RECIPIENT | PROJECT NUMBER |
PROJECT TITLE | TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|
Mississippi | 0008005 | US 49 from the Stone County Line to South Gate Road - PE, UTIL & CON - Forrest County. | 36,941,982.33 | 51,498,874.00 |
Mississippi | 0029103 | ON SR 304 FROM US 61 TO I-55 WITH SPUR. GRADE, DRAIN, PAVE FOR NEW CONST. VISION 21. TUNICA CO. | 58,922,814.00 | 87,739,053.00 |
Mississippi | 0071079 | US 72 from SR 302 to the Tennessee State Line including the US 72 / MRIMF Interchange - ROW & Construction Marshall County. | 36,597,798.00 | 52,600,487.00 |
Mississippi | 0082105 | US 49 from just North of the Forest County Line North 22 Miles to Mount Olive - Safety Project - PE & Const - Covington County | 38,441,994.00 | 43,210,758.00 |
Mississippi | 0083029 | US 49 from Florence to Scale Area in Richland - Reconstruction Widen to 6 Lanes - ROW and CON - Rankin County. | 264,598,187.45 | 347,073,910.45 |
Mississippi | 0111056 | US 82 Greenville Bypass Freight Corridor Improvement Project from MSi River Bridge to Leland - New Construction - PE & CON - Washington Co (INFRA) | 1,120,000.00 | 147,422,926.00 |
Mississippi | 0201216 | I-20 Bridge Replacement #44.9B & Rail Replacements on Bridges # 45.2B&C - I-20, US 49 & I- 55 Install Fiber Optic Cables - PE & CON - Hinds & Rankin Co | 32,150,930.32 | 53,593,711.00 |
Mississippi | 0201234 | I-20 at Norrell Road - Interchange Improvements and Frontage Road Widening - Hinds County | 9,677,912.00 | 40,349,260.00 |
Mississippi | 0224063 | SR 15 APD SR 76 to the Union County Line - Paving - Pontotoc County | 20,683,120.00 | 25,853,900.00 |
Mississippi | 0250047 | City of Jackson - Greening the Gateways - PE & Construction - Hinds County | 26,031,913.00 | 42,494,629.00 |
Mississippi | 0261080 | Improvements to SR 19 to SR 492 to Philadelphia in Neshoba County, Mississippi (BUILD Grant) | 34,162,726.00 | 56,175,820.00 |
Mississippi | 0290100 | Bond Project for I-269/MS304 from I-55 to Tennessee State Line in Desoto and Marshall Counties per MOU | 288,953,881.00 | 843,554,254.00 |
Mississippi | 0401021 | SR 25 from SR 8 to US 278. Full ROW and Construction for 4 Lanes. Monroe County | 23,354,454.00 | 29,193,069.00 |
Mississippi | 0552202 | Madison County Bond Project (I-55, SR 463 and connector roads) per MOU. | 145,833,443.00 | 238,557,847.00 |
Mississippi | 0553094 | I-55 from the Carroll County Line to 2.5 Miles South of Carroll County - Mill & Overlay - CON - Montgomery County | 21,166,252.00 | 25,080,992.00 |
Mississippi | 0554102 | I-55 Replace Twin Bridges over Hickahala Creek and Relief Bridges - PE & CON - Tate County | 43,699,808.00 | 64,281,715.00 |
Mississippi | 0591075 | I-59 at SR 42 - Interchange - PE [survey, plans & phase B], ROW & Construction - Forrest County | 40,941,003.00 | 48,716,256.00 |
Mississippi | 0591121 | I-59 from the Lamar County Line to the Jones County Line - Pavement Restoration - CON - Forrest County | 12,533,486.00 | 42,282,185.00 |
Mississippi | 0592091 | I-59 BETWEEN 16TH AVE. AND 4TH AVE. IN LAUREL (S CURVE) RECONSTRUCTION JONES CO. | 36,498,429.00 | 53,508,188.00 |
Mississippi | 0592110 | I-59 from the Forrest County Line to 0.3 Miles South of Moselle - Pavement Restoration - CON - Jones County | 9,643,038.00 | 37,820,101.00 |
Mississippi | 0593099 | Improvements to I-59 / I-20 - Bridge Improvements - PE & CON - Lauderdale County [Design- Build] | 20,360,000.00 | 29,625,483.00 |
Mississippi | 0702015 | SR 6 through Marks - (Bridge #'s 31.3, 32.1, 33.2 & 33.5) - Bridge Replacement - ROW, UTIL & CON - Quitman County | 19,178,964.00 | 30,949,731.00 |
Mississippi | 0703022 | SR 6 over Tallahatchie River & Relief [Bridge #s 44.3 & 44.7] - Bridge Replacement - Panola County | 10,309,303.00 | 40,749,300.00 |
Mississippi | 0725011 | SR 3 from the Panola County Line to Just West of the Tunica County Line - Bridge #'s 183.8 & 184.2 - ROW, UTIL & CON - Tate and Tunica County | 19,302,792.00 | 31,202,954.00 |
Mississippi | 0781011 | APD COR "V" from Fairview to SR 23 - Grade Bridge Pave 4 Lanes - PE and CON - Itawamba County. | 71,488,414.00 | 98,147,591.00 |
Mississippi | 1920007 | Desoto County Board of Supervisors - Holly Springs Road - Reconstruction of 2.6 miles along Holly Springs Road including 5 Bridges -CON- Desoto County | 15,118,165.00 | 35,525,412.00 |
Mississippi | 2170022 | US 11 from Hobolochitto Creek to Hide-A-Way Lake Road - Construct 5 Lanes - ROW, UTIL & CON - Pearl River County. | 20,583,940.00 | 25,729,926.00 |
Mississippi | 2901015 | US 51 btwn Grenada & I-55, PE, ROW & Construction for Bridge Replacement and additional lanes, Grenada Co. | 16,334,259.00 | 28,140,124.00 |
Mississippi | 9371101 | SR 605 over Industrial Waterway - Bridge Rehabilitation {BR #3.5} - PE and CON - Harrison County | 22,896,652.00 | 28,295,816.00 |
Mississippi | FY01001 | VARIOUS CITIES & RURAL AREAS STATEWIDE, PE & ROW & CONSTRUCTION. FISCAL YEAR 2001 ANNUAL STP PROGRAM. | 34,988,185.00 | 43,671,344.00 |
Mississippi | FY02001 | STATEWIDE--ANNUAL PROGRAM STP PROJECT FOR VARIOUS CITIES & RURAL AREAS. PE & ROW & CONSTRUCTION. | 105,698,876.00 | 131,971,750.00 |
Mississippi | FY03001 | VARIOUS CITIES AND RURAL AREAS STATEWIDE. PE , ROW, & CONSTRUCTION. STATEWIDE. | 53,589,079.00 | 66,713,211.00 |
Mississippi | FY04001 | ANNUAL PROGRAM PROJECT FOR VARIOUS URBAN AND RURAL AREAS, PE, ROW, & CONST. STATEWIDE | 49,472,357.00 | 61,817,450.00 |
Mississippi | FY05001 | Annual Program STP projects for various urban and rural areas, PE, ROW, CONST. Statewide. | 43,954,317.00 | 54,776,953.00 |