California 0001002 IN LONG BEACH, ON STATE RTE 47 AT OCEAN BLVD, CONSTRUCT INTERCHANGE 26,345,883.16 44,546,187.98
California 0004001 ALAMEDA ST: DEL AMO BLVD TO RTE 91, WIDEN FROM 4 TO 6 LANES, CONST 24,751,440.00 42,823,402.00
California 000C355 SR60/SR91/I-215 TO ORANGE SHOW ROAD I/C NORTH OF THE I-215/I-10, CONSTRUCT HOV LANES IN EACH DIRECTION (TC) 14,005,463.00 173,933,571.00
California 000C438 ON I-205 AND I-580 FROM SAN JOAQUIN COUNTY LINE TO GREENVILLE ROAD OVERHEAD. RESURFACE AND RESTORE PAVEMENT ON THE MAINLINE AND RAMPS. (TC) 73,740,300.00 79,491,200.00
California 000C466 TUOLUMNE AND STANISLAUS COUNTIES NEAR SONORA ON ROUTE 108 FROM YOSEMITE JUNCTION TO MONTEZUMA ROAD AND ON ROUTE 120 FROM 0.2 MILE WEST OF LANCASTER R 24,991,900.00 25,323,700.00
California 000C469 IN AND NEAR SAN DIEGO AT ROUTE 905/125/11 SEPARATION (SEGMENT 4) AND ON ROUTE 11 FROM 0.1 MILE WEST OF ENRICO FERMI DRIVE TO 1.2 MILE EAST OF ENRICO 52,630,000.00 126,507,700.00
California 000C470 ALAMEDA, CONTRA COSTA, AND SOLANO COUNTIES AT VARIOUS LOCATIONS INSTALL TRAFFIC OPERATION SYSTEM (TC) 0.00 40,973,000.00
California 000C494 IN THE CITY OF SACRAMENTO, AT SACRAMENTO RIVER BRIDGE NO. 24-0053 AND NORTH SACRAMENTO UNDERCROSSING NO. 24-0111L; ALSO IN SAN JOAQUIN COUNTY, AT MOK 28,269,600.00 32,725,000.00
California 000C526 IN SAN DIEGO COUNTY AND IMPERIAL COUNTY ON VARIOUS ROUTES AT VARIOUS LOCATIONS INSTALL FIBER OPTIC CABLE ALONG THE I-5, I-805, AND SR-905, CONNECT AL 16,532,800.00 27,445,100.00
California 0051625 IN SAN DIEGO COUNTY IN SAN DIEGO FROM 0.4 MILES SOUTH OF GENESEE AVE OC TO REPLACE BRIDGE, RAMP, IC, BUTTRESS, BIKE TRL 11,519,460.00 77,584,859.00
California 0051636 IN SAN DIEGO COUNTY ON INTERSTATE 5 AT VARIOUS LOCATIONS FROM 0.2 MILE SOUTH OF SAN ELIJO LAGOON BRIDGE TO 0.5 MILE SOUTH OF PALOMAR AIRPORT ROAD OVE 59,240,700.00 301,625,107.00
California 0051639 I-5 NORTH COAST CORRIDOR HOV EXTENSION - PHASE 1 - ENCINITAS HOV (SAN DIEGO COUNTY IN ENCINITAS AND CARLSBAD FROM SAN ELIJO LAGOON BRIDGE TO 0.3 MILE 97,602,100.00 300,466,000.00
California 0051993 CONSTRUCT HOV LANES, AUXILARY LANES, AND ITS (CMGC) IN SAN DIEGO COUNTY AT VARIOUS LOCATIONS FROM LOMAS SANTA FE DRIVE UNDERCROSSING TO 0.2 MILES NOR 0.00 74,356,000.00
California 0052019 IN SAN JUAN CAPISTRANO AND MISSION VIEJO FROM ROUTE 73 TO OSO PARKWAY. ADD GENERAL PURPOSE LANE IN EACH DIRECTION AND RECONSTRUCT INTERCHANGES AT AVE 20,000,000.00 71,816,600.00
California 0052868 I-5 IN ORA CO-CRESCENT AV/LA PALMA AV WIDEN FREEWAY & HOV LANES 40,591,459.78 62,968,282.78
California 0052949 ON ROUTE 5 FROM ALONDRA BLVD(KP 2.9/PM 1.8) TO SHOEMAKER AVE(KP 4.0/PM 3.1) INTERSECTION IMPROVEMENTS 45,958,183.00 125,171,506.00
California 0052966 ON INTERSTATE ROUTE 5 IN ORANGE COUNTY IN SAN CLEMENTE AND DANA POINT *** RECONSTRUCTION (WIDENING FOR HOV LANES) (TC) 47,428,433.25 48,818,820.66
California 0052969 IN LA CTY IN LAMIRADA, SANTA FE SPRINGS, NORWALK & DOWNEY FROM OC TO LA CTY, WIDEN FREEWAY, RECONSTRUCT OH (TC) 7,379,087.00 112,841,043.00
California 0052981 IN LOS ANGELES COUNTY IN LAMIRADA FROM ARTESIA BLVD TO NORTH FORK COYOTE CREEK OVERCROSSING WIDEN AND REALIEGN FREEWAY TO ADD ONE MIXED FLOW LANE AND 45,903,500.00 60,256,800.00
California 0053029 LA CO RTE 5 FROM N. OF BUENA VISTA TO RTE 170, HOV AND ROADWAY REHAB 47,406,661.21 65,864,877.21
California 0053074 NEAR CASTAIC, FROM LAKE HUGHES ROAD UNDERCROSSING TO 1.9 MILES NORTH OF TEMPLIN HIGHWAY. REPLACE APPROACH SLABS, UPGRADE DRAINAGE SYSTEMS, UPGRADING 0.00 39,056,000.00
California 0053078 IN LOS ANGELES COUNTY FROM MAGNOLIA BLVD TO JUST NORTH OF BUENA VISTA CONSTRUCT HOV LANES & MODIFICATION AND ROADWAY REHABILITATION BASED ON THE CHA 103,745,612.00 324,615,854.00
California 0053122 LA-005-45.4R/61.2R. IN AND NEAR SANTA CLARITA, FROM 0.5 MILES SOUTH OF I-5/SR- 14 SEPARATION TO 1.7 MILES NORTH OF LAKE HUGHES ROAD UNDERCROSSING. RO 155,881,000.00 156,180,200.00
California 0053129 IN LOS ANGELES COUNTY ON ROUTE 5, PM R45.0 TO R59.6, EXTEND THE HOV LANES FROM THE SR-14 INTERCHANGE TO JUST SOUTH OF THE PARKER ROAD INTERCHANGE, IN 0.00 533,596,550.00
California 0054195 KERN CO NR LOST HILLS FRM LERDO AVE OC TO ROUTE 5/46 SEPARATION CONC LANE & PANEL REPLACEMENT & GRIND CONC (TC) 49,061,479.00 49,260,979.00
California 0054204 IN KERN COUNTY NEAR KETTLEMEN CITY FROM 0.6 MILE SOUTH OF TWISSLEMAN ROAD OVERCROSSING TO 0.3 MILE NORTH OF KERN/KINGS COUNTY LINE. REHABILITATE AND 37,469,460.97 41,289,800.00
California 0055156 MERCED COUNTY 0.4 MILE NORTH OF THE FRESNO COUNTY LINE AT THE JOHN "CHUCK" ERRECA SAFETY ROADSIDE REST AREA REPLACE SAFETY ROADSIDE REST AREA (SRRA) 0.00 28,752,000.00
California 0056338 SJ CO IN/NR STOCKTON FR 0.3 MI S CHARTER WY UC TO 0.2 MI N COUNTRY CLUB BLVD UC ROADWAY REHABILITATION (TC) 63,328,500.00 63,570,000.00
California 0056349 IN SACRAMENTO, FROM 1.1 MILES SOUTH OF ELK GROVE BLVD OC TO AMERICAN RIVER BRIDGE CORRIDOR ENHANCEMENT - CONSTRUCT HOV LANE, ROADWAY REHABILITATION, 0.00 334,355,700.00
California 0058337 IN SHA CO NR LAKEHEAD AT SACTO RVR,BR#06-0089 (TC) REPLACE BRIDGE (TC) 186,149,723.43 186,149,723.43
California 0058355 IN SHA CO ABOUT 8 MI N OF SHA LAKE CITY & NEAR LAKEHEAD FRM TURNTABLE BAY OC TO BRIDGE REPLACEMENT AND SEISMIC RETROFIT (TC) 30,460,600.00 44,026,000.00
California 0058359 IN SHASTA COUNTY IN AND NEAR ANDERSON FROM ROUTE 5/273 SEPARATION TO 0.4 MILE SOUTH OF CHURN CREEK ROAD OVERCROSSING. WIDENING TO 6 LANES, BRIDGE REP 112,782,153.00 150,659,000.00
California 0059177 IN SISKIYOU COUNTY IN AND NEAR DUNSMUIR FROM SACRAMENTO RIVER BRIDGE TO 0.6 MILE SOUTH OF NORTH MOUNT SHASTA UNDERPASS. 2 R ROADWAY REHABILIATION - S 69,991,600.00 70,123,000.00
California 0081329 IN SAN DIEGO COUNTY NEAR ALPINE ON INTERSTATE 8 FROM VIEJAS CREEK BRIDGE TO PINE VALLEY CREEK BRIDGE. PLACE CRCP, HMA, RSC, MGS, AND WATER POLLUITION 0.00 43,737,000.00
California 0082109 IN IMPERIAL COUNTY NEAR EL CENTRO FROM 0.5 MILE WEST OF ROUTE 8/111 SEPARATION TO 0.6 MILE WEST OF ANDERHOLT ROAD OVERCROSSING AND FROM 0.5 MILE EAST 97,315,800.00 98,089,600.00
California 0082110 IN IMPERIAL COUNTY ABOUT 6 MILES WEST OF WINTERHAVEN FROM 0.7 MILE WEST OF OGILBY ROAD OVERCROSSING TO 0.7 MILE WEST OF ROUTE 186/8 SEPARATION. PAVEM 51,571,300.00 52,113,400.00
California 0082112 IN IMPERIAL COUNTY IN EL CENTRO FROM 0.4 MILE WEST OF IMPERIAL AVENUE OVERCROSSING TO 0.1 MILE EAST OF 8TH STREET OVERCROSSING RECONSTRUCT INTERCHANG 0.00 32,828,160.26
California 0089001 STATEWIDE COMBINED ROAD PLAN, PROJECT CONSTRUCTION ACTIVITIES 0.00 37,250,104.00
California 0101820 IN LA COUNTY IN CITY OF BALDWIN PARK AND WEST COVINA FR PUENTE AVE TO CITRUS ST CONSTRUCT HOV LANES AND SOUNDWALLS (TC) 40,140,000.00 157,866,051.00
California 0101829 ROUTE 10 HOV LANES FROM CITRUS ST T ROUTE 57 IN LA COUNTY/CITRUS ST TO RTE 57 HOV, WIDENING, AND REALIGN (TC) 73,876,900.00 229,230,500.00
California 0101840 LA, 10, PM: 14-19 IN THE CITY OF LOS ANGELES AT SANTA MONICA VIADUCT (BR. NO. 53-1301). PAINT AND REHABILITATE BRIDGE. THE PURPOSE OF THIS PROJECT IS 39,314,500.00 39,759,700.00
California 0101844 IN THE CITIES OF SANTA MONICA AND LOS ANGELES, FROM ROUTE 1 TO ROUTE 5/101 INTERCHANGE; ALSO ON ROUTE 1 FROM MCCLURE TUNNEL TO LINCOLN BOULEVARD. REP 34,651,200.00 38,106,060.00
California 0101855 LA-010 - IN BALDWIN PARK AND WEST COVINA, FROM ROUTE 605 TO CITRUS AVENUE. REHABILITATE ROADWAY. THIS PROJECT WILL RESTORE THE EXISTING PAVEMENT ALON 56,227,400.00 62,034,000.00
California 0102266 IN SAN BERNARDINO COUNTY IN YUCAIPA FROM 0.2 MILE WEST OF LIVE OAK CANYON ROAD TO COUNTY LINE ROAD UNDERCROSSING PAVEMENT REHABILITATION AND CONTINO 18,144,700.00 36,589,100.00
California 0102268 IN SAN BERNARDINO COUNTY ON INTERSTATE 10 BETWEEN SAN ANTONIO AVENUE AND ROUTE 15. IMPLEMENT TWO EXPRESS LANES IN EACH DIRECTION FOR A TOTAL OF FOUR 104,315,784.00 168,718,000.00
California 0102269 IN SAN BERNARDINO COUNTY ON INTERSTATE 10 BETWEEN SAN ANTONIO AVENUE AND ROUTE 15. IMPLEMENT TWO EXPRESS LANES IN EACH DIRECTION FOR A TOTAL OF FOUR 62,041,969.00 117,755,000.00
California 0103110 RIVERSIDE COUNTY FROM PENNSYLVANIA AVENUE UNDERCROSSING TO ROUTE 10/111 SEPARATION PAVEMENT REPLACEMENT, OVERLAY, CONCRETE SLAB, CURB RAMPS 0.00 214,283,800.00
California 0103112 IN RIVERSIDE COUNTY FROM ROUTE 10/177 SEPARATION TO 1.1 MILES WEST OF WILEY'S WELL ROAD OC REHABILITATE MAINLINE PAVEMENT, SHOULDERS AND RAMPS 0.00 326,730,500.00
California 0104064 ON I-10 IN INDIO BETWEEN WASHINGTON ST & MONROE ST AT JEFFERSON ST INTERCHANGE RECONSTRUCT/REALIGN EXISTING INTERCHANGE 33,310,000.00 56,760,364.00
California 0151237 ON INTERSTATE ROUTE 15 IN SAN BERNARDINO COUNTY IN AND NEAR VICTORVILLE *** ROADWAY RECONSTRUCTION (TC) 98,451,300.00 102,718,300.00
California 0153045 ON INTERSTATE ROUTE 15 IN SAN BERNARDINO COUNTY *** I 15 JOINT POINT OF ENTRY (SCALE - CVEF) (TC) 12,573,994.00 52,150,417.00
California 0154208 IN SAN DIEGO AND RIVERSIDE COUNTY IN AND NEAR TEMECULA FROM 0.1 MILE SOUTH OF SAN DIEGO COUNTY LINE TO 0.1 MILE NORTH OF TEMECULA RIVER BRIDGE REPLAC 33,427,400.00 36,978,500.00
California 0154210 IN SAN DIEGO COUNTY ON INTERSTATE 15 IN AND NEAR ESCONDIDO, FROM 0.2 MILE SOUTH OF ROUTE 15/78 SEPARATION TO 0.5 MILE NORTH OF DEER SPRINGS ROAD OVE 0.00 69,464,000.00
California 0155165 IN SAN BERNARDINO COUNTY IN FONTANA AND NEAR DEVORE FROM 0.3 MILE SOUTH OF SIERRA AVENUE UNDERCROSSING TO GLEN HELEN PARKWAY UNDERCROSSING. REPLACE P 26,479,014.50 29,213,800.00
California 0155166 IN RIVERSIDE COUNTY IN CORONA AND EASTVALE, FROM 0.5 MILE SOUTH OF ONTARIO AVENUE UNDERCROSSING TO ROUTE 60/15 SEPARATION CONCRETE PAVEMENT SLAB REP 27,129,400.00 30,088,200.00
California 0155167 IN HESPERIA AND VICTORVILLE FROM OAK HILL RD OC TO 0.1 MILE S/O BEAR VALLEY RD OC REHABILITATE EXISTING MAINLINE AND RAMP PAVEMENT 0.00 163,648,000.00
California 0401084 IN SAN BERNARDINO COUNTYNEAR LUDLOW FROM 0.3 MILE EAST OF CRUCERO ROAD TO 0.4 MI W/O BADGER WASH REGRADE MEDIAN CROSS SLOPE (TC) 41,220,800.00 41,550,100.00
California 0801117 CONTRA COSTA COUNTY, IN AND NEAR RICHMOND, EL CERRITO, SAN PABLO, PINOLE AND HERCULES, FROM ALAMEDA/CONTRA COSTA COUNTY LINE TO ROUTE 80/4 SEPARATION. 42,147,500.00 42,655,100.00
California 0801120 THE CITY AND COUNTY OF SAN FRANCISCO FROM 16TH STREET TO 4TH STREET. PAINT STEEL STRUCTURE 0.00 31,725,500.00
California 0801121 ALAMEDA COUNTY IN BERKELEY AND ALBANY FROM 0.6 MILE NORTH OF UNIVERSITY AVENUE OVERCROSSING TO 0.3 MILE SOUTH OF EL CERRITO SEPARATION AND OVERHEAD E 0.00 28,803,000.00
California 0802375 SOLANO COUNTY IN FAIRFIELD AND VACAVILLE FROM 1.0 MILE WEST OF RED TOP ROAD UNDER CROSSING TO 0.4 MILE EAST OF LEISURE TOWN ROAD CROSSING HIGHWAY WID 0.00 26,800,000.00
California 0803235 PLA CO;ROCKLIN;I-80 @ SIERRA COLLEGE BLVD OC, INTERCHANGE RECONSTRUCTION - (TC) 18,432,000.00 25,545,565.00
California 0803237 IN SACRAMENTO AND WEST SACRAMENTO FROM 80/84 SEPARATION TO WATT AVENUE OVERCROSS CONST. HOV LANES & REHAB. ROADWAY - (TC) 73,653,185.91 127,190,346.57
California 0803243 IN AND NEAR LOOMIS AT VARIOUS LOCATIONS FROM BRACE ROAD OVERCROSSING TO MAGRA RO IMPROVE VERTICAL CLEARANCE - (TC) 33,886,844.00 33,937,687.00
California 0803250 IN YOLO AND SACRAMENTO COUNTIES IN WEST SACRAMENTO AND SACRAMENTO FROM 0.1 MILE WEST OF REED AVENUE UNDERCROSSING TO 0.1 MILE EAST OF SACRAMENTO RIVE 23,617,000.00 26,080,200.00
California 0804194 NEAR COLFAX ON RTE 80FROM LONG RAVINE RD TO EAST OF MAGRA RD OC TRUCK CLIMBING LANE (TC) 53,602,900.00 53,812,700.00
California 0804207 N PLACER COUNTY AT VARIOUS LOCATIONS FROM CRYSTAL SPRINGS ROAD OVERCROSSING TO CISCO OVERCROSSING. REPLACE BRIDGES AT FOUR LOCATIONS (#19-0112, #19-0 34,766,500.00 38,244,500.00
California 0804213 NEVADA COUNTY IN AND NEAR TRUCKEE FROM 0.2 MILE WEST OF DONNER PARK OVERCROSSING TO ROUTE 89/267 SEPARATION ROADWAY EXCAVATION, JPCP AND FURNISH POL 0.00 27,027,000.00
California 1101841 LA-110 - IN AND NEAR THE CITIES OF LOS ANGELES AND CARSON, FROM GAFFEY STREET TO COLLEGE STREET, EXTEND SERVICE LIFE OF EXISTING PAVEMENT AND INSTALL 39,412,800.00 39,631,200.00
California 1187011 SM CO NEAR PACIFIC ON RT 1 S/O LINDA MAR BLVD CONSTRUCT TUNNELS, APPROACH RO 498,589,217.34 502,809,766.87
California 19FF004 IN MENDOCINO COUNTY NEAR DOS RIOS FROM 1.4 TO 1.7 MILES EAST OF RODEO CREEK BR #10-237 STABILIZE ROADWAY 0.00 25,902,000.00
California 2012001 AT RTE 76/15 SEP & ON RTE 76 FR SOUTH MISSION RD TO 76/15 SEP, CONSTRUCT 4 LANE HIGHWAY 300,000.00 100,146,000.00
California 2056356 SAN JOAQUIN COUNTY IN AND NEAR TRACY FROM JANNEY OVERHEAD TO 1.3 MILES EAST OF MACARTHUR DRIVE OVERCROSSING WIDENING BRIDGES, RAMPS AND ROADWAY 0.00 26,545,000.00
California 2101823 IN AND NEAR GLENDALE & LA CANADA FLINTRIDGE FR DUNSMORE TO HAMPTON RD/FOOTHILL PAVEMENT PRESERVATION (TC) 147,640,643.00 152,492,643.00
California 2151219 IN RIVERSIDE COUNTY, IN RIVERSIDE, *** , WIDEN 215 (6 TO 8)                                          (2004A GARVEE) 0.00 165,853,564.00
California 27E8004 IN VENTURA COUNTY, SOUTH OF POINT MUGU STATE PARK (PM 4.0) AND SYCAMORE CANYON ROAD (PM 4.2). CONSTRUCT SECANT WALLS AT TWO LOCATIONS AS A PERMANENT 0.00 56,254,000.00
California 2801150 SANTA CLARA AND SAN MATEO COUNTIES IN LOS ALTOS HILLS AND MENLO PARK FROM FOOTHILL EXPRESSWAY UNDERCROSSING TO 0.5 MILE NORTH OF SAND HILL ROAD ROADW 53,402,900.00 58,733,100.00
California 29R4006 IN MENDOCINO CO. NEAR WESTPORT, FROM 0.6 TO 1.4 MI NORTH OF BLUE SLIDE GULCH BRIDGE. EMERGENCY RELIEF - RECONSTRUCT ROADWAY 23,118,014.96 38,650,000.00
California 31D0001 IN TRINITY CO., NEAR DEL LOMA AT BIG FRENCH CREEK ROAD EMERGENCY RELIEF - EMERGENCY OPENING STORM DAMAGE REPAIRS. 43,231,326.00 43,853,000.00
California 31R0001 MONTEREY COUNTY, NEAR POSTS, AT PFEIFFER CANYON BRIDGE, NO. 44-0060 EMERGENCY PROJECT - EMERGENCY OPENING REMOVE AND REPLACE DAMAGED BRIDGE, RESTORE 23,899,700.00 26,996,626.00
California 31RH001 MONTEREY COUNTY, NEAR GORDA, 0.9 MILE NORTH OF VILLA CREEK BRIDGE TO 1.7 MILES NORTH OF RAIN ROCKS SIDEHILL VIADUCT. EMERGENCY RELIEF / OPENING - REM 1,497,124.77 94,217,533.34
California 31TC001 IN SANTA CLARA COUNTY, NEAR LOS GATOS, AT 1.2 MILES NORTH OF LAS CUMBRES ROAD CONSTRUCT SOLDIER PILE WALLS. 0.00 34,558,500.00
California 31TN001 IN MARIN COUNTY, NEAR STINSON BEACH AT 0.6 MILE SOUTH OF PANORAMIC HIGHWAY NORTH JUNCTION CONSTRUCT SOLDIER PILE WALL 0.00 31,650,000.00
California 37B3004 MEN CO;NR LEGGETT;S/O TO N/O RED MTN CK NEW FWY;2 BRIDGES;RET WALLS;PA 65,894,389.11 89,545,023.43
California 37Y0001 ON STATE ROUTE 70 IN YUBA COUNTY AND STATE ROUTE 99 IN SUTTER COUNTY AT VARIOUS LOCATIONS. PAVEMENT DAMAGED AT VARIOUS LOCATIONS DUE TO FEMA DEBRIS R 22,244,925.00 29,612,500.00
California 4052986 IN ORANGE COUNTY ON ROUTE 405 FROM STATE ROUTE 73 TO I-605 ADD ONE MIXED FLOW AND TOLL EXPRESS LANE IN EACH DIRECTION WITH OTHER OPERATIONAL IMPROVEM 74,191,000.00 1,900,000,000.00
California 4052999 I-405 AT CRENSHAW BLVD. RAMP IMPROVEMENT; IN LOS ANGELES COUNTY, IN THE CITY OF TORRANCE BETWEEN WESTERN AVENUE AND WEST 182ND STREET / CRENSHAW BLVD. 0.00 66,756,000.00
California 4053015 FROM PM 0.43 S/O LA-10 TO VENTURA BL., WIDEN FOR HOV LANE 222,428,625.26 827,217,719.00
California 4053048 LA 405, FROM ROUTE 90 TO ROUTE 10, CONSTRUCT HOV LANES 135,609,173.16 191,678,475.76
California 4127001 LA CO NON-INTERSTATE RTES VAR LOCATIONS, ER RELIEF STORM DAMAGE REPAIR 26,537,637.51 29,114,534.00
California 5004049 W MISSION BAY DRIVE/SAN DIEGO RIVER BRIDGE REPLACEMENT (57C-0023) 41,887,016.00 146,919,728.00
California 5006219 N. SPRING ST. BRDG OVR L.A. RVR, BRIDGE # 53C0859 BRIDGE REHABILITATION/WIDENING 36,048,438.00 45,996,471.46
California 5006221 RIVERSIDE DR. OVER L.A. RIVER, BRDG #53C0160 BRIDGE REPLACEMENT /WIDENING 49,654,086.98 60,868,544.00
California 5006336 FIRST ST. OVER L.A. RIVER BRIDGE # 53C-1166 BRIDGE REHABILITATION 58,331,222.66 66,314,332.22
California 5006664 SIXTH STREET VIADUCT OVER LA RIVER AND EAST SANTA ANNA FREEWAY, 53C1880 REPLACE STRUCT DEFICIENT VIADUCT WITH NEW (TC) 119,965,869.00 148,909,901.00
California 5006811 SIXTH STREET VIADUCT OVER LA RIVER, US 101, AND UPRR, BNSF, AMTRACK, LACMTA AND METROLINK TRACKS BRIDGE # 53C-1880 AND STATE BRIDGE # 53-0595 CMGC PA 28,978,113.00 33,088,934.00
California 5006831 SIXTH STREET VIADUCT OVER LA RIVER, US 101, AND UPRR, BNSF, AMTRACK, LACMTA AND METROLINK TRACKS BRIDGE # 53C-1880 AND STATE BRIDGE # 53-0595 THIS I 26,125,154.00 29,509,945.00
California 5006839 SIXTH STREET VIADUCT OVER LA RIVER, US 101, AND UPRR, BNSF, AMTRACK, LACMTA AND METROLINK TRACKS BRIDGE # 53C-1880 AND STATE BRIDGE # 53-0595 102,462,444.00 230,364,054.00
California 5006882 THIS IN THE PORT OF LOS ANGELES, TERMINAL ISLAND TERMINAL ISLAND RAILYARD 21,645,000.00 55,650,000.00
ENHANCEMENT PROJECT: THIS PROJECT ENTAILS THE ADDITION OF 5 STAGING/STORAGE TRAC
California 5012037 LAKE MERRITT CHANNEL BRIDGE (BR.NO.33C-0030) REPLACE BRIDGE (PER SEISMIC STRATEGY) 27,595,632.00 31,446,836.00
California 5012085 12TH & 14TH ST BRIDGES 33C0181 & 33C0182 BRIDGE REPLACEMENT (SEISMIC) 11,060,488.42 55,410,000.00
California 5059230 STATE ROUTE 132 FROM NORTH DAKOTA AVE TO THE NEEDHAM STREET OVERCROSSING INCLUDING THE 132 / 99 INTERCHANGE. CONSTRUCT TWO-LANE EXPRESSWAY / HIGHWAY 22,101,971.00 33,360,766.00
California 5060263 FULTON MALL & MARIPOSA MALL ROAD RECONSTRUCTION 16,924,620.00 28,016,759.02
California 5060384 VETERANS BLVD./SH99/GOLDEN STATE BLVD. (PHASE 3) VETERANS BLVD./SH99 INTERCHANGE; NORTHERLY JUG HANDLE; VETERANS BLVD. OVERCROSSING OF GOLDEN STATE 10,540,582.00 59,151,158.00
California 5068001 CYPRESS AVE. @ SAC RIVER, BR #. 06C0108 L&R (NEW BRIDGE # 06C0377) REPLACE BRIDGES 79,976,316.00 92,138,624.00
California 5104033 AUTO CENTER DRIVE AT BNSF RAILROAD SOUTH OF RAILROAD STREET, NEW OVERHEAD 8,061,892.00 32,238,599.00
California 5108137 GERALD DESMOND BRIDGE BR# 53C0065 BRIDGE REPLACEMENT 173,115,000.00 888,400,000.00
California 5108189 PORT OF LONG BEACH-PIER G TO J DOUBLE TRACK ACCESS FRO PIER G TO J, CREATING 9,000 FOOT DEPARTURE TRACK FOR TRAIN SERVING FOUR MARINE TERMINALS ALONG 14,000,000.00 26,700,780.00
California 5109106 SR58: FROM 0.60 MILE E/O COFFEE RD OVERCROSSING TO TRUXTUN AVE UNDERCROSSING, ELEMENT OF THE CITY OF BAKERSFIELD CENTENNIAL CORRIDOR PROJECT. CONSTRU 113,362,209.00 127,729,712.00
California 5109200 24TH/23RD STREETS (SR178) FROM 0.1 MI WEST OF SR99 (W/O KERN RIVER BR.) TO 0.2 MI EAST OF "M" STREET ROADWAY WIDENING AND INTERSECTION IMPROVEMENTS 23,540,432.70 44,294,976.43
California 5109242 KERN COUNTY IN THE CITY OF BAKERSFIELD ON RTE 99 FROM 0.3 MI SOUTH OF BELLE TERRACE OVERCROSSING TO 0.1 MILE NORTH OF ROUTE 58; ALSO ON ROUTE 58 FROM 4,280,000.00 36,549,100.00
California 5109245 SR99/ SR58 CONNECTOR, SR99 FROM BELLE TERRACE TO MING AVE. IMPROVEMENTS ON SR99/ SR58 CONNECTOR INCLUDING THE CONSTRUCTION OF A COLLECTOR- DISTRIBUTOR 11,122,638.65 58,633,355.00
California 5109251 CENTENNIAL CORRIDOR CONNECTOR: WESTSIDE PARKWAY(WSP) AT KERN RIVER BR. TO SR58 SR99 NEW ROAD: CONSTRUCT NEW CENTENNIAL CORRIDOR MAINLINE AND INTERCH 97,719,464.10 156,024,110.25
California 5133035 STATE COLLEGE BOULEVARD FROM 700 FEET SOUTH OF VALENICA DRIVE TO SANTA FE AVENUE NEW UNDERPASS 38,882,375.42 90,106,344.52
California 5163027 5TH STREET AT 2ND STREET AND 5TH STREET OVER FEATHER RIVER BRIDGE REPLACEMENT (TC) 76,942,547.91 79,048,216.00
California 5166015 BON AIR BRIDGE (BON AIR RD OVER CORTE MADERA CREEK). BR.# 27C0028 BRIDGE REPLACEMENT 32,404,556.00 37,828,547.00
California 5203016 WILLOW ST @ SWEETWATER RIVER, BRIDGE 57C0011 REPLACE TWO LANE BRIDGE WITH FOUR LANE BRIDGE 24,394,942.00 29,080,076.00
California 5282017 INDIAN CANYON DRIVE OVERHEAD AT THE UNION PACIFIC RAILROAD SOUTH OF GARNET AVENUE, BR. NO. 56C-0025 BRIDGE WIDENING TO SIX LANES 1,635,943.00 26,425,723.00
California 5288046 IN FOLSOM ON WHITE ROCK RD FROM PRAIRIE CITY RD TO EAST BIDWELL ST. CONSTRUCT 4 LANE ROAD WITH 8 FOOT SHOULDERS. (CLASS 1 TRAIL TO BE BUILT IN LATER 15,000,000.00 31,201,500.00
California 5380028 GREEN TREE BOULEVARD FROM HESPERIA ROAD TO RIDGECREST BOULEVARD EXTENSION OF 4-LANE ROAD WITH NEW OVERHEAD 25,696,701.07 46,758,408.45
California 5381033 VIA VERA CRUZ, BRDG NO. 57C0780 REPLACE 2-LANE BRIDGE WITH 4-LANE BRIDGE 2,832,960.00 32,885,590.00
California 5459025 I-15/SR 79 INTERCHANGE FROM 0.4 MILES SOUTH OF SR 79 TO 0.6 MILES NORTH OF THE I-15/SR 79 SEPARATION IN THE CITY OF TEMECULA WIDEN INTERCHANGE RAMPS 14,415,839.50 27,271,373.50
California 5464029 I-215 / CLINTON-KEITH ROAD INTERCHANGE , RECONSTRUCT INTERCHANGE 9,999,452.00 26,437,922.00
California 5801051 ON I-580 IN ALAMEDA COUNTY NEAR LIVERMORE 1 MILE EAST OF NORTH FLYNN ROAD CONSTRUCT RETAINING WALL AND CLIMBING LANE (TC) 53,480,532.41 54,003,380.41
California 5801054 ISABEL AVEN (LIVERMORE) TO FOOTHILL (DUBLIN) CONSTRUCT A WESTBOUND HOV LANE 9,609,605.39 51,907,082.00
California 5801055 GREENVILLE ROAD TO ISABEL AVENUE (LIVERMORE) CONSTRUCT A WESTBOUND HOV LANE 12,404,356.26 68,826,847.67
California 5801076 ALAMEDA COUNTY FROM ROUTE 580/ROUTE 238 SEPERATION TO FRUITEVALE AVENUE UNDERCROSSING TO REPLACE SLAPBS, RESURFACE SHLDS & RAMPS, & CONSTRUCT MGS, & 39,410,700.00 43,446,500.00
California 5908031 JELLYS FERRY RD OVER SACRAMENTO RIVER BRIDGE (BR. #08C0043) BRIDGE REPLACEMENT ON NEW ALIGNMENT 37,025,766.00 53,014,639.00
California 5912085 MIDWAY RD @ BUTTE CREEK 3.9 MILES SOUTH OF NELSON RD. BRIDGE NO. 12C0052 & 12C0053 BRIDGE REPLACEMENT 21,264,112.00 27,196,250.00
California 5925098 MOSQUITO RD OVER SOUTH FORK AMERICAN RIVER 5.7 MILES NORTH OF US 50 BR#25C0061 BRIDGE REPLACEMENT (TC) 8,814,000.00 79,314,000.00
California 5929166 MCHENRY AVENUE OVER STANISLAUS RIVER (BRIDGE 38C0032) BRIDGE REPLACEMENT 22,651,344.00 25,943,318.00
California 5934171 2ND STREET FROM MARKET TO KING BICYCLE & PED IMPROVEMENTS, REPAVE 11,116,386.00 25,883,895.00
California 5934177 IN SAN FRANCISCO, ON 3RD STREET, CROSSING OVER THE MISSION CREEK CHANNEL BETWEEN BERRY STREET AND TERRY A FRANCOIS BOULEVARD; BR. # 34C0025 BRIDGE RE 32,060,268.00 36,214,015.00
California 5934185 MARKET STREET, 5TH STREET TO 8TH STREET. WORK MAY EXTEND OFF MARKET STREET, UP TO 50 FEET AT INTERSECTIONS. ROADWAY IMPROVEMENTS, INCLUDING ROADWAY R 18,366,000.00 191,108,886.00
California 5938076 CROWS LANDING ROAD (BRIDGE 38C0010) OVER SAN JOAQUIN RIVER REPLACE BRIDGE (SEISMIC) 11,016,825.00 25,617,720.09
California 5956221 66TH AVENUE FROM EAST OF STATE ROUTE 86 TO DALE KILER ROAD IN THE COMMUNITY OF MECCA NEW OVERHEAD 24,479,641.00 47,974,058.00
California 5956230 HAMNER AVENUE OVER SANTA ANA RIVER, BR. NO. 56C-0446 REPLACE 2-LANE BRIDGE WITH 6-LANE BRIDGE 22,690,484.00 72,163,126.00
California 5956234 NEWPORT ROAD OVER I-215 FROM HAUN ROAD TO ANTELOPE ROAD IN THE CITY OF MENIFEE WIDEN OVERPASS AND RECONSTRUCT ON- AND OFF-RAMPS 14,625,000.00 34,907,563.00
California 5956235 I-10 INTERCHANGE WITH JEFFERSON STREET IN THE CITY OF INDIO RECONSTRUCT INTERCHANGE 12,252,248.00 57,292,064.00
California 5956262 SCOTT ROAD AT I-215 INTERCHANGE FROM HAUN ROAD TO ANTELOPE ROAD, BR. NO. 56 0649 RECONSTRUCT INTERCHANGE 8,000,000.00 35,127,620.00
California 6003010 GOLDEN GATE BRIDGE SEISMIC RETROFIT PHASE II 176,766,529.00 179,829,873.49
California 6003051 GOLDEN GATE BRIDGE SUICIDE DETERRENT SYSTEM 126,992,886.00 204,092,868.00
California 6053122 US 395 FROM PALMDALE ROAD (SR 18) IN PALMDALE TO CHAMBERLAINE WAY IN ADELANTO, PHASE 1 WIDEN HIGHWAY FROM TWO TO FOUR LANES (TC) 8,027,804.64 40,003,413.00
California 6053130 I-10 CORRIDOR EXPRESS LANE WIDENING FROM SAN ANTONIO AVENUE IN THE CITY OF POMONA TO THE I-10/I-15 INTERCHANGE IN THE CITY OF ONTARIO, PHASE 1 DESIGN 207,167,533.00 319,461,533.00
California 6054081 I-15 FROM CAJALCO ROAD IN THE CITY OF CORONA TO STATE ROUTE 60 IN THE CITIES OF EASTVALE AND JURUPA VALLEY CONSTRUCT TOLL EXPRESS LANES IN EACH DIREC 98,418,952.00 341,863,797.00
California 6054090 STATE ROUTE 60 FROM GILMAN SPRINGS ROAD TO 1.37 MILES WEST OF JACK RABBIT TRAIL CONSTRUCT EASTBOUND AND WESTBOUND TRUCK LANES 45,401,000.00 109,133,000.00
California 6065198 I-405 NB HOV LANE, WIDENING: I-10 TO I-101 ROAD WIDENING FOR HOV LANE 92,600,000.00 104,597,312.00
California 6065240 NORTHERN LOS ANGELES COUNTY FROM I-5/SR14 JCT. TO PARKER ROAD. THE INTERSTATE 5 (I-5) GOLDEN STATE CHOKEPOINT RELIEF PROJECT (THE PROJECT) OFFERS A C 47,000,000.00 533,596,550.00
California 6065251 I-210 FREEWAY FROM 0.2 MILES WEST OF MARENGO AVE TO W ILSON AVE IN THE CITY OF PASADENA AND APPROXIMATELY 1.5 MILES OF SOUNDWALLS FROM BALDWIN AVE TO 48,649,000.00 48,649,000.00
California 6066104 NCTD RAIL R/W FOR SPRINTER COMMUTER TRAIN IN CITIES OF VISTA, SAN MARCOS, OCEANSIDE AND THE COUNTY OF SAN DIEGO BUILD 7.1 MILES OF CLASS I BICYCLE TR 17,827,622.64 28,374,000.00
California 6071122 INTERSTATE 405 FROM STATE ROUTE 73 TO INTERSTATE 605 ADD TOLL EXPRESS (TEL) AND MIXED-FLOW LANES IN EACH DIRECTION 1,000.00 1,900,000,000.00
California 6164023 ALONG THE WHITEWATER RIVER STORM CHANNEL FROM THE CITY OF PALM SPRINGS TO THE CITY OF COACHELLA, PHASE 1, SEGMENT 1 CONSTRUCT 13.47 MILES OF NEW BIKE 18,655,000.00 33,009,000.00
California 6202007 HWY 299 BETWEEN TRINITY & SHASTA COUNTIES; APPROX 20 MILES WEST OF REDDING, HWY REALIGNMENT (TC) 839,440.00 30,298,000.00
California 6203055 SR-99 FROM ASH ST TO RAMSDELL DR STREETSCAPE IMPROVEMENTS (TC) 10,810,000.00 39,563,000.00
California 6203058 RECONFIGURE I-80/SR-65 I/C & WIDEN NB SR-65 FROM I-80 WB RAMP TO PLEASANT GROVE BL RECONFIGURE I-80/SR-65 INTERCHANGE AND WIDEN SR-65 6,830,000.00 43,180,600.00
California 6203059 SR-49 FROM 0.1 MILE SOUTH OF ROUTES 49/80 SEPARATION TO 0.1 MILE NORTH OF DRY CREEK REHABILITATE PAVEMENT (TC) 1,450,000.00 34,750,000.00
California 6203060 NEAR PLACERVILLE AND CAMINO, FROM 0.2 MILE WEST OF STILL MEADOWS ROAD TO 0.4 MILE EAST OF UPPER CARSON ROAD. PM23.50 CONSTRUCT AN UNDERCROSSING AND A 6,091,900.00 30,688,902.12
California 6204105 I-580 LIVERMORE; GREENVILLE RD TO ISABEL AVE, CONSTRUCT W/B HOV LANE 6,187,759.00 73,055,000.00
California 6204113 US 101 BROADWAY INTERCHANGE IN BURLINGAME, RECONSTRUCT INTERCHANGE INCLUDE BIKE/PED FACILITY 3,613,000.00 50,647,000.00
California 6204117 WB I-80 TO SR12 CONNECTOR, INTERCHANGE RECONSTRUCTION (TC) 999,962.00 52,215,503.00
California 6204120 US 101 MARIN SONOMA NARROWS; NEAR PENTALUMA .8MIL S. TO 2MIL N. OF MARIN- SON LNS REALIGN US101 & CONSTRUCT WIDENING FOR HOV (TC) 127,845.25 55,486,000.00
California 6204123 IN SAN FRANCISCO ROUTE 101 POSTMILE 8.3 TO 9.8 PRESIDIO PKWY-PH II CONCESSIONARE PMTS P3 (TC) 34,000,000.00 34,000,000.00
California 6204127 US 101 MARIN & SONOMA CO. BETWEEN KASTANIA RD. & SOUTH OF MARIN/SONOMA COUNTY LINE CONSTRUCT HOV LANES (TC) 32,200,000.00 38,368,000.00
California 6204131 ON I-80 THROUGH THE CITIES OF FAIRFIELD AND VACAVILLE IN SOLANO COUNTY, FROM (PM) 10.4 TO 30.2 SOLANO COUNTY: I-8O FROM RED TOP RD TO I-505:CONVER 63,464,510.00 178,700,000.00
California 6204132 ON ROUTE 101, IN MARIN COUNTY, IN AND NEAR CITY OF NOVATO, FROM JUST SOUTH OF THE FRANKLIN AVENUE TO 0.3MILES SOUTH OF THE MARIN/SONOMA COUNTY LINE. 75,651,097.00 103,646,000.00
California 6205010 STATE HWY 46 CORRIDOR SAN LUIS OBISPO COUNTY ROAD WIDENING 14,510,070.80 25,734,967.65
California 6205015 ROUTE 46 CORRIDOR, ROAD WIDENING 2,477,410.47 63,244,534.42
California 6205026 IN SANTA BARBARA COUNTY, IN AND NEAR SUMMERLAND FROM 0.2 MI NORTH OF PADARO LANE OVERCROSSING TO SAN YSIDRO CREEK BRIDGE. RECONSTRUCT PAVEMENT WITH C 3,098,688.99 127,191,000.00
California 6205028 NEAR THE CITY OF SANTA CRUZ AND CAPITOLA ON HIGHWAY 1, FROM 41ST AVENUE TO SOQUEL AVENUE CONSTRUCT AUXILIARY LANES AND CONSTRUCT BICYCLE/PEDESTRIAN O 1,640,000.00 28,110,000.00
California 6205029 ON SR156 IN SAN JUAN BAUTISTA, FROM THE ALAMEDA TO 0.2 MILE EAST OF FOURTH ST. ROADWAY WIDENING 404,017.00 58,711,000.00
California 6206010 ROUTE 99 FROM GOSHEN TO KINGSBURG, WIDEN FROM 4-LANE TO 6-LANE 7,198,215.85 99,465,000.00
California 6206011 ROUTE 99 FROM GOSHEN TO KINGSBURG, WIDEN FROM 4-LANE TO 6-LANE 5,903,344.57 99,465,000.00
California 6206021 SR 46 FROM THE INTERSECTION OF LOST HILLS ROAD TO 0.9 MI. E OF I5 WIDENING FROM 2 TO 4 LANES 17,701,000.00 49,972,000.00
California 6206025 KINGS CANYON EXPRESSWAY SEGMENT 3, ON SR 180 FROM WEST OF SMITH AVENUE TO EAST OF FRANKWOOD AVENUE, PM R74.1/R78.6 CONSTRUCT 4 LANE EXPRESSWAY 2,666,318.70 53,598,170.00
California 6207028 ON SR 14:PEARBLOSSOM TO AVE P-8                                                   , CONSTRUCT HOV LANES 32,127,808.86 36,812,808.86
California 6207042 IN NORWALK AND SANTA FE SPRING(CARMENITA INT), INTERCHANGE RECONSTRUTION 98,527,001.00 179,624,855.00
California 6207046 I-5/SR-14 SEPARATION NR CITY OF SANTA CLARITA CONSTR. 2 LANE ELEV. HOV CONNE 116,062,579.72 164,015,944.00
California 6207055 I-5 : FROM RTE 134 TO MAGNOLIA BLVD HOV LANES 72,706,000.00 113,213,945.00
California 6207059 ROUTE 10: PUENTE TO CITRUS HOV LANES FROM 8 TO 10 LANES AND SOUNDWALLS (TC) 116,546,051.00 157,866,051.00
California 6207063 SR-138, SEGMENT 6, (IN LITTLEROCK FROM 87TH ST E TO 96 ST. E) WIDENING OF SR- 138 FROM 2 LANES TO 4 LANES (TC) 25,130,000.00 25,130,000.00
California 6207067 LA COUNTY LINE TO MOORPARK RD. IN THOUSAND OAKS ADD ONE LANE IN EACH DIRECTION, WIDEN RAMPS ETC. 15,417,915.00 40,083,904.38
California 6207068 ROUTE 005: (SEG. 5) ARTESIA BLVD. TO 0.4 MILE NORTH OF SAN GABRIEL RIVER BRIDGE WIDEN I-5 WITH HOV MIXED FLOW LANES ETC. (TC) 96,114,000.00 124,714,000.00
California 6207070 RT. 10 : FROM CITRUS AVE. TO RT. 57 CONSTRUCT HOV LANE IN BOTH DIRECTIONS 154,720,000.00 222,884,000.00
California 6207072 IN LOS ANGELES COUNTY FROM MAGNOLIA BLVD. TO JUST NORTH OF BUENA VISTA CONSTRUCT HOV LANES AND IC MODIFICATIONS 31,568,000.00 325,040,000.00
California 6207078 I-5 CARPOOL LANE-ORANGE COUNTY LINE TO I-605 (SEGMENT 2) IN LA MIRADA WIDEN HOV 100,079,000.00 199,898,000.00
California 6208009 LOCATION DETAILS SEGMENT 2.: IN LA MIRADA FROM ARTESIA BL TO NOR STATE ROUTE 91 FROM ADAMS STREET TO THE 60/91/215 INTERCHANGE HOV LANES 57,796,950.00 181,141,569.00
California 6208013 I-215: ORANGE SHOW RD. - RIALTO AVE. (SEG. 3) , CONSTRUCT HOV & MIXED-FLOW LANES 46,940,000.00 87,997,100.00
California 6208016 I-15/I-215 INTERCHANGE S/O GLEN HELEN PARKWAY TO KENWOOD & I-215 S/O DEVORE ROAD, RECONSTRUCT INTERCHANGE, ADD MIXED-FLOW LANES TC 65,708,000.00 258,659,000.00
California 6208018 SR 91 FROM SPRUCE ST. IN RIVERSIDE TO I-215 AT ORANGE SHOW RD. IN SAN BERNARDINO, HOV LANES, BRIDGE REPLACEMENT, ROAD REHABILITATI 44,871,000.00 180,391,000.00
California 6208023 I-215 INTERCHANGE AT BARTON ROAD IN THE CITY OF GRAND TERRACE RECONSTRUCT OVERCROSSING AND RAMPS (TC) 18,756,086.83 65,708,645.83
California 6208029 I-15 FROM 0.5 MILES N/O MOJAVE DRIVE TO 1.5 MILES N/O STODDARD WELLS ROAD, RECONSTRUCT INTERCHANGE AND FRONTAGE ROADS (TC) 3,637,000.00 84,990,000.00
California 6208032 I-10 CORRIDOR EXPRESS LANE WIDENING FROM SAN ANTONIO AVENUE IN THE CITY OF POMONA TO THE I-10/I-15 INTERCHANGE IN THE CITY OF ONTARIO, PHASE 1 QUALIT 21,300,000.00 84,926,325.00
California 6211073 IN SD C .6 KM E OF CACTUS RD & .3 KM W MEXICO , 6 LANES CONSTRUCTION 0.00 73,498,982.00
California 6211114 I15-PM R46.2/R46.8 & SR76-PM R12.1/R17.7 INTERCHANGE SR76 EAST - ROADWAY WIDENING FROM 2 TO 4 LANES 86,750,801.30 121,682,757.37
California 6211119 IN SAN DIEGO COUNTY IN SAN DIEGO ON I-5 FROM 0.4 MILES SOUTH OF GENESEE AVE OC TO THE SORRENTO VALLEY OVERHEAD REPLACE BRIDGE, RAMP, IC, BUTTRESS, BI 49,546,999.50 69,363,715.00
California 6211121 I-805 SOUTH FROM PALOMAR STREET TO SR54 CONSTRUCT NOISE WALL (TC) 31,302,000.00 32,092,210.06
California 6211126 IN IMPERIAL COUNTY IN THE CITY OF EL CENTRO AT I-8 AND IMPERIAL AVE INTERCHANGE RECONSTRUCTION OF INTERCHANGE (TC) 2,399,999.74 31,342,999.74
California 6211131 IN SAN DIEGO COUNTY AT VARIOUS LOCATIONS ALONG 1-5 FROM LOMAS SANTA FE DRIVE TO 0.5 MILE SOUTH OF PALOMAR AIRPORT ROAD REPLACE THE SAN ELIJO LAGOON B 182,074,475.00 246,122,594.00
California 6212018 INTERSTATE 405 FROM STATE ROUTE 73 TO INTERSTATE 605 ADD TOLL EXPRESS (TEL) AND MIXED-FLOW LANES IN EACH DIRECTION 36,130,000.00 256,189,516.00
California 6212021 INTERSTATE 5 FROM STATE ROUTE 73 TO OSO PARKWAY, SEGMENT 1 ADD MIXED- FLOW LANES IN EACH DIRECTION AND RECONSTRUCT THE I-5 INTERCHANGE INTERCHANGE (TC 19,848,000.00 87,810,000.00
California 6212022 INTERSTATE 5 FROM OSO CREEK TO ALICIA PARKWAY CONSTRUCT ONE GENERAL PURPOSE LANE ON EACH DIRECTION, RECONSTRUCT LA PAZ ROAD INTERCHANGE AND ADD AUXIL 43,930,000.00 158,080,000.00
California 6212024 INTERSTATE 5 FROM ALICIA PARKWAY TO EL TORO ROAD (SEGMENT 3) ADD GENERAL PURPOSE LANE, EXTEND 2ND HOV LANE IN BOTH DIRECTIONS, AND ADD AUXILIARY LANE 44,915,000.00 149,817,000.00
California 6212025 INTERSTATE 5 FROM STATE ROUTE 55 TO STATE ROUTE 57 ADD ONE HOV LANE IN EACH DIRECTION (TC) 29,603,000.00 32,843,000.00
California 6272023 YERBA BUENA ISLAND EASTSIDE WESTBOUND ON & OFF RAMPS RECONST EXISTING WB ON & OFF RAMPS ON EAST OF YBI 75,747,201.00 85,581,736.00
California 6272047 ON YERBA BUENA ISLAND, SAN FRANCISCO - I-80 ON AND OFF RAMPS APPROACH ROADWAY REALIGNMENTS 3,629,730.00 42,559,511.00
California 6303005 NOGALES ST. AT UPRR IN THE CITY OF INDUSTRY , GRADE SEPARATION ON NOGALES ST. 40,069,700.95 50,129,010.95
California 6303030 RAMONA ST, MISSION RD, DEL MAR AVE, SAN GABRIEL BL UPTO WALNUT GROVE AVE W/UPRR, CONST. 2.6M LONG RAILROAD TRENCH 12,404,576.45 399,597,000.00
California 6303032 NOGALES ST. AT RAILROAD STREET/UPRR(SCRRA) GRADE SEPERATION 20,502,039.70 66,260,431.70
California 6303039 DURFEE AVENUE AT UPRR (LA SUBDIVISION) IN CITY OF PICO RIVERA CONSTRUCTION OF RAIL ROAD GRADE SEPARATION 19,737,808.21 78,030,062.20
California 6480017 IN THE CITY OF OAKLAND, WITHIN THE PORT OF OAKLAND'S SEAPORT FACILITIES AND ADJACENT AREA IN THE CITY OF OAKLAND ALONG WEST GRAND AVE., MARITIME HAR 9,741,364.11 28,562,849.11
California 6507003 MOUNT VERNON AVENUE OVERHEAD AT THE BURLINGTON NORTHERN SANTA FE RAILROAD YARD FROM KING STREET TO 5TH STREET, BR. NO. 54C-0066 BRIDGE REPLACEMENT 28,218,653.00 224,564,085.00
California 6507011 I-10 CORRIDOR EXPRESS LANE WIDENING FROM SAN ANTONIO AVENUE IN THE CITY OF POMONA TO THE I-10/I-15 INTERCHANGE IN THE CITY OF ONTARIO, PHASE 1 DESIGN 22,570,956.00 33,438,891.00
California 6801079 IN FREMONT AND AT SUNOL FROM MISSION BOULEVARD SEPARATION TO KOOPMAN ROAD UNDERCROSSING. ROADWAY REHABILITATION, BRIDGE REPLACEMENT, RETAINING WALLS, 32,796,100.00 145,178,000.00
California 6801081 IN FREMONT FROM SOUTH OF SCOTT CREEK ROAD TO AUTO MALL PARKWAY. RAMP METERING (TC) 27,415,200.00 27,916,900.00
California 6801082 CONTRA COSTA COUNTY ON I-680 FROM NORTH MAIN STREET TO LIVORNA IN THE SOUTHBOUND DIRECTION. CONSTRUCT AN HOV LANE 14,759,200.00 76,295,900.00
California 6801946 ALAMEDA COUNTY AT SUNOL AND IN PLEASANTON AND DUBLIN PRECAST CONCRETE PAVEMENT AND HMA 0.00 75,364,000.00
California 7101807 IN THE CITY OF LONG BEACH AT THE GERALD DESMOND BRIDGE BRIDGE REPLACEMENT 394,303,000.00 836,532,728.00
California 7101809 ON RTE 710 FROM LOS ANGELES RIVER BRIDGE TO RAMONA BLVD UNDERCROSSING PAVE AND WIDEN ROADWAY AND BRIDGES (TC) 174,024,056.52 174,479,456.52
California 7101839 IN BELL, VERNON, COMMERCE AND EAST LOS ANGELES, FROM 0.2 MILES SOUTH OF SLAUSON AVENUE OVERCROSSING TO 0.1 MILES NORTH OF 3RD STREET OVERCROSSING, . 112,901,800.00 113,434,400.00
California 8051640 IN SAN DIEGO COUNTY IN CHULA VISTA AND NATIONAL CITY FROM 0.2 MILE SOUTH OF SWEETWATER RIVER BRIDGE TO ROUTE 805/54 SEPARATION. UPGRADE BRIDGE RAILS, 0.00 25,209,100.00
California 8801053 I-880 AT COLEMAN AVENUE INTERCHANGE , RECON 880/COLEMAN                             (2004A GARVEE) 0.00 71,460,660.00
California 8801070 IN OAKLAND FROM SOUTH OF 29TH AVENUE TO NORTH OF 23RD AVENUE IMPROVE ON AND OFF RAMPS (TC) 78,497,887.00 79,331,752.00
California 8801074 IN ALAMEDA COUNTY FROM 0.4 MI S/O FREMONT BLVD O/C TO 0.3 MI S/O HIGH STREET INSTALL MEDIAN CONCRETE BARRIER 41,717,500.62 67,955,933.93
California 8801081 IN AND NEAR FREMONT, UNION CITY, HAYWARD, SAN LEANDRO, AND OAKLAND FROM 0.4 MILE NORTH OF FREMONT BOULEVARD OVERCROSSING TO HIGH STREET SEPARATION AN 61,935,300.00 64,663,400.00
California A905019 IN SD 1.2 KM E/O 805/905 TO 0.8KM E/O BRI. OC , CON 73,654,279.62 74,477,833.62
California E2CA018 WALERGA RD AT DRY CREEK BR #19C-159 BRIDGE REPLACEMENT 31,231,307.00 36,721,268.00
California ERI8005 IN MARIPOSA COUNTY ABOUT 8 MILES WEST OF EL PORTAL FROM 1.2 MILES WEST OF SOUTH FORK MERCED RIVER BRIDGE TO 0.5 MILE WEST OF SOUTH FORK MERCED RIVER 0.00 30,717,000.00
California NBIL512 FOOTHILL RD (1.5 MI W OF SR33) @ CUYAMA RIVER, SANTA BARBARA COUNTY. REPLACE LWC #00L0047 WITH 2-LANE BRIDGE (TC). 2,585,000.00 25,960,300.00
California NBIS017 STATEWIDE BRIDGE INSPECTION & MANAGEMENT (TC) 33,000,000.00 33,000,000.00
California NBIS018 STATEWIDE BRIDGE INSPECTION & MANAGEMENT 34,664,063.22 39,155,240.00
California P001529 MEN CO;NR FORT BRAGG;N & S OF TEN MILE RV BR , REPLACE BRIDGE, REALIGN ROADWAY 18,939,549.00 54,949,796.00
California P001590 SLO CO ABOUT 9 MI N OF SAN SIMEON FR PIEDRAS BLANCAS LIGHTHOUSE RD TO ARROYO... CONSTRUCT 3 BRIDGES & REALIGN 2 LANE HIGHWAY (TC) 30,723,700.00 30,908,500.00
California P001649 SANTA CRUZ COUNTY IN AND NEAR SANTA CRUZ FROM NORTH APTOS UP TO JUNCTION ROUTE 9. COLD PLANE AND RESURFACE PAVEMENT, UPGRADE RAILING AND BARRIERS. 24,074,787.03 30,114,900.04
California P001662 MONTEREY COUNTY FROM TORRE CANYON BRIDGE NEAR BIG SUR TO SAN LUIS AVENUE IN CARMEL. RHMA OVERLAY ON EXISTING ROADWAY AND UPGRADE GUARDRAIL. 24,668,600.00 28,328,000.00
California P001675 SANTA CRUZ COUNTY IN AND NEAR CITY OF CAPITOLA FROM 0.2 MILE SOUTH OF 41ST AVENUE OVERCROSSING TO 0.2 MILE NORTH OF SOQUEL DRIVE OVERCROSSING. CONSTR 0.00 31,870,000.00
California P012106 IN NAPA COUNTY FROM STATE ROUTE 29 TO 0.1 MILE WEST OF SOLANO COUNTY LINE, WIDEN HWY TO 4 LANES AND CONSTR RET WALLS 20,510,000.00 39,033,684.00
California P012107 IN NAPA AND SOLANO COUNTIES FROM 0.5 MILE WEST OF NAPA CO LINE TO RED TOP ROAD., WIDEN RTE 12 FROM 2 TO 4 LANE CONV HWY 7,985,146.00 49,784,651.00
California P012112 IN SJ COUNTY NEAR TERMINOUS FROM MOKELUMNE RIVER BRIDGE TO POTATO SLOUGH BRIDGE PAVEMENT REHABILITATION AND WIDENING (TC) 53,429,122.00 53,700,760.00
California P014081 IN KERN COUNTY AT AND NEAR ROSAMOND AND MOJAVE FROM 1.4 MILES SOUTH OF DAWN ROAD OVERCROSSING TO 0.5 MILE NORTH OF SILVER QUEEN ROAD OVERCROSSING. CO 44,616,500.00 50,941,700.00
California P017117 SANTA CLARA COUNTY IN AND NEAR LOS GATOS AND SAN JOSE FROM HEBARD ROAD TO ROUTE 17/280 SEPERATION COLD PLAN AND PAVE AC, REMOVE AND INSTALL CULVERTS, 0.00 58,733,500.00
California P020184 NEAR YUBA CITY, FROM EAST END OF SUTTER BYPASS TO LYTLE ROAD. REHABILITATE ROADWAY, WIDEN SHOULDERS, AND REPLACE WADSWORTH CANAL BRIDGE NO.I8-0003. T 23,097,900.00 26,246,200.00
California P020189 NEAR SMARTSVILLE, FROM THE YUBA RIVER BRIDGE TO EAST OF SMARTSVILLE ROAD. REALIGN AND WIDEN ROADWAY. THE NEED FOR THE FOLLOWING IMPROVEMENTS ARE ANAL 39,900,700.00 44,855,100.00
California P020191 NEAR MARYSVILLE, FROM MARYSVILLE ROAD TO YUBA RIVER (PARKS BAR) BRIDGE. REHABILITATE ROADWAY. EXTEND SERVICE LIFE OF PAVEMENT, BRING HIGHWAY GEOMETRI 40,665,500.00 46,500,100.00
California P020196 NEVADA COUNTY NEAR OMEGA AT VARIOUS LOCATIONS FROM 0.2 MILE WEST OF CONSERVATION ROAD (WASHINGTON RIDGE ROAD) TO 1.2 MILES WEST OF ZIEBRIGHT ROAD. RO 0.00 49,914,000.00
California P020198 IN MENDOCINO COUNTY NEAR UKIAH FROM 0.3 MILE WEST OF RUSSIAN RIVER BRIDGE AND OVERHEAD TO 0.4 MILE EAST OF COUNTY ROAD 144 REPLACE TWO BRIDGES 0.00 36,949,000.00
California P023041 IN VENTURA COUNTY, ON STATE ROUTE 23, PM R3.3/R11.5. IN AND NEAR CITIES OF THOUSAND OAKS AND MOORPARK, FROM ROUTE 101 TO ROUTE 118. REHABILITATE PAVE 0.00 91,342,600.00
California P024029 RT 24 FROM CALDECOTT TUNNEL TO EL CURTOLA O/C, ROADWAY REHABILITATION 41,284,906.00 46,634,305.00
California P029148 IN LAKE COUNTY NEAR KELSEYVILLE ON RTE 29 FROM 0.6 MI TO 3.7 MILES NORTH OF RTE 281 AND ON RTE 175 FROM SOUTH JCT RTE 29 TO 0.3 MI EAST OF SO JCT RTE 60,679,000.00 68,278,700.00
California P047010 LOS ANGELES COUNTY LONG BEACH - SCHUYLER HEIM BRIDGE #53-2618 - REPLACE BRIDGE SCHYULER HEIM BRIDGE REPLACEMENT (TC) 368,659,356.00 368,785,856.00
California P049177 IN AUBURN, FROM 0.1 MILE SOUTH OF ROUTES 49/80 SEPARATION TO 0.1 MILE NORTH OF DRY CREEK ROAD. REHABILITATE PAVEMENT 30,494,000.00 35,017,400.00
California P050139 IN SOUTH LAKE TAHOE, NORTH OF ROUTE 89 TO TROUT CREEK BRIDGE. WATER QUALITY IMPROVEMENTS - (TC) 41,368,400.00 42,093,600.00
California P050152 (03-4E620) NEAR PLACERVILLE AND CAMINO, FROM 0.2 MILE WEST OF STILL MEADOWS ROAD TO 0.4 MILE EAST OF UPPER CARSON ROAD. INSTALL MEDIAN BARRIER, WIDEN 27,348,100.00 36,018,900.00
California P050154 IN SACRAMENTO COUNTY ON ROUTE 50 FROM I-5 JUNCTION TO WATT AVE. ADD HIGH OCCUPANCY VEHICLE LANE AND PAVEMENT REHAB. 54,496,300.00 434,546,200.00
California P057067 IN ORANGE COUNTY, IN BREA, FROM 0.6 MILE SOUTH TO 0.7 MILE NORTH OF LAMBERT ROAD UNDERCROSSING INTERCHANGE IMPROVEMENT 63,147,650.00 71,876,400.00
California P057069 LA-057, IN LOS ANGELES COUNTY IN DIAMOND BAR AND CITY OF INDUSTRY FROM ORANGE COUNTY LINE TO ROUTE 57/60 SEPARATION THE PROJECT IS LOCATED IN LOS ANG 0.00 80,120,300.00
California P058119 ON STATE ROUTE 58 IN SAN BERNARDINO COUNTY A HENKLEY *** RECONSTRUCTION (2 LANE TO 4 LANE EXPRESSWAY) (TC) 139,313,220.00 139,827,720.00
California P058126 NEAR BAKERSFIELD FROM COTTONWOOD ROAD UNDERCROSSING TO 0.3 MILE EAST OF ROUTE 58/184 SEPARATION. CONSTRUCT CRCP, HMA PAVEMENT, MGS, AND MODIFYING ELE 39,401,100.00 39,628,100.00
California P058127 IN SAN BERNARDINO FROM 0.4 MI W/O KERN CO LINE TO 7.5 MI E/O JCT 395 (KRAMER) CONSTRUCT 4-LANE DIVIDED EXPW ON NEW ALIGNMENT; SR 08/USR 395 IC & RR O 207,775,600.00 208,375,000.00
California P058128 KERN COUNTY IN BAKERSFIELD FROM RTE 58/99 SEPARATION TO COTTONWOOD ROAD UNDERCROSSING REPLACE LANES AND SHOULDERS WITH CONTINUOUSLY REINFORCED CONCRE 28,516,300.00 29,022,400.00
California P060153 IN SAN BERNARDINO COUNTY IN AND NEAR CHINO AT VARIOUS LOCATIONS FROM 0.1 MI WEST OF PIPELINE AVE OC TO 0.1 MI EAST OF BENSON AVE OC REMOVE AND REPLA 0.00 26,041,300.00
California P060154 IN RIVERSIDE COUNTY NEAR BEAUMONT ON SR 60 FROM GILMAN SPRINGS ROAD OVERCROSSING TO 1.4 MILES WEST OF JACK RABBIT TRAIL. CONSTRUCT A TRUCK CLIMBING L 62,120,400.00 121,915,500.00
California P060155 IN SAN BERNARDINO AND RIVERSIDE COUNTIES IN ONTARIO, JURUPA VALLEY AND RIVERSIDE, FROM EUCLID AVENUE UNDERCROSSING TO ROUTE 60/91/215 SEPARATION. REP 0.00 162,158,000.00
California P060159 IN SAN BERNARDINO COUNTY IN ONTARIO FROM 0.2 MILE WEST OF CUCAMONGA CREEK BRIDGE TO MILLIKEN AVENUE ADD WEST BOUND AUXILIARY LANE, ADD EAST- BOUND DEC 0.00 32,806,300.00
California P062046 IN RIVERSIDE AND SAN BERNARDINO COUNTIES IN AND NEAR YUCCA VALLEY AND IN TWENTYNINE PALMS FROM 0.2 MILE NORTH OF INDIAN CANYON DRIVE TO 0.6 MILE WEST 0.00 30,011,400.00
California P065108 IN AND NEAR ROSEVILLE AND ROCKLIN, FROM ROUTE 80 TO 0.5 MILES SOUTH OF PLEASANT GROVE OVERCROSSING INCLUDING WIDENING OF THE GALLERIA BLVD/STANFORD R 24,480,600.00 43,180,600.00
California P070094 SUT/YUB CO'S;NR NICOLAUS;FR 70/99 SEP TO * , WIDEN & REALIGN ROADWAY 79,879,899.00 90,255,065.00
California P070137 NEAR MARYSVILLE, FROM 0.1 MILE NORTH OF BINNEY JUNCTION UNDERPASS TO 0.3 MILE NORTH OF LAURELLEN ROAD, AT SIMMERLY SLOUGH BRIDGE NO. I 6-00 I 9. REPL 44,482,700.00 50,845,800.00
California P070143 IN YUBA AND BUTTE COUNTIES ABOUT 11 MILES NORTH OF MARYSVILLE FROM 0.8 MILE NORTH OF CHANDLER ROAD TO 0.2 MILE SOUTH OF EAST GRIDLEY ROAD WIDEN ROADW 0.00 48,518,000.00
California P070144 YUBA COUNTY NEAR MARYSVILLE FROM 0.2 MILE NORTH OF LAURELLEN ROAD TO SOUTH HONCUT CREEK BRIDGE WIDEN SHOULDERS AND IMPROVE CLEAR RECOVERY ZONE. 0.00 108,710,800.00
California P074067 IN RIVERSIDE COUNTY ON ROUTE 74 FROM 0.6 MILES EAST OF ROUTE 215 TO 0.8 MILES WEST OF ACACIA AVENUE IN THE CITY OF HEMET CONSTRUCT RAISED CURB MEDIAN 25,014,020.00 28,130,900.00
California P074071 ORANGE COUNTY NEAR SAN JUAN CAPISTRANO FROM 1.0 MILE WEST OF SAN JUAN HOT SPRINGS ROAD TO ORANGE COUNTY LINE APPLY HFST, OVERLAY OGAC AND INSTALL MGS 25,766,000.00 29,137,100.00
California P084042 IN/NEAR LIVERMORE & PLEASANTON FROM S/O RUBY HILL DRIVE TO N/O CONCANNON BLVD WIDEN AND UPGRADE 2.8 MILES OF SR 84 (TC) 46,709,000.00 53,248,900.00
California P084054 ALAMEDA COUNTY NEAR FREMONT AT ALAMEDA CREEK BRIDGE REPLACE BR PAVING, SOIL NAIL WALL, DRAINAGE & CHANNEL RESTORATION 21,851,100.00 25,221,800.00
California P089102 NEAR TAHOE CITY FROM 0.2 MI SOUTH OF ED/PLA COUNTY LINE TO TRUCKEE RIVER BRIDGE PAVEMENT REHAB/ DRAINAGE SYSTEM IMPROVEMENT- (TC) 49,472,273.00 50,713,238.00
California P099629 STANISLAUS COUNTY AT VARIOUS LOCATIONS FROM 0.1 MILE NORTH OF MERCED STANISLAUS COUNTY LINE TO 0.2 MILE SOUTH OF STANISLAUS SAN JOAQUIN COUNTY LINE C 13,985,600.00 28,348,000.00
California P099635 MADERA COUNTY IN AND NEAR MADERA FROM AVENUE 12 OVERCROSSING TO 0.9 MILE NORTH OF AVENUE 17 OVERCROSSING REHABILITATE PAVEMENT AND CONSTRUCT NEW LANE 58,293,200.00 65,925,900.00
California P099636 KERN COUNTY NEAR WHEELER RIDGE FROM 0.8 MILE SOUTH OF ROUTE 5/99 SEPARATION TO 0.3 MILE NORTH OF OLD US 99 OVERCROSSING REPLACE CONCRETE PAVEMENT LAN 58,859,700.00 71,341,800.00
California P099637 IN GALT, FROM THE SAN JOAQUIN COUNTY LINE TO SIMMERHOM ROAD; ALSO, IN THE CITIES OF ELK GROVE AND SACRAMENTO, FROM 0.7 MILE SOUTH OF ELK GROVE BOULEV 34,977,800.00 39,752,800.00
California P099639 MERCED COUNTY IN AND NEAR LIVINGSTON FROM 0.8 MILE SOUTH OF HAMMATT AVENUE OVERCROSSING TO STANISLAUS COUNTY LINE NORTHBOUND LANE WIDENING FROM 2 TO 29,166,100.00 41,803,800.00
California P099644 FRESNO COUNTY IN AND NEAR KINGSBURG AND SELMA FROM ROUTE 99/201 SEPARATION TO 0.3 MILES SOUTH OF SECOND STREET UNDERCROSSING. REPLACE CONCRETE AND AS 35,418,100.00 40,420,100.00
California P099646 MERCED COUNTY IN AND NEAR ATWATER FROM 0.4 MILE SOUTH OF BUHACH OVERCROSSING TO 0.8 MILE NORTH OF WEST ATWATER OVERHEAD REPLACE CONCRETE AND ASPHALT 1,396,600.00 72,340,200.00
California P099654 IN SUTTER COUNTY, IN AND NEAR LIVE OAK, FROM SOUTH OF COLEMAN AVENUE TO NEVADA STREET (NORTH INTERSECTION). REHABILITATE PAVEMENT, IMPROVE PEDESTRIAN 22,843,100.00 34,163,100.00
California P099660 KERN COUNTY, IN AND NEAR BAKERSFIELD, FROM 0.4 MILE SOUTH OF OLD US-99 OVERCROSSING TO 0.1 MILE NORTH OF WHITE LANE OVERCROSSING. RECONSTRUCT CONCRE 54,176,800.00 61,831,100.00
California P099662 MERCED COUNTY IN MERCED FROM 0.2 MILE SOUTH OF CHILDS AVENUE OVERCROSSING TO 0.2 MILE SOUTH OF FRANKLIN ROAD OVERCROSSING RECONSTRUCT PAVEMENT 54,775,200.00 62,124,100.00
California P099663 IN SACRAMENTO COUNTY IN AND NEAR ELK GROVE FROM 0.3 MILE SOUTH OF DILLARD ROAD OVERCROSSING TO 0.6 MILE SOUTH OF GRANT LINE ROAD. REMOVE AND REPLACE 0.00 73,158,900.00
California P099665 TULARE COUNTY IN AND NEAR TULARE FROM PROSPERITY AVENUE TO 1.2 MILES SOUTH OF AVENUE 280 OVERCROSSING WIDEN FREEWAY FROM FOUR TO SIX LANES 59,190,000.00 67,376,000.00
California P099666 FRESNO COUNTY IN AND NEAR SELMA AND FOWLER FROM MCCALL AVENUE UNDERCROSSING TO 0.5 MILE NORTH OF MERCED STREET UNDERCROSSING. RECONSTRUCT CONCRETE PA 71,509,800.00 81,481,800.00
California P099669 SACRAMENTO COUNTY IN AND NEAR ELK GROVE FROM 0.3 MILE SOUTH OF DILLARD ROAD OVERCROSSING TO 0.6 MILE SOUTH OF GRANT LINE ROAD BRIDGE REPLACEMENT AND 50,329,800.00 57,173,100.00
California P118065 IN AND NEAR THE CITY OF LOS ANGELES, FROM COUNTY LINE TO ROUTE 210; ALSO ON ROUTE 27 (TOPANGA CANYON BLVD) FROM DEVONSHIRE STREET TO ROUTE 118. REHAB 26,431,500.00 26,633,900.00
California P132050 SAN JOAQUIN COUNTY NEAR VERNALIS FROM 0.4 MILE EAST OF ROUTE 580 TO STANISLAUS COUNTY LINE REPAIR PAVEMENT AND INSTALL ITS ELEMENTS (TC) 29,773,992.00 30,210,800.00
California P134040 IN LOS ANGELES COUNTY IN CITIES OF LOS ANGELES, BURBANK, GLENDALE AND PASADENA FROM 0.0 MILE EAST OF ROUTE 101/134 SEPARATION TO JUNCTION OF ROUTE 21 0.00 43,785,600.00
California P138049 IN SAN BERNARDINO COUNTY ON STATE ROUTE 138 NEAR PHELAN *** ROADWAY RECONSTRUCTION (ADDED CAPACITY) (TC) 63,153,528.00 63,678,528.00
California P138055 NEAR HESPERIA FROM 1.9 MI E/O RTE 15 TO 0.1 MI W/O SUMMIT POST OFFICE ROAD REALIGN AND CONSTRUCT 2-LANE PAVED SECTION WITH OUTSIDE SHOULDERS, 3 WILDL 22,578,900.00 32,975,900.00
California P162041 GLENN COUNTY AT BUTTE CITY FROM ROUTE 45 TO 0.1 MILE EAST OF MCDOUGAL STREET REPLACE BRIDGE 11-0017 & VIADUCT APPROACH, RECONSTRUCT ROADWAY 0.00 98,488,000.00
California P198077 TULARE COUNTY, IN AND NEAR VISALIA, FROM LOVERS LANE UNDERCROSSING TO 0.1 MI EAST OF FRIANT-KERN CANAL BRIDGE REMOVE AND REPLACE HMA PAVEMENT AND MO 26,491,600.00 26,765,100.00
California P210016 IN SAN BERNARDINO COUNTY IN SAN BERNARDINO, HIGHLAND, AND REDLANDS FROM 0.1 MILE WEST OF DEL ROSA AVENUE TO LUGONIA AVENUE BASELINE INTERCHANGE IMPRO 47,764,600.00 149,679,901.00
California P299185 IN SHASTA COUNTY ABOUT 20 MILES WEST OF REDDING FROM 0.3 MILE EAST OF TRINITY COUNTY LINE TO 0.9 MILES WEST OF CRYSTAL CREEK ROAD. HIGHWAY REALIGNMEN 44,998,502.00 45,932,442.00
California P395236 IN SBD COUNTY FR 7.9 MI N/O SR-18 TO 10.4 MI S/O KRAMER JCT (RTE)58 WIDEN MEDIAN & SHOULDERS, CONSTRUCT TURNOUTS (TC) 31,415,318.00 32,032,678.00
California P395276 IN SAN BERNARDINO COUNTY IN ADELANTO AND IN VICTORVILLE ON ROUTE 395 FROM ROUTE 18-PALMDALE ROAD TO CHAMBERLAINE WAY WIDEN HIGHWAY FROM TWO TO FOUR L 9,547,000.00 31,613,553.00
California P395348 IN INYO COUNTY NEAR OLANCHA AND CARTAGO FROM 1.4 MILES SOUTH OF LOS ANGELES AQUEDUCT BRIDGE TO 0.2 MILE SOUTH OF ASH CREEK BRIDGE. CONSTRUCT 4 LANE E 0.00 92,966,000.00
California Q101153 SF ON RTE 101 FROM PM 8.8-9.2, DOYLE DR REPL REPLACE/REHABILITATE ROADWAY 122,574,329.58 160,696,807.58
California Q101237 IN SAN MATEO COUNTY ON US 101 IN THE CITY OF BURLINGAME RECONFIGURE THE BROADWAY INTERCHANGE (TC) 19,989,548.00 60,223,732.00
California Q101247 IN AND NEAR THE CITIES OF LOS ANGELES, CALABASAS AND AGOURA HILLS FROM SR170 TO REHABILITATION PAVEMENT CONDITIONS (TC) 63,199,100.39 63,408,100.39
California Q101261 MRN & SON COUNTIES ON US 101 SAN ANTONIO CURVE CORRECTION (TC) 75,275,041.00 75,791,241.00
California Q101290 SANTA BARBARA COUNTY IN CARPINTERIA FROM 0.2 MILE SOUTH OF CARPINTERIA CREEK BRIDGE TO FRANKLIN CREEK BRIDGE RECONSTRUCT 3 BRIDGES, CONSTRUCT 1 BRIDG 54,846,100.00 80,591,000.00
California Q101306 SAN LUIS OBISPO AND MONTEREY COUNTIES NEAR PASO ROBLES FROM 0.5 MILE SOUTH OF SAN MARCOS CREEK BRIDGE TO 0.2 MILE SOUTH OF BRADLEY ROAD OVERCROSSING. 69,860,400.00 70,452,900.00
California Q101338 MONTEREY COUNTY IN AND NEAR KING CITY FROM 0.4 MILE SOUTH OF WILD HORSE ROAD OVERCROSSING TO TEAGUE AVENUE CONSTRUCT CONTINUOUS REINFORCED CONCRETE P 81,681,100.00 105,748,900.00
California Q101342 MONTEREY COUNTY IN SALINAS FROM EAST MARKET STREET UNDERCROSSING TO 0.3 MILE SOUTH OF ESPINOSA ROAD RECONSTRUCT, CRACK AND SEAT PAVEMENT AND RECONSTR 41,570,900.00 47,437,600.00
California Q101348 MONTEREY COUNTY NEAR SAN LUCAS FROM 0.1 MILE SOUTH OF PARIS VALLEY ROAD OVERCROSSING TO RANCHO UNDERCROSSING CONSTRUCT CONTINUOUSLY REINFORCED CONCRE 27,497,400.00 31,230,600.00
California Q101350 MONTEREY COUNTY NEAR CHUALAR FROM 0.5 MILE NORTH OF NORTH GONZALES OVERCROSSING TO EAST MARKET STREET UNDERCROSSING REPLACE CONCRETE PANEL AND RESURF 26,578,449.00 30,164,400.00
California Q101353 SONOMA COUNTY IN PETALUMA FROM ROUTE 101/116 SEPERATION TO 0.4 MILE NORTH OF CORONA ROAD OVERCROSSING ROADWAY, BRIDGES, RETAINING WALLS, SOUND WALL A 0.00 104,750,100.00
California Q101363 THE CITY AND COUNTY OF LOS ANGELES FROM PILGRIMAGE OVERCROSSING TO VALLEY CIRCLE BOULEVARD OVERCROSSING; UPGRADE MEDIAN CONCRETE BARRIER TO MEET THE 43,822,300.00 44,130,700.00
California Q101365 SONOMA COUNTY AT VARIOUS LOCATIONS FROM LIMERICK LANE OVERCROSSING TO ROUTE 101/128 SEPARATION. CRACK, SEAT AND OVERLAY, AND REHABILITATE AND REPLACE 0.00 87,903,000.00
California Q101366 THE CITY AND COUNTY OF SAN FRANCISCO AT ALEMANY CIRCLE UNDERCROSSING REPLACE BRIDGE DECK 12,265,254.00 43,170,200.00
California Q101373 SANTA BARBARA COUNTY IN CARPINTERIA FROM 0.2 MILE SOUTH OF BAILARD AVENUE OVERCROSSING TO 0.7 MILE SOUTH OF SOUTH PADARO LANE. CONSTRUCT HOV LANES AN 48,147,600.35 108,459,352.52
California Q101379 CITY AND COUNTY OF SAN FRANCISCO FROM THE SAN MATEO COUNTY LINE TO THE BAYSHORE VIADUCT COLD PLANE AND OVERLAY WITH RHMA. REPLACE EXISTING PCC SLAB. 22,612,400.00 25,361,400.00
California Q101381 SANTA BARBARA COUNTY IN AND NEAR SUMMERLAND FROM 0.2 MILE NORTH OF PARDARO LANE OVERCROSSING TO SAN YSIDRO CREEK BRIDGE. CONSTRUCT NEW HOV LANES AND 39,857,600.00 127,191,000.00
California Q101385 VEN-101- IN VENTURA COUNTY, ON STATE ROUTE 101, PM R36.3/R40.6. NEAR SEA CLIFF, FROM 0.4 MILE SOUTH OF PADRE JUAN CANYON ROAD OVERCROSSING TO 0.3 MIL 38,098,900.00 43,287,200.00
California Q101389 THE CITY AND COUNTY OF SAN FRANCISCO FROM 17TH STREET TO SOUTH VAN NESS AVENUE CLEAN AND PAINT STEEL STRUCTURE 0.00 38,493,100.00
California Q101394 IN HUMBOLDT COUNTY NEAR EUREKA FROM EUREKA SLOUGH BRIDGE TO BAYSIDE CUTOFF UPGRADE 4-LANE FACILITY 0.00 58,721,000.00
California Q101395 SANTA BARBARA COUNTY IN AND NEAR CARPINTERIA AND AT SUMMERLAND FROM 0.9 MILE SOUTH OF SOUTH PADARO LANE UNDERCROSSING TO 0.6 MILE NORTH OF PADARO LANE 0.00 193,632,000.00
California Q101398 IN DEL NORTE COUNTY NEAR CRESCENT CITY FROM 0.3 MILE SOUTH OF SMITH RIVER BRIDGE TO 0.4 MILE NORTH OF SMITH RIVER BRIDGE REPLACE BRIDGE 0.00 78,032,000.00
California Q101399 IN HUMBOLDT COUNTY IN AND NEAR TRINIDAD FROM 1.3 MILES SOUTH OF SCHOOL ROAD OC TO 0.4 MILE NORTH OF BIG LAGOON BRIDGE CAPITAL PREVENTATIVE MAINTENANC 0.00 34,300,000.00
California S036115 IN LASSEN COUNTY NEAR WESTWOOD FROM 1.3 MILES WEST OF GOODRICH CREEK BRIDGE TO 1.0 MILE WEST OF WILLARD CREEK ROAD. REHABILITATE ROADWAY AND REPLACE 33,295,000.00 37,854,700.00
California S074071 IN RIVERSIDE COUNTY NEAR LAKE ELSINORE FROM ORANGE/RIVERSIDE COUNTY LINE TO MONTE VISTA STREET WIDEN EXISTING LANES TO PROVIDE 12' LANES, 4' SHOULDER 45,413,100.00 51,089,100.00
California S087026 IN SAN JOSE RT 87 FROM JULIAN ST TO 280 U/C , WIDEN FWY (4 TO 6)                                  (2004A GARVEE) 0.00 27,948,674.00
California S180059 IN FRESNO COUNTY ABOUT 8.4 MILES EAST OF FRESNO FROM 0.7 MILE WEST OF SMITH AVENUE TO 0.7 MILE EAST OF FRANKWOOD AVENUE. CONSTRUCT 4 LANE EXPRESSWAY 39,274,300.00 65,206,600.00
California X023033 HUM CO;NR MCKIN'LYVL;SR-101;FR 0.2 KM S/O * REPLACE BRIDGES 46,858,060.00 52,929,020.00
California X029126 KERN COUNTY NEAR INDIAN WELLS ON ROUTE 14 FROM 2.4 MILES SOUTH OF JUNCTION ROUTE 178 TO 1.7 MILES NORTH OF JUNCTION ROUTE 178 AND ON ROUTE 178 FROM R 27,853,200.00 28,251,600.00
California X029141 KERN COUNTY IN THE CITY OF BAKERSFIELD ON ROUTE 99 FROM 0.3 MILE SOUTH OF BELLE TERRACE OVERCROSSING TO 0.1 MILE NORTH OF ROUTE 58; ALSO ON ROUTE 58 0.00 40,522,000.00
California X029143 KERN COUNTY IN BAKERSFIELD ON ROUTE 99 FROM 0.3 MILE SOUTH OF PALM AVENUE OVERCROSSING TO BEARSLEY CANAL BRIDGE AND ON ROUTE 178 AT ROUTE 99/178 SEP 41,404,800.00 83,744,700.00
California X029144 KERN COUNTY IN THE CITY OF BAKERSFIELD ON RTE 58 AND RTE 99 FROM 0.1 MILE WEST OF RTE 99 TO 0.2 MILE EAST OF RTE 99 AND FROM 0.3 MILE SOUTH OF MING A 25,000,000.00 58,633,355.00
California X029147 KERN COUNTY IN THE CITY OF BAKERSFIELD ON ROUTE 58 FROM 0.1 MILE WEST OF MOHAWK STREET TO COTTONWOOD ROAD AND ROUTE 99 FROM 0.8 MILE SOUTH OF ROUTE 5 0.00 186,679,411.00
California X037165 NEAR THOUSAND OAKS, FROM VENTURA CNTY LINE TO RTE 101/23 INTERCHANGE , INTERCHANGE IMPROVEMENT 16,646,289.49 38,055,456.00
California X037169 IN LOS ANGELES COUNTY AT VARIOUS LOCATIONS REPLACE AND REPAIR ELEC WIRE (TC) 28,750,000.00 28,750,000.00
California X037199 IN LOS ANGELES COUNTY IN AND NEAR CARSON ON ROUTE 110 FROM 0.2 MILE NORTH OF TORRANCE BLVD UC TO 190TH STREET UC AND ON ROUTE 405 FROM MAIN STREET UC 25,656,200.00 25,930,700.00
California X037204 IN LOS ANGELES COUNTY ON ROUTES 2, 5, 10, 47, 90, 91, 105, 110, 405, 605 AND 710 REPAIR AND REPLACE THE PROJECT WILL IS MAXIMIZE THE USE OF THE EXI 29,044,200.00 29,044,200.00
California X037211 IN LOS ANGELES CONUTY ON ROUTE 60 FROM 0.5 MILE WEST OF 60/710 SEPARATION TO ROUTE 60/605 SEPARATION AND ON ROUTE 710 FROM 0.5 MILE SOUTH OF 710/60 32,910,097.00 175,051,477.00
California X037218 IN LOS ANGELES COUNTY, AT VARIOUS LOCATIONS UPGRADE EXISTING TRAFFIC MANAGEMENT COMMUNICATION SYSTEM UPGRADE EXISTING TRAFFIC MANAGEMENT COMMUNICATIO 33,916,000.00 38,613,000.00
California X059083 IN ORANGE COUNTY AT VARIOUS LOCATIONS UPGRADE AND INSTALL INTELLIGENT TRANSPORTATION SYSTEM (ITS) ELEMENTS. 0.00 25,171,300.00
California X071063 IN SAN BERNARDINO COUNTY NEAR DEVORE ON INTERSTATE ROUTES 15 AND 215 *, 1-15/1-215 DEVORE INTERCHANGE IMPROVEMENT ** 134,351,000.00 266,213,136.00
California X071071 IN SAN BERNARDINO COUNTY ON ROUTE 62 FROM 3.8 MILES WEST OF ROUTE 95 TO ARIZONA STATE LIN AND ON ROUTE 95 FROM ROUTE 62 TO 2.0 MILES SOUTH OF TURTLE 24,047,800.00 27,490,700.00
California X075027 SF 101/1 SEPARATION TO GOLDEN GATE TOLL PLAZA REPLACE/REHABILITATE ROADWAY 82,124,382.00 104,451,807.00
California X075041 IN SAN FRANCISCO ROUTE 101 POSTMILE 8.3 TO 9.8 PRESIDIO PKWY-PHASE II CONCESSIONAIRE PMTS P3 (TC) 188,339,626.16 731,328,837.00
California X075046 IN SAN FRANCISCO ROUTE 101 POSTMILE 8.3 TO 9.8 PARK PRESIDIO P3, DEPT DIRECTED CHANGES& SUPPT(TC) 156,252,688.00 169,572,970.00
California X077014 SJ CO RTE205 IN TRACY 0.6KM W/11TH ST OC RTE5 WIDEN 4 LANE TO 6 LANE FREEWAY 72,879,005.00 90,778,579.00
California X077023 SAN JOAQUIN COUNTY NEAR TRACY FROM STANISLAUS COUNTY LINE TO ALAMEDA COUNTY LINE REPAIR PVMNT/HMA RESURF & INSTALL ITS ELEMENT (TC) 34,196,100.00 34,353,600.00
California X077028 SAN JOAQUIN COUNTY IN STOCKTON ON ROUTE 4 FROM 0.2 MILE EAST OF FRESNO AVENUE TO EL DORADO STREET AND ON ROUTE 5 FROM TAYLOR STREET OVERHEAD TO STOC 0.00 37,712,800.00
California X095025 IN FAIRFIELD AT I-80 AND SR 12 CONSTRUCT A TWO-LANE WB I-80/WB SR 12 (TC) 19,569,973.18 61,959,006.00
California X099645 IN AND NEAR THE CITY OF MODESTO ON SR 132 NEAR NORTH DAKOTA AVE TO NEAR 6TH ST AND ON SR 99 FROM 0.5 M SOUTH OF TUOLUMNE RIVER BRIDGE TO 0.1 M NORTH 0.00 114,049,200.00