DETAILED PROJECT LEVEL DATA PURSUANT TO 23 U.S.C. 104(g)(3)(B) WITH AN ESTIMATED TOTAL COST OF $25,000,000 OR MORE
AS OF SEPTEMBER 30, 2025
RECIPIENT PROJECT
NUMBER
COUNTY POPULATION
RANGE
OWNERSHIP PROGRAM TYPE OF
IMPROVEMENT
TOTAL
OBLIGATIONS
ESTIMATED
TOTAL COST
New York 0016273 Suffolk >= 200,000 State HSIP LIMITING FLEXIBLE 4R - Added Capacity $9,386,087.00 $10,428,987.00
New York 0016273 Suffolk >= 200,000 State HSIP LIMITING FLEXIBLE Construction Engineering $730,823.00 $812,025.00
New York 0016273 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $14,856,111.00 $18,570,139.00
New York 0016273 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,237,580.00 $2,796,975.00
New York 0016273 Suffolk >= 200,000 State NATIONAL HWY FREIGHT PGM 4R - Added Capacity $5,280,000.00 $6,600,000.00
New York 0054093 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $17,724,000.00 $32,044,321.00
New York 0054093 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,508,000.00 $5,730,938.10
New York 0054093 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Facilities for Pedestrians and Bicycles $2,784,166.00 $3,480,207.00
New York 0054093 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway $9,031,834.00 $11,289,793.00
New York 0054183 Suffolk >= 200,000 State HSIP LIMITING FLEXIBLE 4R - No Added Capacity $3,585,879.00 $3,984,310.00
New York 0054183 Suffolk >= 200,000 State HSIP LIMITING FLEXIBLE Utilities $847,540.00 $943,400.00
New York 0054183 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $26,064,382.00 $32,580,478.00
New York 0054203 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $18,391,454.00 $31,489,318.00
New York 0054203 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities $445,771.00 $557,214.00
New York 0054233 Suffolk >= 200,000 State CONGESTION AIR QUALITY 4R - No Added Capacity $3,433,132.00 $4,291,415.00
New York 0054233 Suffolk >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $1,082,936.00 $1,353,670.00
New York 0054233 Suffolk >= 200,000 State HSIP LIMITING FLEXIBLE 4R - No Added Capacity $5,518,074.00 $6,131,195.00
New York 0054233 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $31,960,911.12 $40,013,043.12
New York 0054233 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,925,904.00 $4,907,380.00
New York 0054233 Suffolk >= 200,000 State NATIONAL HWY FREIGHT PGM 4R - No Added Capacity $2,000,000.00 $2,000,000.00
New York 0054233 Suffolk >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM 4R - No Added Capacity $2,079,782.88 $2,599,728.88
New York 0054233 Suffolk >= 200,000 State REPURPOSED EARMARKS EXEMPT 4R - No Added Capacity $712,500.00 $890,625.00
New York 0054233 Suffolk >= 200,000 State REPURPOSED SPECIAL 4R - No Added Capacity $3,443,202.00 $4,304,003.00
New York 0054233 Suffolk >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity $9,008,818.00 $11,261,023.00
New York 0054233 Suffolk >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $1,759,960.00 $2,199,950.00
New York 0229483 Suffolk >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,246,510.00 $5,308,138.00
New York 0229483 Suffolk >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Safety $12,509,587.00 $17,587,984.00
New York 0229483 Suffolk >= 200,000 Other NATIONAL HWY FREIGHT PGM Safety $15,000,000.00 $16,250,000.00
New York 0229563 Nassau >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $24,512.76 $40,662.30
New York 0229563 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $22,259,811.24 $36,925,063.70
New York 0229563 Suffolk >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,355,406.20 $2,617,118.00
New York 0229563 Nassau >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,593.80 $2,882.00
New York 0534803 Nassau >= 200,000 State HIGHWAY INFRA PRGM -APPOR 4R - Maintenance Resurfacing $17,929,985.00 $22,412,482.59
New York 0534803 Nassau >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $2,579,660.00 $3,224,576.54
New York 0534803 Nassau >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM 4R - Maintenance Resurfacing $576,130.00 $720,163.00
New York 0534803 Nassau >= 200,000 State REPURPOSED EARMARKS EXEMPT 4R - Maintenance Resurfacing $137,972.93 $172,466.17
New York 0534803 Suffolk >= 200,000 State REPURPOSED EARMARKS EXEMPT 4R - Maintenance Resurfacing $4,147.07 $5,183.83
New York 0534803 Suffolk >= 200,000 State REPURPOSED SPECIAL 4R - Maintenance Resurfacing $29,971.19 $37,463.99
New York 0534803 Nassau >= 200,000 State REPURPOSED SPECIAL 4R - Maintenance Resurfacing $997,287.81 $1,246,610.01
New York 0759783 Suffolk >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $32,508,000.00 $34,218,949.00
New York 0759783 Suffolk >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Construction Engineering $2,109,000.00 $2,220,000.00
New York 0759783 Suffolk >= 200,000 Local HWY INFRA PRGM-IIJA DEMO Bridge Replacement - Added Capacity $5,000,000.00 $6,250,000.00
New York 0759783 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity   $13,850,000.00
New York 0759783 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $1,539,000.00
New York 0759783 Suffolk >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - Added Capacity   $62,195,097.24
New York 0759783 Suffolk >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $6,000,000.00
New York 0760653 Nassau >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $8,206,128.00 $27,301,000.00
New York 0760653 Nassau >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $365,056.00 $1,271,000.00
New York 0760653 Nassau >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $200,000.00 $2,461,000.00
New York 0760653 Nassau >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $23,200.00 $29,000.00
New York 0760783 Suffolk >= 200,000 Local HIGH PRIORITY PROJECT SEC 1702 Bridge Replacement - Added Capacity $4,319,520.00 $5,399,401.00
New York 0760783 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $12,603,052.00 $17,059,750.00
New York 0760783 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,088,000.00 $2,610,000.00
New York 0760783 Suffolk >= 200,000 Local REPURPOSED EARMARK SUBJ TO LIM Bridge Replacement - Added Capacity $1,146,577.00 $1,433,222.00
New York 0760783 Suffolk >= 200,000 Local REPURPOSED EARMARKS EXEMPT Bridge Replacement - Added Capacity $530,286.00 $662,858.00
New York 0760783 Suffolk >= 200,000 Local REPURPOSED SPECIAL Bridge Replacement - Added Capacity $3,479,239.00 $4,349,049.00
New York 0761353 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $22,018,614.29 $27,523,268.29
New York 0761353 Suffolk >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,233,242.41 $2,791,553.41
New York 0809253 Nassau >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $18,740,090.00 $25,437,989.00
New York 0809253 Nassau >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,731,840.00 $2,164,800.00
New York 0809253 Nassau >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Utilities $1,828.00 $2,285.00
New York 1306813 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $3,616,714.00 $4,670,893.00
New York 1306813 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $361,671.00 $452,089.00
New York 1306813 Albany >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - No Added Capacity $19,787,500.00 $24,734,377.00
New York 1306813 Albany >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $1,866,750.00 $2,333,438.00
New York 1306813 Statewide N/A State TECHNOLOGY DEPLOYMENT GRANTS T 4R - Maintenance Resurfacing $100,000.00 $125,000.00
New York 1525383 Schenectady >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $14,841,766.00 $21,487,115.00
New York 1525383 Schenectady >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,240,000.00 $4,000,000.00
New York 1721903 Albany >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $30,930,343.00 $34,417,048.00
New York 1721903 Albany >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,510,000.00 $3,900,000.00
New York 1810993 Statewide N/A State HSIP LIMITING FLEXIBLE Construction Engineering $1,120,000.00 $1,400,000.00
New York 1810993 Statewide N/A State HSIP LIMITING FLEXIBLE Safety $5,310,882.00 $5,900,980.00
New York 1810993 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Safety $6,753,856.00 $17,937,880.00
New York 1SRP013 Albany >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Transit $90,000,000.00 $690,042,700.00
New York 3057673 Tompkins >= 50,000 AND < 200,000 State HSIP LIMITING FLEXIBLE 4R - Maintenance Resurfacing $4,691,657.66 $5,212,953.27
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local HSIP LIMITING FLEXIBLE 4R - Maintenance Resurfacing $41,772.52 $46,413.91
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local HSIP LIMITING FLEXIBLE Construction Engineering $4,050.67 $4,500.74
New York 3057673 Tompkins >= 50,000 AND < 200,000 State HSIP LIMITING FLEXIBLE Construction Engineering $454,949.33 $505,499.26
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing   $60,571.88
New York 3057673 Tompkins >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing   $6,803,098.54
New York 3057673 Tompkins >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $750,817.05
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $6,684.95
New York 3057673 Tompkins >= 50,000 AND < 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing   $15,060,950.00
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing   $238,490.00
New York 3057673 Tompkins >= 50,000 AND < 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $15,289.29
New York 3057673 Tompkins >= 50,000 AND < 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $1,717,208.71
New York 3314343 Cayuga >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $19,377,113.00 $24,221,392.00
New York 3314343 Cayuga >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,000,000.00 $2,500,000.00
New York 3501903 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $189,196,827.28 $292,576,051.56
New York 3501903 Onondaga >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $2,778,877.72 $3,810,439.44
New York 3501903 Onondaga >= 200,000 Local NATIONAL HIGHWAY SYSTEM 4R - No Added Capacity $1.65 $2.00
New York 3501903 Onondaga >= 200,000 State NATIONAL HIGHWAY SYSTEM 4R - No Added Capacity $8.35 $10.00
New York 3501913 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $303,615,000.00 $384,516,116.00
New York 3501923 Onondaga >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $28,575,576.00 $45,780,589.16
New York 3501923 Onondaga >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Construction Engineering $3,040,000.00 $3,800,000.00
New York 3501923 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $42,396,177.67 $112,448,166.25
New York 3501923 Onondaga >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $232,910.33 $617,752.38
New York 3501923 Onondaga >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,240,000.00 $7,500,000.00
New York 3501923 Onondaga >= 200,000 Local NEIGHBORHOOD ACCESS EQUITY PGM Bridge Replacement - Added Capacity $56,371,277.01 $60,125,722.32
New York 3501933 Onondaga >= 200,000 State HIGHWAY INFRA PRGM -APPOR 4R - Added Capacity $71,484,291.00 $94,594,770.33
New York 3501933 Onondaga >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $7,148,700.00 $11,752,000.00
New York 3501933 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $150,916,289.03 $170,122,073.50
New York 3501933 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $15,092,300.00 $17,013,000.00
New York 3501933 Onondaga >= 200,000 State NEIGHBORHOOD ACCESS EQUITY PGM 4R - Added Capacity $22,158,660.67 $24,158,660.67
New York 3501933 Onondaga >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH 4R - Added Capacity $19,710,089.85 $24,637,612.85
New York 3501933 Onondaga >= 200,000 State REDISTRIBUTION OF CERTAIN AUTH Construction Engineering $1,199,999.95 $1,499,999.95
New York 3501933 Onondaga >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $771,200.05 $964,001.05
New York 3501943 Onondaga >= 200,000 State HIGHWAY INFRA PRGM -APPOR 4R - Added Capacity $19,080,704.00 $41,293,898.00
New York 3501943 Onondaga >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $1,936,000.00 $6,618,648.00
New York 3501943 Onondaga >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $958,438.00 $1,446,542.40
New York 3501943 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $99,401,562.00 $150,023,865.60
New York 3501943 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $8,128,000.00 $11,939,200.00
New York 3501943 Onondaga >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,032,000.00 $2,984,800.00
New York 3501943 Onondaga >= 200,000 State NEIGHBORHOOD ACCESS EQUITY PGM 4R - Added Capacity $71,480,062.32 $71,480,062.32
New York 3506413 Onondaga >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - No Added Capacity $61,559,777.03 $68,399,753.03
New York 4104903 Monroe >= 200,000 State HIGH RISK RURAL ROAD Safety $1,602,009.00 $2,175,758.00
New York 4104903 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $12,880,000.00 $26,057,411.00
New York 4104903 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,288,000.00 $2,500,000.00
New York 4390303 Monroe >= 200,000 State NAT SIG FREIGHT AND HWY PROJ 4R - No Added Capacity $22,338,536.00 $25,138,596.00
New York 4390303 Monroe >= 200,000 State NAT SIG FREIGHT AND HWY PROJ Bridge New Construction $4,202,258.00 $4,669,176.00
New York 4390303 Monroe >= 200,000 State NAT SIG FREIGHT AND HWY PROJ Bridge Rehabilitation - Added Capacity $3,074,060.00 $3,415,622.00
New York 4390303 Monroe >= 200,000 State NAT SIG FREIGHT AND HWY PROJ Bridge Rehabilitation - No Added Capacity $2,385,146.00 $2,650,162.00
New York 4390303 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $350,937.00 $1,760,227.00
New York 4390303 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge New Construction $1,272,296.00 $1,413,663.00
New York 4390303 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - No Added Capacity $2,703,779.00 $3,004,199.00
New York 4390303 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,161,000.00 $4,623,334.00
New York 4390303 Monroe >= 200,000 State NATIONAL HWY FREIGHT PGM 4R - No Added Capacity $13,482,580.00 $14,989,945.00
New York 4390933 Livingston >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $7,266,006.00 $26,773,812.00
New York 4390933 Livingston >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,755,000.00 $2,515,000.00
New York 4490163 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $6,555,600.00 $10,838,266.00
New York 4490163 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,366,000.00 $3,840,000.00
New York 4490163 Monroe >= 200,000 State NATIONAL HWY FREIGHT PGM 4R - Added Capacity $20,900,000.00 $31,205,541.00
New York 4490163 Monroe >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM Bridge Replacement - Added Capacity $711,025.00 $15,104,085.00
New York 4490163 Monroe >= 200,000 State REPURPOSED EARMARKS EXEMPT Bridge Replacement - Added Capacity $1,244,787.00 $1,244,787.00
New York 4490163 Monroe >= 200,000 State REPURPOSED SPECIAL Bridge Replacement - Added Capacity $310,930.00 $2,420,224.00
New York 4490503 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $21,862,365.00 $24,306,517.00
New York 4490503 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,187,000.00 $2,430,000.00
New York 4590043 Monroe >= 200,000 State HSIP LIMITING FLEXIBLE Safety $88,200.00 $102,129.00
New York 4590043 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $24,620,490.00 $56,239,182.00
New York 494X053 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $3,596,303.50 $14,126,487.00
New York 494X053 Orleans >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $3,596,303.50 $14,126,487.00
New York 494X053 Orleans >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $522,000.00 $652,500.00
New York 494X053 Monroe >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $522,000.00 $652,500.00
New York 5006923 Chautauqua >= 50,000 AND < 200,000 Other HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $21,095,184.42 $23,439,094.21
New York 5006923 Chautauqua >= 50,000 AND < 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $53,237,179.58 $59,152,422.79
New York 5006923 Chautauqua >= 50,000 AND < 200,000 Other HIGHWAY INFRA PRGM -APPOR Construction Engineering $2,055,602.55 $2,284,002.85
New York 5006923 Chautauqua >= 50,000 AND < 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $5,144,406.45 $5,716,007.15
New York 5006923 Chautauqua >= 50,000 AND < 200,000 Other SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $5,085,168.67 $6,423,749.97
New York 5006923 Chautauqua >= 50,000 AND < 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $12,726,280.40 $16,076,250.10
New York 5111773 Erie >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Preservation $24,866,536.00 $47,774,648.00
New York 5111773 Erie >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $3,080,000.00 $4,525,399.00
New York 5512573 Erie >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $14,027,366.13 $51,491,694.01
New York 5512573 Erie >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $4,191,694.01
New York 5512573 Erie >= 200,000 Local RECONNECTING COMMUNITIES IIJA Bridge Replacement - Added Capacity $23,640,971.00 $23,640,971.00
New York 5761603 Erie >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing   $34,231,440.00
New York 5761603 Erie >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing   $168,560.00
New York 5761603 Erie >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $13,230.00
New York 5761603 Erie >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $2,686,770.00
New York 5761603 Erie >= 200,000 Local NATL INTRASTRUCTURE INVESTMENT 4R - Maintenance Resurfacing $22,488,615.08 $22,488,615.08
New York 5761603 Erie >= 200,000 State NATL INTRASTRUCTURE INVESTMENT 4R - Maintenance Resurfacing $111,384.92 $111,384.92
New York 5761603 Erie >= 200,000 State NATL INTRASTRUCTURE INVESTMENT Construction Engineering $11,828.49 $11,828.49
New York 5761603 Erie >= 200,000 Local NATL INTRASTRUCTURE INVESTMENT Construction Engineering $2,388,171.51 $2,388,171.51
New York 5761603 Erie >= 200,000 Local REDISTRIBUTION OF TIFIA FUNDS 4R - Maintenance Resurfacing $385,693.00 $482,117.00
New York 5761603 Erie >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing   $2,517,884.00
New York 5763933 Erie >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity $30,912,000.00 $46,000,002.00
New York 5763933 Erie >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $5,520,000.00
New York 6096323 Steuben >= 50,000 AND < 200,000 N/A HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $4,134,370.00 $5,167,963.00
New York 6096323 Steuben >= 50,000 AND < 200,000 Other HSIP LIMITING FLEXIBLE Construction Engineering $153,000.00 $170,000.00
New York 6096323 Steuben >= 50,000 AND < 200,000 Other HSIP LIMITING FLEXIBLE Safety $1,261,832.00 $1,402,036.00
New York 6096323 Steuben >= 50,000 AND < 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $2,000,000.00 $31,835,058.00
New York 6096323 Steuben >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $35,200.00 $5,212,019.00
New York 6096323 Steuben >= 50,000 AND < 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $2,605,680.00 $3,257,101.00
New York 7036043 Lewis >= 5,000 AND < 50,000 State HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity   $27,025,365.00
New York 7036043 Lewis >= 5,000 AND < 50,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering   $3,000,000.00
New York 7036043 Lewis >= 5,000 AND < 50,000 State HIGHWAY INFRA PRGM -APPOR Utilities   $185,335.00
New York 7111213 Jefferson >= 50,000 AND < 200,000 State PROTECT PROGRAM APPORTIONED Bridge Replacement - No Added Capacity $25,763,102.00 $26,123,102.00
New York 7111213 Jefferson >= 50,000 AND < 200,000 State PROTECT PROGRAM APPORTIONED Construction Engineering $2,000,000.00 $2,000,000.00
New York 8002243 Orange >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $80,000.00 $100,000.00
New York 8002243 Orange >= 200,000 State CONGESTION AIR QUALITY New Construction Roadway $888,000.00 $1,110,000.00
New York 8002243 Orange >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing $8,109,425.00 $27,747,456.00
New York 8002243 Orange >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $250,000.00
New York 8002243 Orange >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $4,270,000.00 $5,337,500.00
New York 8002243 Orange >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM New Construction Roadway $86,937.00 $1,464,928.00
New York 8006843 Orange >= 200,000 State HIGH PRIORITY PROJECT SEC 1702 4R - Added Capacity $3,796,184.00 $4,745,230.00
New York 8006843 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $109,361,630.00 $137,897,409.00
New York 8018463 Ulster >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $10,151,972.00 $12,689,965.00
New York 8018463 Ulster >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $5,469,834.76 $6,837,293.76
New York 8018463 Ulster >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $4,385,081.00 $5,481,352.00
New York 8062093 Orange >= 200,000 State BRIDGE REPLAC & REHAB - DISC Bridge Rehabilitation - No Added Capacity $1,881,810.00 $2,352,263.00
New York 8062093 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $23,886,593.00 $38,953,602.00
New York 8062093 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,023,994.00 $6,424,001.00
New York 8065103 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,107,430.95 $1,384,288.80
New York 8065103 Orange >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,106,988.05 $1,383,735.20
New York 8065103 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $28,037,704.21 $35,047,131.60
New York 8065103 Orange >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Other $33,348,676.79 $41,685,847.40
New York 8101463 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $54,031,200.00 $69,511,344.60
New York 8101463 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $36,020,800.00 $46,340,896.40
New York 8101463 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,920,000.00 $2,400,000.00
New York 8101463 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,880,000.00 $3,600,000.00
New York 8127263 Putnam >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $23,051,363.00 $28,828,463.00
New York 8127263 Putnam >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,220,000.00 $3,625,000.00
New York 8239453 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $9,708,007.76 $12,135,009.70
New York 8239453 Orange >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $9,711,992.24 $12,139,990.30
New York 8239453 Orange >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,164,800.00 $1,456,000.00
New York 8239453 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,995,200.00 $3,744,000.00
New York 8392093 Westchester >= 200,000 State PROTECT PROGRAM APPORTIONED 4R - No Added Capacity $10,951,788.00 $23,972,000.00
New York 8392093 Westchester >= 200,000 State PROTECT PROGRAM APPORTIONED Construction Engineering $3,520,000.00 $4,400,000.00
New York 8729723 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $26,174,436.00 $29,082,708.00
New York 8729723 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,522,375.00 $3,913,750.00
New York 8729723 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $76,552.00 $85,058.00
New York 8755234 Chenango >= 5,000 AND < 50,000 N/A SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity $2,115,012.50 $2,718,000.00
New York 8755234 Rockland >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity $16,931,267.50 $26,669,034.00
New York 8755234 Rockland >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $2,240,000.00 $2,800,000.00
New York 8756209 Putnam >= 50,000 AND < 200,000 Local CONGESTION AIR QUALITY 4R - Maintenance Resurfacing $2,500,000.00 $3,125,000.00
New York 8756209 Putnam >= 50,000 AND < 200,000 Local REDISTRIBUTION OF CERTAIN AUTH 4R - Maintenance Resurfacing $2,966,000.00 $3,707,500.00
New York 8756209 Putnam >= 50,000 AND < 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing $14,239,823.00 $17,799,779.00
New York 8756209 Putnam >= 50,000 AND < 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $2,640,000.00 $3,300,000.00
New York 8808623 Ulster >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $59,523,731.00 $59,523,731.00
New York 8808623 Ulster >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $10,813,670.00 $10,813,670.00
New York 8813273 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $18,138,903.00 $22,705,307.00
New York 8813273 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,307,944.00 $5,384,930.00
New York 8813553 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,445,884.00 $2,557,355.00
New York 8813553 Orange >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $12,023,722.00 $25,681,225.00
New York 8813553 Orange >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM Construction Engineering $72,670.00 $90,838.00
New York 8813553 Orange >= 200,000 State REPURPOSED EARMARK SUBJ TO LIM Other $367,704.00 $459,631.00
New York 8813553 Orange >= 200,000 State REPURPOSED SPECIAL Construction Engineering $189,868.00 $237,336.00
New York 8813553 Orange >= 200,000 State REPURPOSED SPECIAL Other $140,845.00 $176,057.00
New York 8813683 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $24,864,054.00 $31,251,090.00
New York 8813683 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $5,046,063.50 $6,307,579.50
New York 8813683 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $5,046,063.50 $6,307,579.50
New York 8813683 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $544,687.00 $680,859.45
New York 8813683 Westchester >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $8,457,715.00 $10,956,970.55
New York 8814073 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,160,000.00 $2,400,000.00
New York 8814073 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway $23,397,955.98 $25,997,728.98
New York 8814073 Westchester >= 200,000 State REPURPOSED SPECIAL New Construction Roadway $1,406.03 $1,758.03
New York 8814893 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $7,510,500.00 $32,377,766.00
New York 8815293 Statewide N/A State OP MOT VEH/INTOX-TEA21 Safety $205,950.51 $257,438.51
New York 8815293 Statewide N/A State REDISTRIBUTION OF CERTAIN AUTH Construction Engineering $3,140,043.74 $3,925,055.74
New York 8815293 Statewide N/A State REDISTRIBUTION OF CERTAIN AUTH Safety $4,523,460.31 $5,654,326.31
New York 8815293 Statewide N/A State SURFACE TRANSP BLOCK GRNT PRGM Safety $17,029,085.44 $21,286,357.44
New York 8815563 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Restoration & Rehabilitation   $36,623,550.00
New York 8815563 Westchester >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering   $2,500,000.00
New York 8LHT113 Westchester >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $3,156,735.88 $3,945,919.84
New York 8LHT113 Rockland >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $1,577,184.12 $1,971,480.16
New York 8LHT113 Rockland >= 200,000 State CONGESTION AIR QUALITY Transit $33,853,578.23 $62,569,800.07
New York 8LHT113 Westchester >= 200,000 State CONGESTION AIR QUALITY Transit $18,472,047.77 $34,265,550.93
New York 8LHT113 Rockland >= 200,000 Local HSIP LIMITING FLEXIBLE Construction Engineering $171,633.70 $190,704.10
New York 8LHT113 Rockland >= 200,000 State HSIP LIMITING FLEXIBLE Construction Engineering $343,679.72 $381,866.36
New York 8LHT113 Westchester >= 200,000 State HSIP LIMITING FLEXIBLE Construction Engineering $515,519.58 $572,799.54
New York 8LHT113 Rockland >= 200,000 Local HSIP LIMITING FLEXIBLE Safety $482,348.65 $535,943.00
New York 8LHT113 Rockland >= 200,000 State HSIP LIMITING FLEXIBLE Safety $965,856.14 $1,073,173.60
New York 8LHT113 Westchester >= 200,000 State HSIP LIMITING FLEXIBLE Safety $1,448,784.21 $1,609,760.40
New York 8LHT113 Rockland >= 200,000 Local NATL INTRASTRUCTURE INVESTMENT Construction Engineering $22,417.92 $28,022.40
New York 8LHT113 Westchester >= 200,000 State NATL INTRASTRUCTURE INVESTMENT Construction Engineering $134,386.56 $167,983.20
New York 8LHT113 Rockland >= 200,000 State NATL INTRASTRUCTURE INVESTMENT Construction Engineering $44,795.52 $55,994.40
New York 8LHT113 Westchester >= 200,000 State NATL INTRASTRUCTURE INVESTMENT Transit $3,194,836.61 $3,993,545.76
New York 8LHT113 Rockland >= 200,000 State NATL INTRASTRUCTURE INVESTMENT Transit $6,580,047.23 $8,225,059.04
New York 8LHT113 Rockland >= 200,000 Local NATL INTRASTRUCTURE INVESTMENT Transit $23,516.16 $29,395.20
New York 8TZ1003 Statewide N/A Other NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity   $3,216,685,500.00
New York 9013393 Sullivan >= 50,000 AND < 200,000 State HSIP LIMITING FLEXIBLE Construction Engineering $886,785.00 $886,785.00
New York 9013393 Sullivan >= 50,000 AND < 200,000 State HSIP LIMITING FLEXIBLE Safety $1,992,865.23 $2,310,268.23
New York 9013393 Sullivan >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $8,122,470.00 $10,153,088.00
New York 9013393 Sullivan >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,386,640.00 $1,733,300.00
New York 9013393 Sullivan >= 50,000 AND < 200,000 State NATIONAL HWY FREIGHT PGM 4R - No Added Capacity $18,013,486.00 $20,025,474.00
New York 9013393 Sullivan >= 50,000 AND < 200,000 State NATIONAL HWY FREIGHT PGM Construction Engineering $460,800.00 $576,000.00
New York 9038263 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,629,889.00 $3,287,362.00
New York 9038263 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Facilities for Pedestrians and Bicycles $20,377,741.00 $25,472,178.00
New York 9067823 Tioga >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Restoration & Rehabilitation $14,116,662.89 $20,519,441.65
New York 9067823 Tioga >= 5,000 AND < 50,000 Other NATIONAL HIGHWAY PERF PROGRAM 4R - Restoration & Rehabilitation $2,082,759.78 $3,027,420.02
New York 9067823 Tioga >= 5,000 AND < 50,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,673,594.00 $2,294,145.48
New York 9067823 Tioga >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,673,594.00 $2,294,145.52
New York 9067823 Tioga >= 5,000 AND < 50,000 State REPURPOSED EARMARK SUBJ TO LIM 4R - Restoration & Rehabilitation $50,787.52 $63,484.52
New York 9067823 Tioga >= 5,000 AND < 50,000 Other REPURPOSED EARMARK SUBJ TO LIM 4R - Restoration & Rehabilitation $50,787.48 $63,484.48
New York 9067823 Tioga >= 5,000 AND < 50,000 Other REPURPOSED SPECIAL 4R - Restoration & Rehabilitation $144,885.48 $181,106.96
New York 9067823 Tioga >= 5,000 AND < 50,000 State REPURPOSED SPECIAL 4R - Restoration & Rehabilitation $144,885.52 $181,107.04
New York 9067823 Tioga >= 5,000 AND < 50,000 Other SURFACE TRANSP BLOCK GRNT PRGM 4R - Restoration & Rehabilitation $8,160,702.69 $11,675,361.21
New York 9067823 Tioga >= 5,000 AND < 50,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Restoration & Rehabilitation $8,160,702.64 $11,675,361.12
New York 9358223 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $42,634,530.00 $47,371,702.00
New York 9358223 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,491,481.00 $4,990,534.00
New York 9358433 Otsego >= 50,000 AND < 200,000 State HIGHWAY INFRA PRGM -APPOR 4R - Restoration & Rehabilitation $3,853,694.92 $4,281,884.14
New York 9358433 Otsego >= 50,000 AND < 200,000 Other HIGHWAY INFRA PRGM -APPOR 4R - Restoration & Rehabilitation $7,705,078.08 $8,561,199.68
New York 9358433 Otsego >= 50,000 AND < 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $89,662.92 $99,625.58
New York 9358433 Otsego >= 50,000 AND < 200,000 Other HIGHWAY INFRA PRGM -APPOR Construction Engineering $179,272.08 $199,191.42
New York 9358433 Otsego >= 50,000 AND < 200,000 Other NATIONAL HIGHWAY PERF PROGRAM 4R - Restoration & Rehabilitation $11,332,200.00 $13,691,223.40
New York 9358433 Otsego >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Restoration & Rehabilitation $5,667,800.00 $6,847,665.60
New York 9358433 Otsego >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,000,200.00 $1,111,333.56
New York 9358433 Otsego >= 50,000 AND < 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,999,800.00 $2,222,000.44
New York 9500804 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $12,155,883.00 $15,194,854.00
New York 9500804 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge New Construction $11,289,071.00 $152,049,009.00
New York 9501243 Broome >= 50,000 AND < 200,000 State INTERSTATE MAINTENANCE 4R - Maintenance Resurfacing $1,542,976.76 $1,714,419.47
New York 9501243 Broome >= 50,000 AND < 200,000 Other INTERSTATE MAINTENANCE 4R - Maintenance Resurfacing $3,085,182.10 $3,427,981.82
New York 9501243 Cortland >= 5,000 AND < 50,000 State INTERSTATE MAINTENANCE 4R - Maintenance Resurfacing $77.14 $85.71
New York 9501243 Cortland >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $280.26 $311.41
New York 9501243 Broome >= 50,000 AND < 200,000 Other NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $11,206,919.18 $12,452,133.30
New York 9501243 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Maintenance Resurfacing $5,604,860.56 $6,227,623.29
New York 9501243 Broome >= 50,000 AND < 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $617,801.64 $686,446.27
New York 9501243 Broome >= 50,000 AND < 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,235,294.46 $1,372,549.40
New York 9501243 Cortland >= 5,000 AND < 50,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $30.90 $34.33
New York X021523 Kings >= 200,000 N/A CONGESTION AIR QUALITY Bridge Rehabilitation - No Added Capacity $15,140,000.00 $18,925,000.00
New York X021523 Kings >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $138,699,866.33 $251,374,833.33
New York X021523 Kings >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - No Added Capacity $10,400,000.00 $13,000,000.00
New York X021733 Kings >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $73,800,000.00 $238,383,771.00
New York X021733 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity   $78,696,440.00
New York X051593 Queens >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $69,035,973.32 $86,331,251.30
New York X051593 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $62,208,685.68 $77,794,196.70
New York X051593 Queens >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,189,301.28 $2,736,626.60
New York X051593 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,875,498.72 $2,344,373.40
New York X051603 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $1,725,904.72 $122,120,577.05
New York X051603 Queens >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $3,452,327.28 $244,277,793.95
New York X110263 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $662,480.00 $828,100.00
New York X110263 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $32,339,268.00 $40,424,086.75
New York X110263 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Other $4,240,000.00 $5,300,000.00
New York X110263 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $4,042,965.00 $5,053,707.00
New York X110263 Bronx >= 200,000 State REDISTRIBUTION OF TIFIA FUNDS Construction Engineering $928,800.00 $1,161,000.00
New York X110263 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $7,200,000.00 $9,232,200.00
New York X110263 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $14,490,252.00 $18,112,815.00
New York X110283 Bronx >= 200,000 State CONGESTION AIR QUALITY Bridge Replacement - Added Capacity $17,564,562.00 $21,964,907.00
New York X110283 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $108,764,172.00 $135,982,748.00
New York X110283 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $7,640,000.00 $9,550,000.00
New York X110293 Bronx >= 200,000 State HIGH RISK RURAL ROAD Bridge Replacement - Added Capacity $18,982,147.00 $21,341,379.00
New York X110293 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $61,057,428.00 $76,336,020.00
New York X110293 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $7,320,000.00 $9,150,000.00
New York X110293 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - Added Capacity $151,237,688.00 $460,281,683.00
New York X228693 Queens >= 200,000 State HSIP LIMITING FLEXIBLE Other $11,300,124.52 $12,555,694.35
New York X228693 Queens >= 200,000 Local HSIP LIMITING FLEXIBLE Other $152,317.48 $169,241.65
New York X228693 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $18,457,546.66 $24,363,326.03
New York X228693 Queens >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM 4R - No Added Capacity $248,794.34 $328,399.97
New York X228693 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,223,076.00 $5,278,845.00
New York X228693 Queens >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $56,924.00 $71,155.00
New York X228693 Queens >= 200,000 State NATIONAL HWY FREIGHT PGM Construction Engineering $986,700.00 $1,096,334.21
New York X228693 Queens >= 200,000 Local NATIONAL HWY FREIGHT PGM Construction Engineering $13,300.00 $14,777.79
New York X228693 Queens >= 200,000 State NATIONAL HWY FREIGHT PGM New Construction Roadway $8,880,300.00 $9,867,000.00
New York X228693 Queens >= 200,000 Local NATIONAL HWY FREIGHT PGM New Construction Roadway $119,700.00 $133,000.00
New York X228693 Queens >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - Added Capacity $30,072,481.00 $38,300,604.00
New York X228693 Queens >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $2,111,112.00 $2,638,890.00
New York X720313 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $26,369,150.00 $35,279,112.00
New York X720313 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $6,440,800.00 $8,051,000.00
New York X720313 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway $1,511,758.14 $1,889,697.68
New York X720313 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM New Construction Roadway $756,105.86 $945,132.32
New York X720313 Bronx >= 200,000 State REDISTRIBUTION OF TIFIA FUNDS 4R - No Added Capacity $720,000.00 $900,000.00
New York X720313 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Maintenance Resurfacing $166,569.00 $208,211.00
New York X720313 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - No Added Capacity $4,997,208.00 $9,092,173.00
New York X720313 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $333,148.00 $416,435.00
New York X720313 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Safety $2,332,032.00 $2,915,040.00
New York X720393 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $39,039,659.00 $43,377,400.89
New York X720393 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $7,427,500.00 $8,252,778.95
New York X720393 Bronx >= 200,000 Other HSIP LIMITING FLEXIBLE Bridge Replacement - Added Capacity $4,614,919.00 $5,127,688.00
New York X720393 Bronx >= 200,000 Other HSIP LIMITING FLEXIBLE Construction Engineering $1,003,545.00 $1,115,050.00
New York X720393 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $50,000.00 $838,636.00
New York X720393 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $49,334,740.00 $56,938,896.00
New York X720393 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $7,880,920.00 $8,756,578.00
New York X720393 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $578,000.00 $642,223.00
New York X720393 Bronx >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - Added Capacity $5,315,550.00 $6,644,438.00
New York X720393 Bronx >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $180,000.00 $225,000.00
New York X720453 Bronx >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Bridge Replacement - No Added Capacity $68,228,488.00 $71,819,461.00
New York X720453 Bronx >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Construction Engineering $4,896,512.00 $13,997,071.00
New York X726993 Bronx >= 200,000 Other BRIDGE PROGRAM - 85% ON/OFF Bridge Rehabilitation - Added Capacity $16,918,000.00 $21,147,501.00
New York X726993 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $18,432,697.00 $50,861,871.00
New York X726993 Bronx >= 200,000 Other NATIONAL HWY FREIGHT PGM Bridge Rehabilitation - Added Capacity $9,999,999.00 $12,499,999.00
New York X727113 Bronx >= 200,000 State CARBON REDUCTION PROGRAM Construction Engineering $1,354,400.00 $1,693,000.00
New York X727113 Bronx >= 200,000 State CARBON REDUCTION PROGRAM Other $120,000.00 $150,000.00
New York X727113 Bronx >= 200,000 State CARBON REDUCTION PROGRAM Traffic Management/Engineering - HOV $9,128,000.00 $11,410,000.00
New York X727113 New York >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $3,621.80 $4,527.25
New York X727113 Bronx >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $2,065,978.20 $2,582,472.75
New York X727113 New York >= 200,000 State NATIONAL HWY FREIGHT PGM Traffic Management/Engineering - HOV $24,500.84 $24,500.84
New York X727113 Bronx >= 200,000 State NATIONAL HWY FREIGHT PGM Traffic Management/Engineering - HOV $13,975,499.16 $13,975,499.16
New York X727163 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $2,921,201.80 $3,651,502.30
New York X727163 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $7,269,669.20 $9,087,086.70
New York X727163 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $25,725,058.00 $32,156,323.00
New York X727163 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,671,148.00 $5,838,935.00
New York X727163 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $1,325,010.61 $1,656,263.61
New York X729773 Kings >= 200,000 State CONGESTION AIR QUALITY Bridge Replacement - Added Capacity $18,500,000.00 $24,654,354.00
New York X729773 Kings >= 200,000 State HSIP LIMITING FLEXIBLE Bridge Replacement - Added Capacity $15,600,000.00 $15,600,000.00
New York X729773 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $283,709,903.00 $283,953,903.00
New York X729773 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $33,572,103.00 $33,572,103.00
New York X731273 Bronx >= 200,000 State CONGESTION AIR QUALITY 4R - Added Capacity $9,163,544.50 $14,323,467.00
New York X731273 Bronx >= 200,000 Local CONGESTION AIR QUALITY 4R - Added Capacity $9,163,544.50 $14,323,467.00
New York X731273 Bronx >= 200,000 Local CONGESTION AIR QUALITY Construction Engineering $1,244,000.00 $1,555,000.00
New York X731273 Bronx >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $1,244,000.00 $1,555,000.00
New York X731273 Bronx >= 200,000 Local HIGH PRIORITY PROJECT SEC 1702 4R - Added Capacity $1,439,840.00 $1,799,801.00
New York X731273 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $891,962.80 $1,114,953.50
New York X731273 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,740,037.20 $2,175,046.50
New York X731273 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM 4R - Added Capacity $4,942,520.00 $6,178,151.00
New York X731453 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $12,240,000.00 $82,000,000.00
New York X731453 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $6,120,000.00 $41,000,000.00
New York X731453 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $12,240,000.00 $82,000,000.00
New York X731453 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $829,370.40 $1,600,713.20
New York X731453 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $829,370.40 $1,600,713.20
New York X731453 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $414,685.20 $800,356.60
New York X731493 Bronx >= 200,000 State CONGESTION AIR QUALITY 4R - Added Capacity $3,349,902.00 $4,187,378.00
New York X731493 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM 4R - Added Capacity $32,736,391.00 $40,920,489.00
New York X731493 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $5,130,532.67 $6,413,166.67
New York X731513 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $40,212,000.00 $44,691,428.00
New York X731513 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $6,184,800.00 $7,731,000.00
New York X731523 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $29,080,000.00 $36,350,000.00
New York X731523 Queens >= 200,000 State NATIONAL HWY FREIGHT PGM Bridge Rehabilitation - No Added Capacity $20,000,000.00 $20,000,000.00
New York X731523 Queens >= 200,000 N/A SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - No Added Capacity $59,827,200.00 $143,884,000.00
New York X731613 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $21,569,881.71 $23,987,860.69
New York X731613 Kings >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $4,788,976.29 $5,325,826.31
New York X731613 Kings >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $430,557.30 $579,351.50
New York X731613 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,936,442.70 $2,605,648.50
New York X731633 Bronx >= 200,000 Other HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $10,612,400.06 $13,265,500.20
New York X731633 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Replacement - Added Capacity $84,822,852.16 $106,028,566.08
New York X731633 Bronx >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $26,450,660.15 $50,451,875.27
New York X731633 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $211,414,989.20 $403,252,040.08
New York X731653 Bronx >= 200,000 State HIGHWAY INFRA PRGM -APPOR Construction Engineering $7,190,000.00 $8,987,500.00
New York X731653 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,010,000.00 $2,512,500.00
New York X731653 Bronx >= 200,000 State NATIONAL HWY FREIGHT PGM 4R - Added Capacity $40,000,000.00 $446,664,897.00
New York X731683 Richmond >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $400,000.00 $3,835,000.00
New York X731683 Richmond >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Facilities for Pedestrians and Bicycles $10,676,646.00 $28,967,804.00
New York X731703 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $28,765,215.00 $37,081,509.00
New York X731703 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $4,960,000.00 $6,200,000.00
New York X731703 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Other $320,000.00 $400,000.00
New York X731713 Statewide N/A State NATIONAL HWY FREIGHT PGM Bridge Preservation $17,885,493.87 $68,250,000.00
New York X731733 Kings >= 200,000 State HIGHWAY INFRA PRGM -APPOR Bridge Preservation $2,000,000.00 $2,500,000.00
New York X731733 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $62,295,236.00 $169,353,493.00
New York X731733 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $10,640,800.00 $13,301,000.00
New York X735563 Queens >= 200,000 N/A BRIDGE PROGRAM - 85% ON/OFF Bridge Replacement - Added Capacity $10,283,326.00 $159,254,883.00
New York X735563 Queens >= 200,000 N/A NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $17,731,628.00 $22,164,536.00
New York X735803 Queens >= 200,000 State BRIDGE PROGRAM - 85% ON/OFF Bridge Rehabilitation - No Added Capacity $201,722.25 $201,722.25
New York X735803 Queens >= 200,000 Other BRIDGE PROGRAM - 85% ON/OFF Bridge Rehabilitation - No Added Capacity $67,240.75 $67,240.75
New York X735803 Queens >= 200,000 State BRIDGE REP & REHAB-20% ON/OFF Bridge Rehabilitation - No Added Capacity $239,879.25 $239,879.25
New York X735803 Queens >= 200,000 Other BRIDGE REP & REHAB-20% ON/OFF Bridge Rehabilitation - No Added Capacity $79,959.75 $79,959.75
New York X735803 Queens >= 200,000 State BRIDGE REP & REHAB-65% ON SYS Bridge Rehabilitation - No Added Capacity $162,288.75 $162,288.75
New York X735803 Queens >= 200,000 Other BRIDGE REP & REHAB-65% ON SYS Bridge Rehabilitation - No Added Capacity $54,096.25 $54,096.25
New York X735803 Queens >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $19,580,087.69 $19,584,585.44
New York X735803 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $106,942,214.30 $108,810,266.55
New York X735803 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $6,450,000.00 $6,450,000.00
New York X735803 Queens >= 200,000 Other NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $2,150,000.00 $2,150,000.00
New York X735803 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - Added Capacity   $14,505.00
New York X735843 Queens >= 200,000 State HIGHWAY INFRA PRGM - COVID APP Other $399,972,319.00 $499,965,400.00
New York X735843 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $7,514,400.00 $9,393,000.00
New York X735843 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $116,998,712.28 $306,223,684.00
New York X757003 Statewide N/A N/A BRIDGE PROGRAM - 85% ON/OFF Bridge Replacement - No Added Capacity $188,498,435.00 $502,253,712.00
New York X757003 Statewide N/A N/A BRIDGE PROGRAM - 85% ON/OFF Construction Engineering $2,349,461.00 $2,936,826.00
New York X757003 Statewide N/A N/A BRIDGE PROGRAM - 85% ON/OFF Preliminary Engineering $1,061,586.00 $1,326,983.00
New York X757003 Statewide N/A N/A EXTENSION OF ALLOC PROGRAMS Bridge Replacement - No Added Capacity $1,331,443.00 $1,664,304.00
New York X757003 Statewide N/A N/A HIGH PRIORITY PROJECT SEC 1702 Bridge Replacement - No Added Capacity $6,096,249.00 $7,620,312.00
New York X757003 Statewide N/A N/A NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - No Added Capacity $8,969,792.00 $11,212,242.00
New York X757003 Statewide N/A N/A NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $114,400.00 $143,000.00
New York X757003 Statewide N/A N/A NATIONAL HIGHWAY SYSTEM Bridge Replacement - No Added Capacity $9,120,492.00 $11,400,615.00
New York X757533 New York >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $88,720,000.00 $110,900,000.00
New York X758863 New York >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $21,400,000.00 $30,353,000.00
New York X758923 Queens >= 200,000 Local CONGESTION AIR QUALITY Bridge Rehabilitation - No Added Capacity $1,498,000.00 $1,872,500.00
New York X758923 Queens >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $51,835,335.00 $68,394,169.00
New York X759193 New York >= 200,000 Local EMERGENCY RELIEF 4R - No Added Capacity $12,000,000.00 $95,000,000.00
New York X759213 New York >= 200,000 Local EMERGENCY RELIEF 4R - Added Capacity $8,029,696.98 $27,429,696.98
New York X759846 New York >= 200,000 N/A FTA TRANSFER AGREEMENT 9/11 4R - No Added Capacity $8,147,000.00 $8,147,000.00
New York X759846 New York >= 200,000 N/A FTA TRANSFER AGREEMENT 9/11 Construction Engineering $26,634,817.00 $26,634,817.00
New York X759846 New York >= 200,000 N/A FTA TRANSFER AGREEMENT 9/11 Preliminary Engineering $4,000,000.00 $4,000,000.00
New York X761243 Bronx >= 200,000 Local HSIP LIMITING FLEXIBLE 4R - No Added Capacity $18,016,401.00 $60,016,863.00
New York X761243 Bronx >= 200,000 Local REPURPOSED EARMARK SUBJ TO LIM 4R - No Added Capacity $394,322.00 $492,903.00
New York X761243 Bronx >= 200,000 Local REPURPOSED SPECIAL 4R - No Added Capacity $45,678.00 $57,098.00
New York X761263 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $11,473,000.00 $97,383,250.00
New York X761263 Kings >= 200,000 Local NATL INTRASTRUCTURE INVESTMENT Bridge Rehabilitation - Added Capacity $25,000,000.00 $31,250,000.00
New York X761263 Kings >= 200,000 State REPURPOSED SPECIAL Bridge Rehabilitation - Added Capacity $12,495,502.00 $15,619,377.00
New York X761263 Kings >= 200,000 Local REPURPOSED SPECIAL Bridge Rehabilitation - Added Capacity $11,830,572.00 $14,788,216.00
New York X761264 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $39,200,000.00 $41,263,158.00
New York X762074 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV $600,000.00 $750,000.00
New York X762074 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV $600,000.00 $750,000.00
New York X762074 New York >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV $600,000.00 $750,000.00
New York X762074 Richmond >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV $600,000.00 $750,000.00
New York X762074 Queens >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Traffic Management/Engineering - HOV $600,000.00 $750,000.00
New York X762074 Queens >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV $6,650,000.00 $11,761,283.00
New York X762074 Kings >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV $6,650,000.00 $11,761,283.00
New York X762074 Bronx >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV $6,650,000.00 $11,761,283.00
New York X762074 New York >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV $6,650,000.00 $11,761,283.00
New York X762074 Richmond >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Traffic Management/Engineering - HOV $6,650,000.00 $11,761,283.00
New York X764203 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $9,622,921.98 $15,266,775.60
New York X764203 New York >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $3,207,640.66 $5,088,925.20
New York X764203 New York >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $3,207,640.66 $5,088,925.20
New York X764263 Kings >= 200,000 Local HIGHWAY INFRA PRGM -APPOR Bridge Rehabilitation - Added Capacity $120,640,800.00 $179,296,937.19
New York X764263 New York >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $13,431,200.00 $16,789,000.00
New York X764273 Niagara >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $22,813,144.00 $28,516,430.00
New York X772433 Bronx >= 200,000 Local BRIDGE PROGRAM - 15% OFF SYST Bridge Replacement - No Added Capacity $3,075,427.00 $3,844,286.00
New York X772433 Bronx >= 200,000 Local BRIDGE REP & REHAB-15% OFF SYS Bridge Replacement - No Added Capacity $156,884.00 $196,105.00
New York X772433 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - No Added Capacity $136,767,689.00 $204,662,612.00
New York X772433 Bronx >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Replacement - No Added Capacity $8,897,916.00 $11,122,395.00
New York X772483 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $28,792,325.00 $35,990,408.00
New York X772483 Kings >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - No Added Capacity $2,510,760.00 $31,501,451.00
New York X772513 New York >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $53,333,600.00 $82,758,144.00
New York X772563 Bronx >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - No Added Capacity $33,000,000.00 $43,085,000.00
New York X772563 Bronx >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - No Added Capacity $1,859,000.00 $2,323,750.00
New York X772653 Bronx >= 200,000 Local CONGESTION AIR QUALITY Transit $25,000,000.00 $161,250,000.00
New York X772653 Bronx >= 200,000 Local NAT SIG FREIGHT AND HWY PROJ Transit $109,125,000.00 $136,406,250.00
New York X772653 Bronx >= 200,000 Local NATIONAL HWY FREIGHT PGM Transit   $102,343,750.00
New York X772843 Kings >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $18,006,894.93 $35,683,432.93
New York X772843 New York >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Bridge Rehabilitation - Added Capacity $18,006,894.93 $35,683,432.93
New York X773093 Kings >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $919,000.00
New York X773093 Kings >= 200,000 Local SURFACE TRANSP BLOCK GRNT PRGM Facilities for Pedestrians and Bicycles $608.00 $30,029,284.00
New York X773113 Kings >= 200,000 Local HIGH RISK RURAL ROAD Facilities for Pedestrians and Bicycles $8,866,800.00 $42,043,195.00
New York X773113 Kings >= 200,000 Local REPURPOSED SPECIAL Facilities for Pedestrians and Bicycles $5,007,375.00 $6,259,219.00
New York X773113 Kings >= 200,000 Local TRANSPORTATION ALTERNATIVES Facilities for Pedestrians and Bicycles $1,900,000.00 $2,375,000.00
New York X773363 Kings >= 200,000 Local CONGESTION AIR QUALITY Facilities for Pedestrians and Bicycles $2,800,000.00 $3,500,000.00
New York X773363 Kings >= 200,000 Local HSIP LIMITING FLEXIBLE Facilities for Pedestrians and Bicycles $6,867,000.00 $31,850,000.00
New York X773363 Kings >= 200,000 Local TRANSPORTATION ALTERNATIVES Facilities for Pedestrians and Bicycles $5,000,000.00 $6,250,000.00
New York X774073 Kings >= 200,000 Local NATIONAL HIGHWAY PERF PROGRAM Bridge Replacement - Added Capacity $45,284,117.00 $50,802,516.00
New York X777013 Queens >= 200,000 Local EMERGENCY RELIEF Bridge Rehabilitation - No Added Capacity $22,600,000.00 $28,250,000.00
New York X777044 Statewide N/A Local EMERGENCY RELIEF Bridge Rehabilitation - Added Capacity $41,673,232.00 $52,091,540.00
New York X777114 New York >= 200,000 Local EMERGENCY RELIEF Safety $53,418,887.00 $66,773,609.00
New York X777503 New York >= 200,000 State EMERGENCY RELIEF Other $31,904,342.55 $66,725,903.53
New York X777503 New York >= 200,000 Other EMERGENCY RELIEF Other $7,835,519.50 $9,794,399.50
New York X777503 New York >= 200,000 Other EMERGENCY RELIEF Other $14,298,166.45 $20,990,038.47
New York X777503 New York >= 200,000 State EMERGENCY RELIEF Other $7,835,519.50 $9,794,399.50
New York X806593 Queens >= 200,000 Local CONGESTION AIR QUALITY Construction Engineering $349,109.52 $436,386.90
New York X806593 Queens >= 200,000 State CONGESTION AIR QUALITY Construction Engineering $2,043,690.48 $2,554,613.10
New York X806593 Queens >= 200,000 State CONGESTION AIR QUALITY Traffic Management/Engineering - HOV $16,802,538.48 $21,003,173.10
New York X806593 Queens >= 200,000 Local CONGESTION AIR QUALITY Traffic Management/Engineering - HOV $2,870,261.52 $3,587,826.90
New York XM16563 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Bridge Rehabilitation - Added Capacity $17,111,761.75 $21,389,702.75
New York XM16563 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $6,581.00 $8,227.00
New York XM16563 Statewide N/A State REPURPOSED EARMARKS EXEMPT Bridge Rehabilitation - Added Capacity $4,000,000.00 $5,000,000.00
New York XM16563 Statewide N/A State REPURPOSED EARMARKS EXEMPT Construction Engineering $440,000.00 $550,000.00
New York XM17033 New York >= 200,000 State EMERGENCY RELIEF Construction Engineering $271,656.00 $3,773,000.00
New York XM17033 New York >= 200,000 State EMERGENCY RELIEF Safety $1,611,000.00 $31,550,007.00
New York XM17033 New York >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Safety $2,240,000.00 $2,800,000.00
New York XM21603 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $617.98 $289,847.49
New York XM21603 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $617.98 $289,847.49
New York XM21603 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $617.98 $289,847.49
New York XM21603 New York >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $617.98 $289,847.49
New York XM21603 Richmond >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Other $617.96 $289,847.45
New York XM21603 Kings >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $414,560.00 $577,200.00
New York XM21603 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $414,560.00 $577,200.00
New York XM21603 Richmond >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $414,560.00 $577,200.00
New York XM21603 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $414,560.00 $577,200.00
New York XM21603 New York >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering $414,560.00 $577,200.00
New York XM21603 New York >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $3,395,633.40 $4,244,541.80
New York XM21603 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $3,395,633.40 $4,244,541.80
New York XM21603 Richmond >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $3,395,633.40 $4,244,541.80
New York XM21603 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $3,395,633.40 $4,244,541.80
New York XM21603 Kings >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Other $3,395,633.40 $4,244,541.80
New York XM22043 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $3,251,065.25 $8,147,056.25
New York XM22043 Richmond >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $3,251,065.25 $8,147,056.25
New York XM22043 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $3,251,065.25 $8,147,056.25
New York XM22043 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $3,251,065.25 $8,147,056.25
New York XM22043 Richmond >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,440,000.00 $2,786,250.00
New York XM22043 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,440,000.00 $2,786,250.00
New York XM22043 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,440,000.00 $2,786,250.00
New York XM22043 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $1,440,000.00 $2,786,250.00
New York XM24033 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $4,840,771.00 $6,093,986.00
New York XM24033 Richmond >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $4,840,771.00 $6,093,986.00
New York XM24033 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $4,840,771.00 $6,093,986.00
New York XM24033 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Bridge Preservation $4,840,771.00 $6,093,986.00
New York XM24033 Bronx >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $772,500.00 $965,625.00
New York XM24033 Queens >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $772,500.00 $965,625.00
New York XM24033 Kings >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $772,500.00 $965,625.00
New York XM24033 Richmond >= 200,000 State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $772,500.00 $965,625.00
New York XM24033 Richmond >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $296,875.00
New York XM24033 Bronx >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $296,875.00
New York XM24033 Kings >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $296,875.00
New York XM24033 Queens >= 200,000 State SURFACE TRANSP BLOCK GRNT PRGM Construction Engineering   $296,875.00
New York XM24603 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Construction Engineering $3,200,000.00 $4,000,000.00
New York XM24603 Statewide N/A State NATIONAL HIGHWAY PERF PROGRAM Other $29,377,959.00 $36,722,449.00