| Volume Delivered VD |
|
cy/m3 |
Actual Rock Socket Volume |
| Volume in Lines VL |
|
cy/m3 |
VRS + (AR)(RSL)/(3888) - VL VRS* = |
|
cy |
| Wastage VW |
|
cy/m3 |
VRS + (AR)(RSL) - VL VRS* = |
|
m3 |
| Volume Placed = VD-VL-VW VP |
|
cy/m3 |
Average Rock Socket Diameter |
| Theoretical Volume VT |
|
cy/m3 |
SQRT[(4950)VSL*/RSL)] RSD = |
|
in |
| Overpour, VP-VT OP |
|
cy/m3 |
SQRT[(1.273)VSL*/RSL)] RSD = |
|
m |
| Cross-Sec. Area of Rebar, Telltales, etc. |
| AR = [(#bars)(As) + (#telltales)(At)] AR = |
|
in2/m2 |
|
| Rock Socket Length RSL = |
|
ft/m |
|
| Est. Rock Socket Volume From Curve VRS = |
|
cy/m3 |
|