RECIPIENT | PROJECT NUMBER |
COUNTY | POPULATION RANGE |
OWNERSHIP | PROGRAM | TYPE OF IMPROVEMENT |
TOTAL OBLIGATIONS |
ESTIMATED TOTAL COST |
---|---|---|---|---|---|---|---|---|
Alabama | 0003521 | Baldwin | >= 50,000 AND < 200,000 | State | EQUITY BONUS EXEMPT LIM | Right of Way | 8,631,239.36 | 10,789,049.21 |
Alabama | 0003521 | Baldwin | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 3,143,489.39 | 22,429,361.74 |
Alabama | 0003521 | Baldwin | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 2,278,572.99 | 3,869,195.47 |
Alabama | 0005512 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 20,423,196.33 | 25,528,995.41 |
Alabama | 0005512 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 2,382,572.89 | 3,020,591.93 |
Alabama | 0005512 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | 2,733,827.82 | 3,417,284.77 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 28,869,075.22 | 36,086,344.02 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 6,015,791.59 | 8,319,024.82 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | 4R - Added Capacity | 3,718,244.33 | 4,647,963.41 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 1,165,279.24 | 1,456,441.05 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | 2,608,800.00 | 3,261,000.00 |
Alabama | 0006521 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | Utilities | 4,796.28 | 5,995.35 |
Alabama | 0006562 | Pickens | >= 5,000 AND < 50,000 | State | FAST ACT NATIONAL FREIGHT | New Construction Roadway | 21,744,588.00 | 27,180,735.00 |
Alabama | 0006562 | Pickens | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 24,307,253.39 | 30,645,789.74 |
Alabama | 0006562 | Pickens | >= 5,000 AND < 50,000 | State | TECHNOLOGY DEPLOYMENT GRANTS T | New Construction Roadway | 524,348.58 | 655,435.73 |
Alabama | 0007549 | Bibb | >= 5,000 AND < | State | HIGHWAY INFRA PROGRAM APPORT | Utilities | 423,595.33 | 529,494.17 |
Alabama | 0007549 | Tuscaloosa | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | Utilities | 663,339.62 | 829,174.52 |
Alabama | 0007549 | Bibb | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 20,054,323.37 |
Alabama | 0007549 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 31,404,564.96 |
Alabama | 0007549 | Bibb | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 779,430.88 | 974,288.60 |
Alabama | 0007549 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,220,569.12 | 1,525,711.40 |
Alabama | 0007549 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 4,303,482.60 | 5,379,353.25 |
Alabama | 0007549 | Bibb | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 2,748,117.40 | 3,435,146.75 |
Alabama | 0007549 | Bibb | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 1,116,227.54 | 2,167,093.45 |
Alabama | 0007549 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 1,747,984.21 | 3,393,613.72 |
Alabama | 0012507 | Coffee | >= 5,000 AND < 50,000 | State | MINIMUM GUARANTEE - TEA-21 | Utilities | 327,602.84 | 409,503.55 |
Alabama | 0012507 | Coffee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 9,600,000.00 | 12,000,000.00 |
Alabama | 0012507 | Coffee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 5,076,381.10 | 6,370,011.05 |
Alabama | 0012507 | Coffee | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | 4,988,960.00 | 6,236,200.00 |
Alabama | 0012507 | Coffee | >= 5,000 AND < 50,000 | State | REPURPOSED SPECIAL | 4R - No Added Capacity | 4,966,882.78 | 6,208,603.48 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < | State | EQUITY BONUS SP LIMITATION | 4R - No Added Capacity | 34,109.25 | 42,636.56 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 6,118,821.09 | 13,373,512.65 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 406,162.45 | 507,703.06 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | 4R - No Added Capacity | 5,002,287.88 | 6,252,859.87 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 462,833.60 | 578,542.00 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | REPURPOSED EARMARK SUBJ TO LIM | 4R - No Added Capacity | 8,265.00 | 10,331.25 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | REPURPOSED SPECIAL | 4R - No Added Capacity | 965,135.00 | 1,206,418.75 |
Alabama | 0013568 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 3,639,295.49 | 4,549,119.36 |
Alabama | 0014509 | Elmore | >= 50,000 AND < 200,000 | State | REDISTRIBUTION OF CERTAIN AUTH | Right of Way | 602,400.00 | 753,000.00 |
Alabama | 0014509 | Elmore | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 18,869,979.84 | 23,587,474.79 |
Alabama | 0014509 | Elmore | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,361,763.87 | 1,702,204.84 |
Alabama | 0014509 | Elmore | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 2,768,000.00 | 3,460,000.00 |
Alabama | 0014509 | Elmore | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 915,519.98 | 1,144,399.98 |
Alabama | 0025556 | Cherokee | >= 5,000 AND < 50,000 | State | FTA HWY PROJ. TRF FHWA | 4R - No Added Capacity | 1,502,609.93 | 1,878,262.41 |
Alabama | 0025556 | Etowah | >= 50,000 AND < 200,000 | State | FTA HWY PROJ. TRF FHWA | 4R - No Added Capacity | 3,137,390.07 | 3,921,737.59 |
Alabama | 0025556 | Etowah | >= 50,000 AND < | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 21,074,104.96 | 26,342,631.20 |
Alabama | 0025556 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 801,158.91 | 1,001,448.64 |
Alabama | 0025556 | Etowah | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,673,081.09 | 2,091,351.36 |
Alabama | 0025556 | Cherokee | >= 5,000 AND < 50,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 664,558.17 | 830,697.71 |
Alabama | 0025556 | Etowah | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 1,387,571.16 | 1,734,463.95 |
Alabama | 0035504 | Jackson | >= 50,000 AND < 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | 5,352,192.88 | 6,690,241.10 |
Alabama | 0035504 | Jackson | >= 50,000 AND < 200,000 | State | HIGHWAY BRIDGE PROGRAM (PLUS) | Bridge Replacement - No Added Capacity | 15,555,494.00 | 19,444,367.50 |
Alabama | 0035504 | Jackson | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | 252,676.79 | 315,845.99 |
Alabama | 0035521 | Montgomery | >= 200,000 | N/A | HIGH PRIORITY PROJECT SEC 1702 | Bridge New Construction | 2,197,328.09 | 2,746,660.11 |
Alabama | 0035521 | Montgomery | >= 200,000 | N/A | TRANSPORTATION IMP PROJ | New Construction Roadway | 26,972,965.90 | 33,716,207.38 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 57,407.50 | 71,759.37 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Bridge New Construction | 48,863,096.60 | 61,078,870.75 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | New Construction Roadway | 1,118,654.77 | 1,398,318.47 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Right of Way | 3,641,610.82 | 4,552,013.53 |
Alabama | 0042501 | Mobile | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Utilities | 1,355,024.56 | 1,693,780.71 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | 11,637,990.40 | 14,547,488.00 |
Alabama | 0042501 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 296,985.77 | 371,232.21 |
Alabama | 0042509 | Mobile | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 0.00 | 38,162,361.85 |
Alabama | 0042509 | Mobile | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 0.00 | 195,148.16 |
Alabama | 0042509 | Mobile | >= 200,000 | State | NATIONAL HIGHWAY SYSTEM | Preliminary Engineering | 320,000.00 | 400,000.00 |
Alabama | 0042509 | Mobile | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 216,784.12 | 270,980.15 |
Alabama | 0053530 | Madison | >= 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | 7,739,007.12 | 9,673,758.91 |
Alabama | 0053530 | Madison | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Rehabilitation - No Added Capacity | 6,252,250.54 | 7,988,819.31 |
Alabama | 0053530 | Madison | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | 4R - Added Capacity | 4,534,739.80 | 5,668,424.76 |
Alabama | 0053530 | Madison | >= 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | Bridge Rehabilitation - No Added Capacity | 5,585,187.48 | 6,981,484.35 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | APPALACHIAN DEVEL HWY | Utilities | 49,526.09 | 49,526.09 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | ARRA AMERICAN RECOV & REINV AC | Bridge New Construction | 36,100,378.68 | 36,100,378.68 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | ARRA AMERICAN RECOV & REINV AC | New Construction Roadway | 606,307.15 | 606,307.15 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECTS-TEA-21 | New Construction Roadway | 228,222.01 | 285,278.01 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECTS-TEA-21 | Preliminary Engineering | 1,826,640.00 | 2,283,300.00 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECTS-TEA-21 | Right of Way | 5,966,693.43 | 7,458,367.43 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECTS-TEA-21 | Utilities | 78,168.49 | 97,711.49 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 4,283,684.00 | 5,354,605.00 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | 347,375.20 | 434,219.20 |
Alabama | 0192901 | Calhoun | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 589,224.38 | 736,530.38 |
Alabama | 0355503 | Franklin | >= 5,000 AND < 50,000 | N/A | APPALACHIA DEVELOPMENT HWY | Utilities | 270,080.01 | 337,600.01 |
Alabama | 0355503 | Franklin | >= 5,000 AND < 50,000 | N/A | APPALACHIAN DEVEL HWY | 4R - No Added Capacity | 24,522,247.28 | 29,587,447.28 |
Alabama | 0355503 | Franklin | >= 5,000 AND < 50,000 | N/A | APPALACHIAN DEVEL HWY | Preliminary Engineering | 624,800.00 | 781,000.00 |
Alabama | 0355503 | Franklin | >= 5,000 AND < 50,000 | N/A | APPALACHIAN DEVEL HWY | Utilities | 220,898.42 | 276,123.03 |
Alabama | 0355503 | Franklin | >= 5,000 AND < 50,000 | N/A | NATIONAL HIGHWAY SYSTEM | 4R - No Added Capacity | 72,800.00 | 91,000.00 |
Alabama | 0471500 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Bridge New Construction | 12,735,594.10 | 15,919,492.62 |
Alabama | 0471500 | Jefferson | >= 200,000 | N/A | APPALACHIAN DEVEL HWY | New Construction Roadway | 22,027,586.08 | 27,534,482.60 |
Alabama | 0471500 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Preliminary Engineering | 115,541.47 | 130,484.84 |
Alabama | 0471500 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Utilities | 347,418.30 | 434,272.88 |
Alabama | 0471500 | Jefferson | >= 200,000 | N/A | APPALCHIAN DEV HWY DEMO'S | Preliminary Engineering | 1,642,000.00 | 1,642,000.00 |
Alabama | 0471501 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Bridge New Construction | 116,541,075.78 | 145,676,344.73 |
Alabama | 0471501 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | New Construction Roadway | 18,485,189.51 | 23,106,486.89 |
Alabama | 0471501 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Preliminary Engineering | 3,123,827.36 | 3,904,784.20 |
Alabama | 0471501 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Utilities | 5,544,572.72 | 6,930,715.90 |
Alabama | 0471501 | Jefferson | >= 200,000 | State | APPALCHIAN DEV HWY DEMO'S | Preliminary Engineering | 1,853,555.96 | 1,853,555.96 |
Alabama | 1602551 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | New Construction Roadway | 58,822,777.82 | 58,877,817.38 |
Alabama | 1602551 | Jefferson | >= 200,000 | State | APPALACHIAN DEVEL HWY | Utilities | 4,093,073.73 | 5,116,342.16 |
Alabama | 1602551 | Jefferson | >= 200,000 | State | HIGH PRIORITY PROJECTS-TEA-21 | New Construction Roadway | 1,287,275.99 | 1,609,094.99 |
Alabama | 1602551 | Jefferson | >= 200,000 | State | HIGH PRIORITY PROJECTS-TEA-21 | Utilities | 5,492,680.58 | 7,488,906.66 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | EQUITY BONUS SP LIMITATION | Bridge Replacement - Added Capacity | 117,987.69 | 147,484.61 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | Local | EQUITY BONUS SP LIMITATION | Bridge Replacement - Added Capacity | 629,891.36 | 787,364.20 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | EQUITY BONUS SP LIMITATION | Right of Way | 233,413.92 | 291,767.40 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECT SEC 1702 | Right of Way | 6,138,644.57 | 7,673,305.71 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | HIGH PRIORITY PROJECT SEC 1702 | Utilities | 161.49 | 201.86 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Bridge Replacement - Added Capacity | 34,974,115.56 | 43,717,644.45 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | 7,403,206.42 | 9,286,373.47 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | 8,340,294.76 | 10,425,368.45 |
Alabama | 1702904 | Baldwin | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 421,646.05 | 527,057.56 |
Alabama | 3716258 | Jefferson | >= 200,000 | Other | CONGESTION AIR QUALITY | Facilities for Pedestrians and Bicycles | 8,000,000.00 | 10,000,000.02 |
Alabama | 3716258 | Jefferson | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Facilities for Pedestrians and Bicycles | 0.00 | 33,170,923.52 |
Alabama | 7002600 | Jefferson | >= 200,000 | N/A | HIGHWAY INFRA PROGRAM APPORT | 4R - Added Capacity | 2,900,715.95 | 3,625,894.94 |
Alabama | 7002600 | Jefferson | >= 200,000 | N/A | HIGHWAY INFRA PROGRAM APPORT | Utilities | 1,567,158.05 | 1,958,947.56 |
Alabama | 7002600 | Jefferson | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 17,571,934.71 | 21,964,918.39 |
Alabama | 7002600 | Jefferson | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 5,426,842.49 | 6,783,553.11 |
Alabama | 7002600 | Jefferson | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 455,560.00 | 574,450.00 |
Alabama | 7009600 | Jefferson | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Right of Way | 1,571,648.38 | 1,964,560.48 |
Alabama | 7009600 | Jefferson | >= 200,000 | State | BRIDGE PROGRAM - 85% ON/OFF | Utilities | 78,599.33 | 98,249.17 |
Alabama | 7009600 | Jefferson | >= 200,000 | State | HIGHWAY BRIDGE PROGRAM | Right of Way | 652,432.00 | 815,540.00 |
Alabama | 7009600 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | 19,742,764.18 | 24,678,455.22 |
Alabama | 7009600 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 518,432.67 | 673,849.26 |
Alabama | 7503600 | Mobile | >= 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | 4R - Added Capacity | 853,635.00 | 1,067,043.75 |
Alabama | 7503600 | Mobile | >= 200,000 | Local | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 1,100,000.00 | 1,375,000.00 |
Alabama | 7503600 | Mobile | >= 200,000 | Local | NATIONAL HIGHWAY SYSTEM | 4R - Added Capacity | 500,000.00 | 625,000.00 |
Alabama | 7503600 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 7,418,609.49 | 21,777,788.11 |
Alabama | 7503600 | Mobile | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 705,136.99 | 881,421.24 |
Alabama | 7503600 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | 1,195,188.70 | 1,497,162.57 |
Alabama | 7503600 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Preliminary Engineering | 1,313,819.48 | 1,642,274.35 |
Alabama | 7503600 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Right of Way | 5,193,362.08 | 6,491,702.60 |
Alabama | 7503600 | Mobile | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 886,682.55 | 1,108,353.19 |
Alabama | 9070900 | Morgan | >= 50,000 AND < 200,000 | State | EMERGENCY RELIEF | 4R - Restoration & Rehabilitation | 19,980,578.60 | 24,975,723.25 |
Alabama | 9070900 | Morgan | >= 50,000 AND < 200,000 | State | EMERGENCY RELIEF | Preliminary Engineering | 1,200,000.00 | 1,500,000.00 |
Alabama | 9070900 | Morgan | >= 50,000 AND < 200,000 | State | EMERGENCY RELIEF | Right of Way | 32,000.00 | 40,000.00 |
Alabama | 9070900 | Morgan | >= 50,000 AND < 200,000 | State | TECHNOLOGY DEPLOYMENT GRANTS T | 4R - Restoration & Rehabilitation | 741,493.00 | 926,866.25 |
Alabama | ATRP001 | Statewide | N/A | N/A | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | 0.00 | 7,001,429.91 |
Alabama | ATRP001 | Statewide | N/A | N/A | HIGH PRIORITY PROJECT SEC 1702 | Right of Way | 270,111.39 | 337,639.24 |
Alabama | ATRP001 | Statewide | N/A | N/A | NATIONAL HIGHWAY PERF PROGRAM | Debt Service | 18,611,317.52 | 21,335,563.70 |
Alabama | ATRP001 | Geneva | >= 5,000 AND < 50,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 30,430.46 | 38,038.08 |
Alabama | ATRP001 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 564,160.80 | 60,092,674.34 |
Alabama | ATRP001 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 601.86 |
Alabama | ATRP001 | Geneva | >= 5,000 AND < 50,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 2,098,100.78 |
Alabama | ATRP001 | Russell | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 345,253.18 | 431,566.48 |
Alabama | ATRP001 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Debt Service | 398,505,984.15 | 498,304,632.99 |
Alabama | ATRP002 | Perry | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 15% OFF SYST | 4R - No Added Capacity | 0.00 | 632,007.59 |
Alabama | ATRP002 | Shelby | >= 50,000 AND < 200,000 | Local | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | 0.00 | 1,008,976.87 |
Alabama | ATRP002 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 689,998.36 | 50,798,632.56 |
Alabama | ATRP002 | Coosa | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 382,206.79 |
Alabama | ATRP002 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 1,315,926.24 |
Alabama | ATRP002 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 6,236,035.81 |
Alabama | ATRP002 | Fayette | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 515,757.77 | 1,875,260.35 |
Alabama | ATRP002 | Coosa | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 515,757.77 | 1,875,260.35 |
Alabama | ATRP002 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 0.00 | 378,541.44 |
Alabama | ATRP003 | Statewide | N/A | State | BRIDGE PROGRAM - 85% ON/OFF | 4R - No Added Capacity | 0.00 | 577,413.66 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 9,120,842.83 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 1,355,086.23 | 32,537,627.67 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 12,103,654.61 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 559,309.46 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - Added Capacity | 0.00 | 10,574,217.45 |
Alabama | ATRP003 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 7,467,358.39 |
Alabama | ATRP003 | Statewide | N/A | State | TECHNOLOGY DEPLOYMENT GRANTS T | Bridge Replacement - Added Capacity | 479,670.00 | 599,587.50 |
Alabama | ATRP004 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 1,380,485.51 | 34,456,921.42 |
Alabama | ATRP004 | Lowndes | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 1,021,207.52 | 1,276,509.40 |
Alabama | ATRP004 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 120,695.37 | 1,860,869.01 |
Alabama | ATRP004 | Lawrence | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 226,666.66 | 4,886,834.34 |
Alabama | ATRP004 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 1,615,882.09 |
Alabama | ATRP004 | Fayette | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 1,466,873.54 |
Alabama | ATRP004 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 0.00 | 147,038.56 |
Alabama | ATRP005 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 808,766.91 | 34,585,261.36 |
Alabama | ATRP005 | Jefferson | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 474,853.48 | 602,846.47 |
Alabama | ATRP005 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 1,668,683.01 |
Alabama | ATRP005 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge New Construction | 0.00 | 481,648.46 |
Alabama | ATRP005 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 272,748.30 | 12,922,028.68 |
Alabama | ATRP006 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 505,735.99 | 23,100,042.08 |
Alabama | ATRP006 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 2,201,508.86 |
Alabama | ATRP006 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 1,281,464.12 |
Alabama | ATRP006 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 1,327,572.50 |
Alabama | ATRP006 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 6,082,873.12 |
Alabama | ATRP006 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | 0.00 | 452,570.96 |
Alabama | ATRP007 | Macon | >= 5,000 AND < 50,000 | Local | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | 0.00 | 1,640,908.85 |
Alabama | ATRP007 | Statewide | N/A | State | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | 0.00 | 4,310,997.55 |
Alabama | ATRP007 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 987,039.22 | 28,763,826.09 |
Alabama | ATRP007 | Madison | >= 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 8,737,881.96 |
Alabama | ATRP007 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 2,236,103.57 |
Alabama | ATRP007 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 649,822.86 | 10,790,322.06 |
Alabama | ATRP007 | Lauderdale | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 9,303,884.73 |
Alabama | ATRP007 | Russell | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 3,227,908.03 |
Alabama | ATRP008 | Statewide | N/A | N/A | BRIDGE PROGRAM - 85% ON/OFF | Bridge Replacement - No Added Capacity | 0.00 | 855,402.96 |
Alabama | ATRP008 | Statewide | N/A | N/A | CONGESTION AIR QUALITY | 4R - Maintenance Resurfacing | 222,884.77 | 278,605.96 |
Alabama | ATRP008 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 5,551,524.16 |
Alabama | ATRP008 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 720,830.38 | 25,404,248.67 |
Alabama | ATRP008 | Jefferson | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 940,284.07 | 1,175,355.09 |
Alabama | ATRP008 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 663,116.81 | 17,582,774.78 |
Alabama | ATRP008 | Marion | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 157,562.96 | 196,953.70 |
Alabama | ATRP009 | Statewide | N/A | N/A | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | 0.00 | 597,911.60 |
Alabama | ATRP009 | Shelby | >= 50,000 AND < 200,000 | Local | CONGESTION AIR QUALITY | 4R - Maintenance Resurfacing | 114.20 | 142.75 |
Alabama | ATRP009 | Jefferson | >= 200,000 | Local | CONGESTION AIR QUALITY | 4R - Maintenance Resurfacing | 380,546.47 | 475,683.09 |
Alabama | ATRP009 | Statewide | N/A | N/A | RAIL HWY CROSSING HAZ ELI | Rail/Hwy Crossing | 742,707.00 | 742,707.00 |
Alabama | ATRP009 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 4,852,097.15 |
Alabama | ATRP009 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 20,507,533.06 |
Alabama | ATRP009 | Jefferson | >= 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 629,726.06 | 787,158.86 |
Alabama | ATRP009 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 8,994,904.72 |
Alabama | ATRP009 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 1,537,349.95 | 22,038,706.07 |
Alabama | ATRP009 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Traffic Management/Engineering - HOV | 0.00 | 436,177.30 |
Alabama | ATRP010 | Jefferson | >= 200,000 | Local | CONGESTION AIR QUALITY | 4R - Restoration & Rehabilitation | 108,766.40 | 135,958.00 |
Alabama | ATRP010 | Statewide | N/A | State | HIGHWAY INFRA PROGRAM APPORT | Bridge Replacement - No Added Capacity | 130,400.00 | 163,000.00 |
Alabama | ATRP010 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 20,139,038.44 |
Alabama | ATRP010 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 3,537,723.51 |
Alabama | ATRP010 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 7,944,000.40 |
Alabama | ATRP010 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 26,987,499.30 |
Alabama | ATRP010 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | New Construction Roadway | 0.00 | 5,306,625.50 |
Alabama | ATRP011 | Russell | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PROGRAM APPORT | 4R - Restoration & Rehabilitation | 262,806.00 | 328,507.50 |
Alabama | ATRP011 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 18,477,124.68 |
Alabama | ATRP011 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 2,970,332.10 |
Alabama | ATRP011 | Russell | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 2,835,571.01 | 3,544,463.76 |
Alabama | ATRP011 | Coosa | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 117,002.58 | 146,253.22 |
Alabama | ATRP011 | Lamar | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 593,679.26 |
Alabama | ATRP011 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 17,092,886.90 |
Alabama | ATRP012 | Statewide | N/A | N/A | BRIDGE PROGRAM - 15% OFF SYST | Bridge Replacement - No Added Capacity | 0.00 | 279,272.14 |
Alabama | ATRP012 | Statewide | N/A | N/A | CONGESTION AIR QUALITY | 4R - Maintenance Resurfacing | 374,831.80 | 468,539.75 |
Alabama | ATRP012 | Statewide | N/A | N/A | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 0.00 | 7,920,548.87 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 3,177,159.97 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 29,805,291.99 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 1,584,804.11 | 2,954,415.47 |
Alabama | ATRP012 | Madison | >= 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 6,927,714.66 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - No Added Capacity | 0.00 | 945,644.72 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 2,263,132.63 | 10,523,351.98 |
Alabama | ATRP012 | Shelby | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 5,288,820.81 | 6,611,026.01 |
Alabama | ATRP012 | Lawrence | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 108,713.22 | 135,891.53 |
Alabama | ATRP012 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 0.00 | 3,086,112.70 |
Alabama | ATRP013 | Cleburne | >= 5,000 AND < 50,000 | Local | HIGHWAY INFRA PROGRAM APPORT | Bridge Replacement - No Added Capacity | 2,815,132.20 | 3,519,336.66 |
Alabama | ATRP013 | Statewide | N/A | N/A | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 9,515,402.99 | 10,801,498.01 |
Alabama | ATRP013 | Limestone | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 1,229,011.01 |
Alabama | ATRP013 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 0.00 | 2,348,917.34 |
Alabama | ATRP013 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 517,842.12 | 14,217,337.26 |
Alabama | ATRP013 | Russell | >= 50,000 AND < 200,000 | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 201,338.73 | 251,673.41 |
Alabama | ATRP013 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 11,575,369.28 |
Alabama | ATRP013 | Lauderdale | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 14,007.38 | 17,509.23 |
Alabama | ATRP013 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 12,705,852.35 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 0.00 | 20,466,803.91 |
Alabama | ATRP016 | Madison | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 10,285,552.48 | 12,856,940.60 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 1,000,000.00 | 3,227,336.31 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 2,916,225.05 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Rehabilitation - No Added Capacity | 0.00 | 351,805.13 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 0.00 | 7,285,335.15 |
Alabama | ATRP016 | Greene | >= 5,000 AND < 50,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 71,525.42 | 89,406.78 |
Alabama | ATRP016 | Statewide | N/A | State | SURFACE TRANSP BLOCK GRNT PRGM | Safety | 0.00 | 227,927.50 |
Alabama | ATRP017 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 569,972.21 | 19,661,481.00 |
Alabama | ATRP017 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 0.00 | 9,039,162.69 |
Alabama | ATRP017 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 1,743,567.50 |
Alabama | ATRP017 | Tuscaloosa | >= 50,000 AND < 200,000 | Local | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Restoration & Rehabilitation | 0.00 | 757,477.94 |
Alabama | ATRP017 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 195,047.37 | 8,514,343.05 |
Alabama | ATRP017 | Statewide | N/A | N/A | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 0.00 | 922,046.72 |
Alabama | I020339 | Cleburne | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 30,613,582.23 | 35,490,332.70 |
Alabama | I020341 | Cleburne | >= 5,000 AND < 50,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 27,029,681.59 | 31,615,196.33 |
Alabama | I059376 | Tuscaloosa | >= 50,000 AND < | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 25,375,001.88 | 31,718,752.35 |
Alabama | I059377 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 29,124,273.85 | 34,922,013.81 |
Alabama | I059377 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 7,221.36 | 8,658.72 |
Alabama | I059383 | Jefferson | >= 200,000 | Other | FAST ACT NATIONAL FREIGHT | Debt Service | 43,734,676.51 | 48,594,085.02 |
Alabama | I059383 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 0.00 | 286,168,734.50 |
Alabama | I059383 | Jefferson | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Debt Service | 10,005,352.23 | 11,117,058.04 |
Alabama | I059383 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 7,592,848.63 | 8,499,748.43 |
Alabama | I059383 | Jefferson | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 438,105.96 | 486,784.40 |
Alabama | I059385 | Jefferson | >= 200,000 | State | FAST ACT NATIONAL FREIGHT | Debt Service | 67,760,095.27 | 75,288,994.74 |
Alabama | I059385 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Bridge Replacement - No Added Capacity | 0.00 | 410,276,632.50 |
Alabama | I059385 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Debt Service | 52,817,420.72 | 58,686,023.03 |
Alabama | I059385 | Jefferson | >= 200,000 | Other | NATIONAL HIGHWAY PERF PROGRAM | Debt Service | 4,945,634.00 | 5,495,148.89 |
Alabama | I059385 | Jefferson | >= 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Bridge Replacement - No Added Capacity | 1,487,306.76 | 1,859,133.45 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 0.00 | 1,444,909.00 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Maintenance Resurfacing | 68,411,255.59 | 81,396,003.84 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 1,150,082.76 | 1,277,869.73 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | REPURPOSED EARMARK SUBJ TO LIM | 4R - Maintenance Resurfacing | 502,681.51 | 628,351.88 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | REPURPOSED SPECIAL | 4R - Maintenance Resurfacing | 4,722,673.82 | 5,903,342.28 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Added Capacity | 4,207,005.96 | 5,258,757.45 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - Maintenance Resurfacing | 3,697,828.91 | 4,108,698.79 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 1,667,956.28 | 2,084,945.35 |
Alabama | I059387 | Tuscaloosa | >= 50,000 AND < 200,000 | State | TECHNOLOGY DEPLOYMENT GRANTS T | 4R - Maintenance Resurfacing | 100,000.00 | 125,000.00 |
Alabama | I059407 | DeKalb | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | 4R - No Added Capacity | 419,804.99 | 466,449.99 |
Alabama | I059407 | DeKalb | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 630,540.00 | 700,600.00 |
Alabama | I059407 | DeKalb | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 17,480,861.03 | 19,423,178.92 |
Alabama | I059407 | DeKalb | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 11,783,349.38 | 13,092,610.42 |
Alabama | I059409 | DeKalb | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 362,242.97 | 402,492.19 |
Alabama | I059409 | Etowah | >= 50,000 AND < 200,000 | State | INTERSTATE MAINTENANCE | Preliminary Engineering | 267,757.04 | 297,507.82 |
Alabama | I059409 | Etowah | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 12,601,337.80 | 14,001,486.44 |
Alabama | I059409 | DeKalb | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - No Added Capacity | 17,048,089.81 | 18,942,322.01 |
Alabama | I059409 | Etowah | >= 50,000 AND < | State | SURFACE TRANSP BLOCK GRNT PRGM | 4R - No Added Capacity | 6,376,201.36 | 7,084,668.18 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | EMERGENCY RELIEF | New Construction Roadway | 1,794,933.81 | 1,994,370.90 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | Other | HIGHWAY INFRA PRGM - COVID APP | New Construction Roadway | 44,792,072.78 | 55,990,090.97 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | HIGHWAY INFRA PRGM - COVID APP | Utilities | 2,503,064.23 | 3,128,830.29 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM APPORT | New Construction Roadway | 200,000.00 | 250,000.00 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | INTERSTATE MAINTENANCE | New Construction Roadway | 26,439,388.64 | 29,377,098.49 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | INTERSTATE MAINTENANCE | Utilities | 1,368,956.47 | 1,521,062.74 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 3,176,255.80 | 3,970,319.75 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | New Construction Roadway | 300,000.00 | 375,000.00 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | N/A | NATIONAL HIGHWAY SYSTEM | New Construction Roadway | 2,600,000.00 | 7,235,144.08 |
Alabama | I065353 | Shelby | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Utilities | 309,390.87 | 386,738.59 |
Alabama | I065354 | Shelby | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Added Capacity | 77,365,586.45 | 95,749,488.19 |
Alabama | I065354 | Shelby | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY SYSTEM | Right of Way | 114,539.04 | 143,173.80 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PRGM - COVID APP | 4R - Restoration & Rehabilitation | 16,000,000.00 | 17,777,777.78 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | HIGHWAY INFRA PROGRAM ALLOC | 4R - Restoration & Rehabilitation | 10,855,000.00 | 13,568,750.00 |
Alabama | I085362 | Lee | >= 50,000 AND < | State | HIGHWAY INFRA PROGRAM APPORT | Utilities | 613,000.00 | 681,111.11 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 1,913,670.00 | 2,126,300.00 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Right of Way | 157,060.44 | 174,511.60 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Utilities | 346,129.50 | 384,588.33 |
Alabama | I085362 | Lee | >= 50,000 AND < 200,000 | State | SURFACE TRANSP BLOCK GRNT PRGM | Utilities | 390,735.26 | 434,150.29 |
Alabama | I459315 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | 4R - Restoration & Rehabilitation | 22,449,600.00 | 24,944,000.00 |
Alabama | I459315 | Jefferson | >= 200,000 | State | NATIONAL HIGHWAY PERF PROGRAM | Preliminary Engineering | 189,000.00 | 210,000.00 |