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $428,955.84 |
$536,194.82 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $216,371.09 |
$270,463.86 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $13,177.06 |
$16,471.33 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $250,316.64 |
$312,895.81 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $812,462.06 |
$1,015,577.57 |
|
South Carolina | Statewide | N/A | N/A | BRIDGE PROGRAM - 85% ON/OFF | Other | $20,568.01 |
$25,710.01 |
|
South Carolina | Statewide | N/A | N/A | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $18,803.10 |
$23,503.86 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $30,859.75 |
$38,574.69 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $140,649.24 |
$175,811.56 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $278,805.95 |
$348,507.46 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $186,701.47 |
$233,376.86 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Preliminary Engineering | $549,896.98 |
$687,371.26 |
|
South Carolina | Statewide | N/A | State | BRIDGE PROGRAM - 85% ON/OFF | Rail/Hwy Crossing | $463,987.50 |
$579,984.37 |
|
South Carolina | Statewide | N/A | N/A | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $185,225.97 |
$231,532.45 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $72,527.31 |
$90,659.13 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $24,175.77 |
$30,219.71 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $48,351.54 |
$60,439.42 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $48,351.54 |
$60,439.42 |
|
South Carolina | York | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | $120,973.11 |
$151,216.40 |
|
South Carolina | York | >= 200,000 | State | BRIDGE REP & REHAB-15% OFF SYS | 4R - No Added Capacity | $238,497.74 |
$298,122.16 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | BRIDGE REP & REHAB-15% OFF SYS | 4R - No Added Capacity | $80,974.95 |
$101,218.68 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | BRIDGE REP & REHAB-15% OFF SYS | 4R - No Added Capacity | $120,921.90 |
$151,152.37 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | BRIDGE REP & REHAB-15% OFF SYS | 4R - No Added Capacity | $61,001.47 |
$76,251.84 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | BRIDGE REP & REHAB-15% OFF SYS | 4R - No Added Capacity | $13,384.27 |
$16,730.36 |
|
South Carolina | Statewide | N/A | N/A | BRIDGE REP & REHAB-20% ON/OFF | Preliminary Engineering | $39,183.49 |
$48,979.36 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | GRANTS SUP PLAN SECTION 117 | Bridge Replacement - No Added Capacity | $836,804.94 |
$836,804.94 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | GRANTS SUP PLAN SECTION 117 | Bridge Replacement - No Added Capacity | $278,934.98 |
$278,934.98 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | GRANTS SUP PLAN SECTION 117 | Bridge Replacement - No Added Capacity | $557,869.96 |
$557,869.96 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | GRANTS SUP PLAN SECTION 117 | Bridge Replacement - No Added Capacity | $557,869.96 |
$557,869.96 |
|
South Carolina | York | >= 200,000 | State | GRANTS SUP PLAN SECTION 117 | Bridge Replacement - No Added Capacity | $1,395,763.13 |
$1,395,763.13 |
|
South Carolina | York | >= 200,000 | State | HIGHWAY BRIDGE PROGRAM | 4R - No Added Capacity | $33,625.37 |
$42,031.70 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | HIGHWAY BRIDGE PROGRAM | 4R - No Added Capacity | $11,416.51 |
$14,270.64 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | HIGHWAY BRIDGE PROGRAM | 4R - No Added Capacity | $17,048.56 |
$21,310.70 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | HIGHWAY BRIDGE PROGRAM | 4R - No Added Capacity | $8,600.49 |
$10,750.61 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | HIGHWAY BRIDGE PROGRAM | 4R - No Added Capacity | $1,887.02 |
$2,358.79 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | HIGHWAY BRIDGE PROGRAM | Preliminary Engineering | $1,481.48 |
$1,851.88 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | HIGHWAY BRIDGE PROGRAM | Preliminary Engineering | $13,384.94 |
$16,731.17 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | HIGHWAY BRIDGE PROGRAM | Preliminary Engineering | $6,752.30 |
$8,440.37 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | HIGHWAY BRIDGE PROGRAM | Preliminary Engineering | $8,963.18 |
$11,203.97 |
|
South Carolina | York | >= 200,000 | State | HIGHWAY BRIDGE PROGRAM | Preliminary Engineering | $26,399.50 |
$32,999.36 |
|
South Carolina | Statewide | N/A | N/A | HIGHWAY PRIORITY PROJECTS | 4R - No Added Capacity | $5,712,338.49 |
$5,712,338.49 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | SEC 115 UNOBL BAL TRANSF | Bridge Replacement - No Added Capacity | $357,585.00 |
$357,585.00 |
|
South Carolina | Fairfield | >= 5,000 AND < 50,000 | State | SEC 115 UNOBL BAL TRANSF | Bridge Replacement - No Added Capacity | $119,195.00 |
$119,195.00 |
|
South Carolina | Chester | >= 5,000 AND < 50,000 | State | SEC 115 UNOBL BAL TRANSF | Bridge Replacement - No Added Capacity | $238,390.00 |
$238,390.00 |
|
South Carolina | Lancaster | >= 50,000 AND < 200,000 | State | SEC 115 UNOBL BAL TRANSF | Bridge Replacement - No Added Capacity | $238,390.00 |
$238,390.00 |
|
South Carolina | York | >= 200,000 | State | SEC 115 UNOBL BAL TRANSF | Bridge Replacement - No Added Capacity | $596,440.00 |
$596,440.00 |
|
South Carolina | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $6,154,296.26 |
$7,692,870.36 |
|
South Carolina | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | $1,403,376.38 |
$1,754,220.48 |
|
South Carolina | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,732,050.57 |
$2,165,063.15 |
|
South Carolina | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $129,431.99 |
$161,789.99 |
|
South Carolina | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $42,935.66 |
$53,669.57 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | CARBON REDUCTION PROGRAM | Construction Engineering | $1,703,286.00 |
$2,129,107.50 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | $940,382.31 |
$1,175,477.89 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | New Construction Roadway | $3,405,767.06 |
$3,405,767.06 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM -APPOR | Utilities | $2,655,734.00 |
$3,319,667.50 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | MINIMUM GUARANTEE - TEA-21 | Preliminary Engineering | $2,033,569.50 |
$2,541,961.88 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SEC 115 UNOBL BAL TRANSF | Preliminary Engineering | $800,000.00 |
$800,000.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SEC 115 UNOBL BAL TRANSF | Right of Way | $200,000.00 |
$200,000.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | $4,800,000.00 |
$27,308,878.12 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,316,025.84 |
$9,092,143.98 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | $19,543,863.44 |
$80,219,662.31 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $4,736,000.00 |
$8,000,000.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $7,556,830.50 |
$9,446,278.12 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $2,000,000.00 |
$2,500,000.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $820,598.66 |
$1,025,748.32 |
|
South Carolina | Charleston | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Preliminary Engineering | $340,703.59 |
$425,879.49 |
|
South Carolina | Charleston | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Utilities | $7,659,296.41 |
$9,574,120.51 |
|
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $39,522,284.50 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $57,089,449.50 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $36,098,958.77 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | $157,466,831.27 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $2,755,077.00 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,414,735.35 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $1,368,109.81 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $65,000,000.00 |
||
South Carolina | Charleston | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $15,468,796.07 |
||
South Carolina | Berkeley | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Construction Engineering | $235,091.79 |
$3,000,000.00 |
|
South Carolina | Berkeley | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Other | $4,804,348.21 |
$24,456,135.23 |
|
South Carolina | Berkeley | >= 200,000 | State | HIGH PRIORITY PROJECT SEC 1702 | Utilities | $500,005.00 |
||
South Carolina | Florence | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $11,188,293.38 |
$13,985,366.73 |
|
South Carolina | Florence | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,000,000.00 |
$2,500,000.00 |
|
South Carolina | Florence | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,057,490.08 |
$1,345,000.00 |
|
South Carolina | Florence | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $4,800,000.00 |
$6,000,000.00 |
|
South Carolina | Florence | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,151,053.67 |
$1,438,817.09 |
|
South Carolina | Greenville | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - Added Capacity | $409,630.40 |
$512,038.00 |
|
South Carolina | Greenville | >= 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | $1,575,000.00 |
$1,750,000.00 |
|
South Carolina | Greenville | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $704,541.98 |
$880,677.47 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $2,891,379.70 |
$3,614,224.63 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $8,533,296.37 |
$10,729,383.08 |
|
South Carolina | Greenville | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $1,442,975.96 |
$1,803,719.94 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $3,013,338.54 |
$3,766,673.17 |
|
South Carolina | Greenville | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $60,000.00 |
$75,000.00 |
|
South Carolina | Greenville | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,000,000.00 |
$1,250,000.00 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $935,925.31 |
$1,169,906.64 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $1,891,741.34 |
$2,364,676.68 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $434,228.79 |
$542,785.99 |
|
South Carolina | Greenville | >= 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Other | $2,290,912.78 |
$2,863,640.98 |
|
South Carolina | Greenville | >= 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Other | $22,875,524.62 |
$28,594,405.04 |
|
South Carolina | Greenville | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $65,520,970.45 |
$86,661,565.49 |
|
South Carolina | Horry | >= 200,000 | N/A | HIGH PRIORITY PROJECTS-TEA-21 | Other | $563,936.23 |
$704,920.29 |
|
South Carolina | Horry | >= 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Other | $37,839,401.68 |
$47,299,252.11 |
|
South Carolina | Horry | >= 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Other | $58,347,780.54 |
$72,934,725.92 |
|
South Carolina | Horry | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Other | $11,276,580.63 |
$14,095,725.28 |
|
South Carolina | Horry | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $86,771,110.86 |
$160,481,294.14 |
|
South Carolina | Spartanburg | >= 200,000 | State | INTERSTATE MAINTENANCE | Other | $457,758.44 |
$463,680.73 |
|
South Carolina | Greenville | >= 200,000 | State | INTERSTATE MAINTENANCE | Other | $55,967,666.94 |
$56,691,744.65 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $160,431,665.52 |
$231,797,164.70 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $19,683,136.88 |
$28,502,637.69 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $25,679.72 |
$25,679.72 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $3,139,747.05 |
$3,139,747.05 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Other | $390,958.32 |
$434,398.14 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Other | $3,197.68 |
$3,552.97 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $368,762.00 |
$368,762.00 |
|
South Carolina | Greenville | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $2,976,713.85 |
$2,976,713.85 |
|
South Carolina | Laurens | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | 4R - Maintenance Resurfacing | $2,216,171.67 |
$2,462,412.96 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | 4R - Maintenance Resurfacing | $4,456,211.68 |
$4,951,346.32 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | $1,802,349.75 |
$2,002,610.84 |
|
South Carolina | Laurens | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | $166,785.78 |
$185,317.53 |
|
South Carolina | Laurens | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Maintenance Resurfacing | $6,058,848.44 |
$6,732,053.82 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Maintenance Resurfacing | $6,058,848.43 |
$6,732,053.81 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $899,838.65 |
$999,820.72 |
|
South Carolina | Laurens | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $899,838.66 |
$999,820.73 |
|
South Carolina | Laurens | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $53,577.36 |
$59,530.40 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $578,977.01 |
$643,307.79 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Construction Engineering | $286,195.75 |
$357,744.69 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $16,151,189.43 |
$22,402,608.75 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $7,386,485.47 |
$9,233,106.84 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,426,912.75 |
$1,783,640.94 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,485,284.12 |
$3,106,605.15 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $538,640.00 |
$673,300.00 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $394,715.88 |
$493,394.85 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $7,984,847.70 |
$9,981,059.62 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $42,042,280.47 |
$52,552,850.59 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $7,505,719.53 |
$9,382,149.41 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $3,192,000.00 |
$3,990,000.00 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $665,517.74 |
$1,381,897.18 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $26,129,900.11 |
$54,506,843.10 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $19,417,297.59 |
$19,417,297.59 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $14,504,526.75 |
$14,504,526.75 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $4,567,524.21 |
$5,421,698.54 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $2,768,882.68 |
||
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $52,708.00 |
$52,708.00 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - No Added Capacity | $3,276,625.73 |
$4,095,782.16 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $264,858.58 |
$331,073.22 |
|
South Carolina | Lexington | >= 200,000 | State | HSIP LIMITING FLEXIBLE | 4R - Added Capacity | $87,989,212.15 |
||
South Carolina | Lexington | >= 200,000 | State | HSIP LIMITING FLEXIBLE | Bridge Replacement - Added Capacity | $3,959,775.75 |
||
South Carolina | Lexington | >= 200,000 | State | HSIP LIMITING FLEXIBLE | Construction Engineering | $16,267,796.35 |
||
South Carolina | Lexington | >= 200,000 | State | HSIP LIMITING FLEXIBLE | Safety | $500,000.00 |
$500,000.00 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $12,000,000.00 |
$12,000,000.00 |
|
South Carolina | Berkeley | >= 200,000 | State | FAST ACT NATIONAL FREIGHT | 4R - Added Capacity | $10,000,000.00 |
$12,500,000.00 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $28,850,636.99 |
$38,061,417.73 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $4,742,246.90 |
$5,927,808.62 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $6,080,000.00 |
$7,600,000.00 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $340,000.00 |
$425,000.00 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,182,707.78 |
$2,728,384.73 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | FAST ACT NATIONAL FREIGHT | Other | $45,886,712.00 |
$57,358,390.00 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $20,500,439.48 |
$25,625,549.35 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $116,150,766.28 |
$150,741,496.20 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $490,320.00 |
$612,900.00 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Traffic Management/Engineering - HOV | $1,062,400.00 |
$1,328,000.00 |
|
South Carolina | Cherokee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $5,456,000.00 |
$6,820,000.00 |
|
South Carolina | Lexington | >= 200,000 | State | CARBON REDUCTION PROGRAM | 4R - Added Capacity | $7,735,485.00 |
$9,669,356.25 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $26,012,307.76 |
$32,515,384.71 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - Added Capacity | $6,168,782.76 |
$7,710,978.44 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,082,639.03 |
$1,353,298.79 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,760,000.00 |
$4,700,000.00 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $1,860,640.00 |
$2,325,800.00 |
|
South Carolina | Lexington | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,958,623.86 |
$2,448,279.83 |
|
South Carolina | Lexington | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $188,886.40 |
$236,108.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | 4R - No Added Capacity | $4,012,000.00 |
$5,015,000.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Replacement - No Added Capacity | $8,342,867.63 |
$10,428,584.53 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $400,000.00 |
$500,000.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Utilities | $77,655.90 |
$97,069.87 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $3,309,748.94 |
$5,418,024.70 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,119,671.51 |
$1,399,589.39 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,835,200.00 |
$3,544,000.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $601,102.40 |
$751,378.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $840,240.00 |
$1,050,300.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $226,253.00 |
$282,816.25 |
|
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | 4R - No Added Capacity | $1,229,004.70 |
$1,365,560.78 |
|
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | $1,052,667.46 |
$1,169,630.51 |
|
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $73,037,563.77 |
||
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,668,809.49 |
||
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $29,000.00 |
||
South Carolina | Colleton | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,332,332.54 |
$1,480,369.49 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | 4R - No Added Capacity | $5,000.00 |
$5,555.56 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | $990,000.00 |
$1,100,000.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $19,173,187.99 |
$21,303,542.21 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,861,960.00 |
$2,068,844.44 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Environmental Only | $577,575.00 |
$641,750.00 |
|
South Carolina | Richland | >= 200,000 | State | FAST ACT NATIONAL FREIGHT | Other | $36,514,073.43 |
$43,515,499.65 |
|
South Carolina | Lexington | >= 200,000 | State | FAST ACT NATIONAL FREIGHT | Other | $24,392,122.72 |
$28,361,652.14 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | FAST ACT NATIONAL FREIGHT | Other | $26,282,053.30 |
$30,723,173.50 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | HIGHWAY INFRA PRGM -APPOR | Other | $3,709,939.28 |
$3,720,419.38 |
|
South Carolina | Lexington | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Other | $3,708,811.85 |
$3,719,287.24 |
|
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Other | $3,705,503.97 |
$3,715,973.10 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $7,686,481.97 |
$8,540,535.51 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,777,350.08 |
$6,419,277.87 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $6,075,509.52 |
$6,750,566.14 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $87,858,760.90 |
$99,781,644.28 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $80,552,215.54 |
$91,190,536.33 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $127,471,835.70 |
$146,363,853.15 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,948,811.65 |
$2,165,346.28 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,630,788.37 |
$1,811,987.08 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $1,680,899.98 |
$1,867,666.64 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | REPURPOSED EARMARKS EXEMPT | Other | $113,238.12 |
$125,820.12 |
|
South Carolina | Lexington | >= 200,000 | State | REPURPOSED EARMARKS EXEMPT | Other | $88,541.74 |
$98,379.71 |
|
South Carolina | Richland | >= 200,000 | State | REPURPOSED EARMARKS EXEMPT | Other | $247,722.17 |
$275,246.87 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $3,023,991.81 |
$3,779,989.75 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $3,456,976.35 |
$3,841,084.83 |
|
South Carolina | Lexington | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,771,240.75 |
$3,464,050.94 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,811,595.96 |
$3,514,494.96 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $9,734,314.74 |
$13,757,855.44 |
|
South Carolina | Lexington | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $9,623,834.39 |
$13,272,926.31 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $10,309,655.48 |
$16,365,374.22 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $3,351,506.25 |
$4,189,382.82 |
|
South Carolina | Lexington | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,197,190.79 |
$1,496,488.48 |
|
South Carolina | Newberry | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,531,302.96 |
$1,914,128.70 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Facilities for Pedestrians and Bicycles | $5,465,003.80 |
$7,778,524.00 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $157,157,627.43 |
||
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $2,999,798.27 |
||
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $25,142,115.17 |
||
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $1,072,000.00 |
$11,138,750.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $528,000.00 |
$5,486,250.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $1,886.00 |
||
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $90,114.00 |
||
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $6,135,588.00 |
$8,159,235.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $128,412.00 |
$170,765.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $267,207.19 |
$334,008.99 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $2,433,436.16 |
$3,041,795.19 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $760,006.83 |
$950,008.54 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $12,573.96 |
$15,717.45 |
|
South Carolina | Berkeley | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | $205,077.67 |
$256,347.09 |
|
South Carolina | Berkeley | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Facilities for Pedestrians and Bicycles | $2,831,730.40 |
$3,539,663.00 |
|
South Carolina | York | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Right of Way | $1,622,020.14 |
$2,027,525.17 |
|
South Carolina | York | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Right of Way | $111,659.86 |
$139,574.83 |
|
South Carolina | York | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $45,773,000.00 |
||
South Carolina | York | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,976,208.80 |
$4,110,261.00 |
|
South Carolina | York | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $57,870,760.79 |
||
South Carolina | York | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $7,896,667.49 |
||
South Carolina | York | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $1,680,000.00 |
$2,100,000.00 |
|
South Carolina | York | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $800,000.00 |
$3,200,000.00 |
|
South Carolina | Kershaw | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $51,112,635.00 |
$51,112,635.00 |
|
South Carolina | Kershaw | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $5,000,000.00 |
$18,710,791.36 |
|
South Carolina | Kershaw | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $7,194,296.00 |
$7,194,296.00 |
|
South Carolina | Kershaw | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,434,514.82 |
$3,916,127.58 |
|
South Carolina | Kershaw | >= 50,000 AND < 200,000 | State | PROTECT PROGRAM APPORTIONED | Bridge Replacement - No Added Capacity | $31,494,708.64 |
$31,494,708.64 |
|
South Carolina | Berkeley | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $2,575,529.43 |
$3,219,411.79 |
|
South Carolina | Berkeley | >= 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $13,424,470.57 |
$42,992,087.87 |
|
South Carolina | Berkeley | >= 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,595,828.16 |
||
South Carolina | Berkeley | >= 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Other | $80,000.00 |
||
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | 4R - Added Capacity | $13,250,000.00 |
$13,250,000.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $4,082,381.67 |
$11,900,645.09 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,263,553.33 |
$2,829,441.66 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Other | $1,607,640.00 |
$2,009,550.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $2,996,381.60 |
$4,606,477.00 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $441,631.30 |
$552,039.13 |
|
South Carolina | Richland | >= 200,000 | State | REDISTRIBUTION OF CERTAIN AUTH | Facilities for Pedestrians and Bicycles | $942,695.97 |
$1,178,369.96 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $462,266.05 |
$1,539,939.22 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | $1,634,241.34 |
||
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | $5,758,493.84 |
$9,528,259.80 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $416,000.00 |
$520,000.00 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $132,000.00 |
$165,000.00 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,590,314.67 |
$2,660,819.44 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $581,572.00 |
$726,965.00 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Construction Engineering | $596,292.95 |
$745,366.19 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Facilities for Pedestrians and Bicycles | $1,395,389.87 |
$5,564,734.35 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Other | $312,604.29 |
$390,755.36 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Preliminary Engineering | $187,673.60 |
$234,592.00 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Utilities | $2,176,918.13 |
$2,721,147.66 |
|
South Carolina | Richland | >= 200,000 | State | TRANSPORTATION ALTERNATIVES | Utilities | $465,386.91 |
$581,733.64 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | $986,557.91 |
$1,096,175.46 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | $6,668,789.25 |
$7,409,765.83 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $26,577.47 |
$29,530.52 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | Local | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $7,497.00 |
$8,330.00 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $145,925.53 |
$162,139.48 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $556,692.56 |
$618,547.29 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | Local | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | |||
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $3,763,307.44 |
$4,181,452.71 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $7,962,677.69 |
$8,868,275.16 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | $27,976,336.97 |
$31,225,794.77 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | |||
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $404,847.38 |
$449,830.42 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $2,736,627.81 |
$3,040,697.56 |
|
South Carolina | Richland | >= 200,000 | State | GRANTS SUP PLAN SECTION 117 | Facilities for Pedestrians and Bicycles | $1,010,000.00 |
$1,010,000.00 |
|
South Carolina | Richland | >= 200,000 | State | NATL INTRASTRUCTURE INVESTMENT | Facilities for Pedestrians and Bicycles | $16,656,966.50 |
$20,821,208.13 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $65,000.00 |
||
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Facilities for Pedestrians and Bicycles | $18,039,389.56 |
||
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $1,871,144.23 |
$2,338,930.29 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $3,018,051.86 |
$3,772,564.83 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $17,546,825.20 |
$21,933,531.50 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,257,317.95 |
$2,821,647.44 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,462,682.05 |
$1,828,352.56 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $2,650,821.71 |
$3,313,527.14 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $4,275,628.36 |
$5,344,535.45 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | $5,000,000.00 |
$6,250,000.00 |
|
South Carolina | Sumter | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,705,954.64 |
$2,132,443.30 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $912,138.42 |
$1,140,173.03 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Rail/Hwy Crossing | $647,967.20 |
$809,959.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Right of Way | $400,000.00 |
$500,000.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Utilities | $1,798,301.46 |
$2,247,876.82 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $15,873,836.92 |
$22,411,619.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | $1,548,071.58 |
$3,059,186.74 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $1,122,739.13 |
$1,940,632.81 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $2,310,441.60 |
$2,888,052.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $1,947,920.00 |
$3,924,900.00 |
|
South Carolina | Spartanburg | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $626,223.86 |
$782,779.83 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,598,532.49 |
$3,998,369.44 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $23,615,369.51 |
$26,239,299.45 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $720,000.00 |
$800,000.00 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Traffic Management/Engineering - HOV | $180,000.00 |
$200,000.00 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $6,114,488.12 |
$6,793,875.69 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $56,167,750.17 |
$64,061,250.49 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,170,710.33 |
$2,411,900.37 |
|
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $2,839,931.43 |
$3,155,479.37 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $19,220,353.97 |
$21,569,484.15 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - Added Capacity | $10,085,581.82 |
$11,206,202.02 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $3,979,940.72 |
$4,422,156.36 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,080,000.00 |
$1,290,000.00 |
|
South Carolina | Greenville | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | $46,934.59 |
||
South Carolina | York | >= 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | Bridge New Construction | $34,597,743.00 |
$53,672,052.86 |
|
South Carolina | York | >= 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | Construction Engineering | $6,780,000.00 |
||
South Carolina | York | >= 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | Other | $4,513,947.14 |
||
South Carolina | York | >= 200,000 | State | NAT SIG FREIGHT AND HWY PROJ | Utilities | $534,000.00 |
||
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $42,118,970.04 |
$157,373,710.58 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $15,540.89 |
$58,067.13 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $14,926,955.94 |
$16,585,506.60 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Construction Engineering | $5,507.69 |
$6,119.66 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $51,067,729.27 |
$56,741,921.41 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $18,842.77 |
$20,936.41 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Planning | $144,630.23 |
$160,700.26 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Planning | $53.37 |
$59.30 |
|
South Carolina | Dorchester | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $2,943,723.47 |
$5,837,086.69 |
|
South Carolina | Orangeburg | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,086.17 |
$2,153.75 |
|
South Carolina | Lexington | >= 200,000 | Other | CARBON REDUCTION PROGRAM | 4R - No Added Capacity | $1,838,758.43 |
$2,043,064.91 |
|
South Carolina | Richland | >= 200,000 | Other | CARBON REDUCTION PROGRAM | 4R - No Added Capacity | $2,496,146.81 |
$2,773,496.45 |
|
South Carolina | Richland | >= 200,000 | State | CARBON REDUCTION PROGRAM | 4R - No Added Capacity | $3,248,903.76 |
$3,609,893.08 |
|
South Carolina | Richland | >= 200,000 | State | HIGHWAY INFRA PRGM - COVID APP | 4R - No Added Capacity | $5,208,415.69 |
$5,208,415.69 |
|
South Carolina | Richland | >= 200,000 | Other | HIGHWAY INFRA PRGM - COVID APP | 4R - No Added Capacity | $4,001,648.25 |
$4,001,648.25 |
|
South Carolina | Lexington | >= 200,000 | Other | HIGHWAY INFRA PRGM - COVID APP | 4R - No Added Capacity | $2,947,769.11 |
$2,947,769.11 |
|
South Carolina | Lexington | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $31,915,602.98 |
$36,104,682.19 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $60,048,062.57 |
$71,569,114.95 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $43,225,556.18 |
$48,901,145.29 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | $42,570,000.00 |
$47,300,000.00 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $376,704.00 |
$418,560.00 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Other | $196,315.16 |
$218,127.96 |
|
South Carolina | Lexington | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Other | $146,980.84 |
$163,312.04 |
|
South Carolina | Lexington | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $183,726.05 |
$204,140.06 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $470,880.00 |
$523,200.00 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $245,393.95 |
$272,659.94 |
|
South Carolina | Richland | >= 200,000 | State | CARBON REDUCTION PROGRAM | 4R - No Added Capacity | $3,381,619.00 |
$3,757,354.45 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $43,463,364.13 |
$48,781,857.04 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | $62,783,592.00 |
$70,596,502.99 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | $9,540,000.00 |
$10,600,000.00 |
|
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Other | $139,444.20 |
$154,938.00 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $238,555.80 |
$265,062.00 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $441,550.25 |
$490,611.39 |
|
South Carolina | Richland | >= 200,000 | Other | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | $258,101.54 |
$286,779.48 |
|
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $182,494,878.66 |
||
South Carolina | Richland | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $190,962,852.15 |
||
South Carolina | Lexington | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $209,351,284.88 |
||
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $472,920,984.31 |
||
South Carolina | Lexington | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $2,640,000.00 |
||
South Carolina | Richland | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Rail/Hwy Crossing | $1,360,000.00 |
||
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Bridge Rehabilitation - No Added Capacity | $13,477,308.42 |
$30,501,798.33 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Construction Engineering | $3,175,642.60 |
$3,969,553.24 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Preliminary Engineering | $80,000.00 |
$755,776.25 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM -APPOR | Traffic Management/Engineering - HOV | $20,000.00 |
$25,000.00 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | PROTECT PROGRAM APPORTIONED | Bridge Rehabilitation - No Added Capacity | $17,278,870.36 |
$21,598,587.95 |
|
South Carolina | Georgetown | >= 50,000 AND < 200,000 | State | PROTECT PROGRAM APPORTIONED | Preliminary Engineering | $995,379.00 |
$1,244,223.75 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | HSIP LIMITING FLEXIBLE | Safety | $900,000.00 |
$1,000,000.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | $22,082,192.01 |
$27,702,422.32 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Other | $7,296,000.00 |
$9,120,000.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | $1,320,000.00 |
$1,650,000.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | $101,680.00 |
$127,100.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | REDISTRIBUTION OF CERTAIN AUTH | Construction Engineering | $498,217.50 |
$622,771.88 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | REDISTRIBUTION OF CERTAIN AUTH | Right of Way | $42,320.00 |
$52,900.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $12,029,470.80 |
$15,158,573.50 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $4,182,702.95 |
$5,228,378.67 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $800,000.00 |
$1,000,000.00 |
|
South Carolina | Jasper | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | $764,272.50 |
||
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECT SEC 1702 | Other | $2,505,158.48 |
$3,131,448.10 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Other | $15,052,712.51 |
$18,815,890.64 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | INTERSTATE MAINT DISC | Other | $855,000.00 |
$950,000.00 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Other | $46,588,383.12 |
$58,235,479.42 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Other | $7,677,429.20 |
$9,595,706.63 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | REDISTRIBUTION OF CERTAIN AUTH | Other | $4,034,313.19 |
$5,042,891.49 |
|
South Carolina | Aiken | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $32,977,534.74 |
$64,033,960.48 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Other | $8,588,285.19 |
$10,735,356.49 |
|
South Carolina | Beaufort | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Other | $62,845,652.67 |
$84,292,143.35 |
|
South Carolina | Richland | >= 200,000 | N/A | HIGHWAY INFRA PRGM -APPOR | 4R - Added Capacity | $4,564,771.00 |
$5,705,963.75 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | $16,110,043.56 |
$50,326,365.90 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | $1,488,264.33 |
$3,222,290.36 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Construction Engineering | $5,339,710.18 |
$6,674,637.72 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $2,700,000.00 |
$3,375,000.00 |
|
South Carolina | Richland | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | $500,000.00 |
$625,000.00 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Rail/Hwy Crossing | $195,514.40 |
$880,117.00 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | $12,900,400.00 |
$16,125,500.00 |
|
South Carolina | Richland | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | $1,422,370.42 |
$3,778,521.31 |