| RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
|---|---|---|---|---|
| Montana | 0017056 | E OF ZURICH - HARLEM (CN & CE) National Highway 1, Blaine County, Reconstruction of the roadway from reference point 416.7 to 423.9 | $24,897,606.53 | $28,756,764.32 |
| Montana | 0052160 | US 93 N - POST CREEK HILL (CN & CE) National Highway 5, Lake County, Reconstruct the roadway from reference point 37.6 to 39.4 | $47,055,296.00 | $47,055,296.00 |
| Montana | 0110078 | US 2 - CULBERTSON (CN & CE) National Highway 1, Roosevelt County, Reconstruction of the roadway from reference point 644.2 to 645.5 | $22,451,413.79 | $27,134,999.41 |
| Montana | 0143020 | WHEATLAND COUNTY LINE-EAST (CN & CE) Primary Route 14, Multiple counties, Reconstruct the roadway and structure from reference point 77.0 to 88.1 | $28,127,817.91 | $32,487,662.19 |
| Montana | 0146023 | TIMBER BRIDGES-FORSYTH AREA (IC, CN & CE) Primary Route 14, Rosebud County, Replace structures from reference point 227.2 to 258.6 | $27,141,423.90 | $31,348,376.08 |
| Montana | 0154138 | WOLF CREEK-N & S (CN & CE) Multiple routes, Lewis & Clark County, Rehabilitate the existing roadway at various locations | $48,129,332.47 | $52,594,259.18 |
| Montana | 0154168 | SIEBEN INTERCHANGE - NORTH (CN & CE) Interstate 15, Lewis & Clark County, Rehabilitation of the existing roadway from reference point 217.4 to 221.8 | $24,581,314.16 | $26,941,379.00 |
| Montana | 0513014 | LAMBERT-WEST (CN & CE) State Primary 51, Richland County, Rehabilitation of the existing roadway from reference point 38.4 to 49.3 | $26,476,663.55 | $30,580,577.00 |
| Montana | 0575047 | JCT SEC 462-EAST & WEST (CN & CE) National Highway 57, Garfield County, Reconstruct the roadway from reference point 230.1 to 239.7 | $29,495,949.70 | $34,077,856.00 |
| Montana | 0575056 | FLOWING WELLS - EAST & WEST (CN & CE) National Highway 57, Multiple counties, Reconstruct the roadway from reference point 246.8 to 253.5 | $25,241,913.34 | $28,875,437.00 |
| Montana | 0602101 | BELT-N & S-PHASE 3 (CN & CE) Multiple routes, Cascade County, Reconstruct the roadway at various locations | $23,455,814.61 | $27,107,923.39 |
| Montana | 0614026 | MALTA-SOUTH (CN & CE) National Highway 61, Phillips County, Rehabilitate/reconstruct the roadway from reference point 147.3 to 157.0 | $27,482,684.21 | $31,759,056.00 |
| Montana | 0821006 | FLATHEAD RIVER-3M NW BIG FORK (CN & CE) Primary Route 82, Flathead County, Replace the structure from reference point 5.0 to 6.6 | $35,457,890.34 | $40,953,904.32 |
| Montana | 0831046 | SALMON LAKE (CN & CE) State Primary 83, Missoula County, Reconstruction of the roadway from reference point 4.8 to 9.0 | $46,027,902.69 | $49,236,653.00 |
| Montana | 0901228 | TAFT-WEST (CN & CE) Multiple routes, Mineral County, Reconstruction of the roadway at various locations | $43,250,842.51 | $50,860,905.44 |
| Montana | 0901252 | CLARK FORK/ OLD HWY 10 BRIDGES (CN & CE) Interstate 90, Mineral County, Replace structures from reference point 65.4 to 66.4 | $25,894,239.97 | $32,367,800.00 |
| Montana | 0908177 | I-90 YELLOWSTONE R-BILLINGS (CN & CE) Multiple routes, Yellowstone County, Reconstruct the roadway and replace structures at various locations | $75,616,587.59 | $87,160,308.56 |
| Montana | 0908188 | MOSSMAIN INTCH-WEST BLGS INTCH (CN & CE) Multiple routes, Yellowstone County, Rehabilitate the roadway at various locations | $22,469,637.67 | $25,013,225.44 |
| Montana | 0945042 | BAD ROUTE INTERCHANGE - SW (CN & CE) Multiple routes/counties, Reconstruction of the existing roadway at various reference points | $30,048,003.49 | $32,932,928.00 |
| Montana | 2012015 | FAIRVIEW - WEST (CN & CE) Multiple routes, Richland County, Reconstruct the roadway on various routes | $37,919,327.73 | $43,796,867.39 |
| Montana | 2671007 | RESERVE DR-W OF WHITEFISH STG (PE, RW, IC, CN & CE) Primary Route 267, Flathead County, Reconstruction of roadway from reference point 0.2 to 0.9 | $41,676,071.10 | $44,260,881.47 |
| Montana | STWD788 | MT-200 BRIDGES LEWISTOWN AREA (CN & CE) Multiple routes, Fergus County, replace structures and associated roadwork at various locations | $53,136,727.75 | $61,398,082.09 |
| Montana | STWD790 | TIMBER BRIDGES-GLASGOW AREA (IC, CN & CE) Multiple routes/counties, Replace structures at various locations | $63,058,769.45 | $72,719,638.45 |
| Montana | STWD899 | RED LODGE AREA FLOOD REPAIRS (CN & CE) Multiple routes/counties, Reconstruct existing roadways at multiple locations | $35,776,242.34 | $41,331,601.27 |