Drilled Shaft Soil Field Record
(pdf, 21 kb.)
| Date Excavation Started |
|
Surface Casing |
 |
| Date Excavation Finished |
|
Top Elev. |
|
| Date Bottom Observed |
|
Bottom Elev. |
|
| Date Concrete Placed |
|
Length |
|
| |
Design |
As-Built |
Thickness |
|
| Station |
|
|
Permanent or Temporary Casing |
| Offset |
|
|
Top Elev. |
|
| Top Elevation |
|
|
Bottom Elev. |
|
| Bottom Elevation |
|
|
Length |
|
| Shaft Diameter |
|
|
Thickness |
|
| Shaft Length |
|
|
|
| Bell Diameter, BD |
|
|
| Bell Height, BH |
|
|
| Plumbness |
|
|
| Design Capacity |
|
|
| Observed Groundwater Elevation |
|
|
| Remarks |
| Date |
Time |
Depth |
Soil or Rock Description |
Tool |
Observations |
| |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
TOC
|