| FHWA > Engineering > Pavements > Concrete > Evaluation of Procedures for Quality Assurance Specifications > Appendix C |
APPENDIX C: SUMMARY OF AGENCY SUPERPAVE SPECIFICATIONS RECEIVEDConnecticutQuality ControlThe contractor is responsible for developing the mix design for the project, providing a QC plan that must be approved by the engineer prior to construction, and providing qualified personnel and equipment to conduct QC testing. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated for the following properties: gradation, asphalt content, voids @ Ndes, VMA, VFA, Gmm @ Ndes and Nmax, Gmb, Gse, TSR, Ndes, Nini, Nmax, recycled asphalt pavement (RAP) gradation, fine aggregate angularity (FAA), coarse aggregate angularity (CAA), sand equivalent, and dust-to-asphalt ratio. The contractor must exercise control over the following properties: asphalt content, gradation, air voids, mix moisture, VMA, VFA, BSG of mix, MSG of mix, RAP gradation, aggregate moisture, RAP moisture, and density. In addition, the contractor must provide split samples to the engineer for verification testing. Quality AssuranceConnecticut DOT is responsible for QA. Assurance is accomplished through verification testing by Connecticut DOT and through independent assurance testing. Verification tests are conducted on split samples. A lot is considered 1 day's production. Sublots are five equal divisions of any lot. AcceptanceAcceptance is based on the QC tests as verified by Connecticut DOT's verification tests. Density acceptance is based on the PWL of a lot. The PWL is calculated using 10 tests (2 per sublot). Pay FactorsPay factors are assigned for gradation, asphalt content, joint density, and mat density. The pay factors for each can be determined from the following tables. Total payment is determined by successively multiplying the percent payment by the contract price per metric ton of material. Pay Factors for Gradation and Binder ContentMaximum Allowable Deviation (M.A.D.) From Job-Mix Formula for Consecutive Tests
Pay Factors for Joint and Mat Density
QC/QA Tests for Connecticut
NA = Not applicable KansasQuality ControlThe contractor is responsible for developing the mix design for the project, providing a QC plan that must be approved by the engineer prior to construction, and providing qualified personnel and equipment to conduct QC testing. All testing equipment and procedures must conform to the Kansas DOT Superpave Mix Design and Superpave Field Laboratory Technician Certification Training Manual. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated for the following properties: gradation, asphalt content, theoretical MSG, BSG, air voids, VMA, VFA, dust-to-asphalt ratio, flat or elongated particles, percent moisture, and TSR. The contractor must exercise control over the following properties: asphalt content, gradation, air voids, VMA, VFA, CAA, sand equivalent, FAA, TSR, density, and dust-to-asphalt ratio. Samples for mixture properties, aggregate gradation, and binder must be taken from behind the paver and transported to the field laboratory for testing. Quality AssuranceKansas DOT is responsible for all assurance and verification testing. Kansas DOT assurance tests are independent of the contractor's QC tests. The lot size for verification testing is 3000 tons (2720 Mg) with 750-ton (680 Mg) sublots. AcceptanceThe contractor's control tests are used for acceptance unless the results do not compare favorably with Kansas DOT's verification test results. In this case, Kansas DOT's tests are used for acceptance unless the contractor requests referee testing. The testing frequencies vary, depending on the property being measured. Pay FactorsPay factors are assigned for in-place density, air voids, and smoothness. Pay factors for density and air voids can be determined from the following tables. Information concerning methods for determining a smoothness pay factor was not included. Pay Factors for Specified Density
Calculations for Pay Factors A1, A2, A3, A4, A5, B1, B2, B3, B4, and B5:
Pay Factor Calculation: Density Pay Adjustment Factor (PD)* = [ (Pay Factor A) (Pay Factor B) - 1.000 * PD will be rounded to the nearest 0.001 Air Void PaymentPayment adjustment for air voids will be computed by multiplying the air voids pay adjustment factor (PV) times the number of tons included in the lot times the bid price per ton. Calculate PV to 0.001. A lot will normally be comprised of the results of four contiguous individual air void tests performed on Superpave gyratory compacted samples of a given mix design. Lot size is defined in subsections 5.0(f) and 5.0(g) of this special provision. (Air void lots and density lots are normally of different sizes.) The absolute value of the deviation from the target at Ndes for each individual air void test in a lot will be computed as shown: (57)Deviation From Target = 4.0 - Test Value The average deviation (D) from the target will be computed as follows: (58)D = Sum of deviations from target ÷ number of tests in lot The average air void deviation (D) will be used to select the air void pay factor from the appropriate table below. Calculate D to 0.01. Pay Factor Table for Air Voids (Lot Size of Four Tests)
(a) Engineer will determine whether the material may remain in place. The pay factor for such material remaining in place is 0.8000. When the testing rate does not provide a complete four-test lot (e.g., at the end of a production run), the following applies: Combine the three tests into a lot and use the following table for D3. When there are one or two tests remaining, combine them with the previous four tests to create a five- or six-test lot, respectively. The pay factors for D5 and D6 are also shown below. Pay Factor Table for Air Voids (Lot Size of Three Tests)
(a) Engineer will determine whether the material may remain in place. The pay factor for such material remaining in place is 0.8000. Pay Factor Table for Air Voids (Lot Size of Five Tests)
(a) Engineer will determine whether the material may remain in place. The pay factor for such material remaining in place is 0.8000. Pay Factor Table for Air Voids (Lot Size of Six Tests)
(a) Engineer will determine whether the material may remain in place. The pay factor for such material remaining in place is 0.8000. (59)Pay Factor Calculation = Air Void Pay Adjustment Factor (PV) = Pay Factor - 1.000 QC/QA Tests for Kansas
NA = Not applicable LouisianaQuality ControlThe contractor is responsible for developing the mix design for the project. The JMF must include the recommended formula, extracted gradation, and supporting design data. In addition, the contractor is responsible for providing a QC plan that must be approved by the engineer prior to construction and providing qualified personnel and equipment to conduct QC testing. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated on the following properties: gradation, asphalt content, percent crushed aggregate, MSG, corrected BSG @ Ndes, percent air voids @ Ndes, percent VMA @ Ndes, percent VFA @ Ndes, gyratory compaction curve @ Nmax, slope of the compaction curve, and percent anti-strip. Upon validation of the JMF, the validation parameters shall be used to control the process. The quality of the mixtures will be evaluated during two phases: (1) production of the mixture at the plant, and (2) hauling, laying, and compacting of the mixture. The quality of both phases must be evaluated continuously. AcceptanceThe Louisiana Department of Transportation and Development (DOTD) is responsible for all acceptance testing. Louisiana DOTD's acceptance tests are independent of the contractor's QC tests. The lot size is 5000 Mg, with 1000-Mg sublots unless otherwise specified by the engineer. Acceptance is based on the validation parameters used to verify the JMF. Acceptance testing for VMA, VFA, voids, maximum theoretical gravity, Nini, Ndes, Nmax, percent anti-strip, quality of asphalt cement, extracted aggregate gradation, percent crushed aggregate, percent asphalt cement, and percent moisture in the mix will be conducted on the total lot quantity. Pay FactorsPayment adjustments will be calculated based on specification limits and specified maximum variances from the JMF: Plant Acceptance:For: Percent voids PWL will be calculated for each of the parameters listed above. A mixture with any parameter below 40 PWL is subject to removal as directed by the engineer. The percent payment for each of the parameters will be calculated using the formula: (60)Percent Payment = 55 + 0.5PWL For: Percent anti-strip additive Payment adjustments for anti-strip additive will be based on the table below. For: Asphalt cement Payment adjustments for asphalt cement will be based on section 1012 of the specifications. For: Percent payment for plant acceptance All payment parameters will be averaged. The maximum payment factor shall be 100 percent. Roadway Acceptance:For: Pavement density PWL will be calculated for the pavement density. A mixture with density results below 40 PWL is subject to removal as directed by the engineer. The percent payment for pavement density will be calculated using the formula: (61)Percent Payment = 55 + 0.5PWL For: Surface tolerance (final wearing course travel lanes) Payment adjustments for surface tolerance will be based on the table below. For: Percent payment for roadway acceptance All payment parameters will be averaged. The maximum payment factor shall be 100 percent. Total Payment Factor:The total payment factor for the mixture used for the project will be calculated using the following formula: Total Percent Payment = (Percent payment for plant acceptance) + (Percent payment for roadway acceptance) - 100 Payment Adjustment Schedule: Smoothness and Percent Anti-Strip
1 inch/mi = 15.8 mm/km QC/QA Tests for Louisiana
MaineQuality ControlThe contractor is responsible for developing the mix design for the project, providing a QC plan that must be approved by the engineer prior to construction, and providing qualified personnel and equipment to conduct QC testing. The QC inspections and tests must be documented and provided to Maine DOT. The contractor must maintain records of all inspections and tests. These records shall indicate the nature, number, and type of deficiencies found; the quantities approved and rejected; and the nature of the corrective actions taken. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated on the following properties: gradation, asphalt content, theoretical MSG, CA angularity, FA angularity, air voids, VMA, VFA, dust-to-asphalt ratio, flat or elongated particles, percent moisture, and TSR. The contractor must exercise control over the following properties: asphalt content, temperature of mix, temperature of mat, percent TMD, gradation, air voids, VMA, VFA, Rice specific gravity, CA angularity, and dust-to-asphalt ratio. Quality AssuranceMaine DOT is responsible for QA and acceptance of the material. QA is accomplished using verification testing. Maine DOT's verification tests are independent of the contractor's QC tests. Lot size is usually 6000 Mg or less, with sublots of 1500 Mg or less. AcceptanceThe contractor's control tests are not used for acceptance. Acceptance is based on Maine DOT's verification tests. If the QC and QA test results do not agree, acceptance is based on referee testing for asphalt content, density, air voids, and VMA. The testing frequencies vary, depending on the property being measured. Pay FactorsPay factors are assigned for gradation, asphalt content, in-place density, air voids, and VMA. The determination of these factors uses quality-level analysis and price adjustment or f factors listed in the specification for the applicable property. Pay factors are assigned on a lot-by-lot basis. The composite pay factor is then computed by: (62)CPF = [ f1 ( PF1 ) + f2 ( PF2 ) + ... + fj ( PFj ) ] / Σf QC/QA Tests for Maine
NA = Not applicable MinnesotaQuality ControlThe contractor is responsible for developing the mix design in accordance with AASHTO TP-4, June 1997, or the Asphalt Institutes' Superpave Mix Design Manual (SP-2), such that it meets the requirements of the specification. In addition, the contractor is responsible for providing a QC plan that must be approved by the engineer prior to construction and providing qualified personnel and equipment to conduct QC testing. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated on the following properties: gradation; asphalt content; voids; VMA; TSR; compaction @ Ndes, Nini, and Nmax; VFA; FA angularity; CA angularity; Gmm; Gmb; Gsb; mix moisture; and dust-to asphalt ratio. The contractor must exercise control over the following properties: asphalt content, gradation, voids, mix moisture, VMA, FA angularity, density, CA angularity, and percent Gmm @ Ndes. In addition, the contractor must provide split samples to the engineer for verification testing. Testing frequency will be equal to the day's planned production divided by 1000, then rounded to the next whole number. Quality AssuranceMinnesota DOT is responsible for QA and for the acceptance of the material. The assurance process is achieved through the use of verification tests conducted on split samples, observation of sampling and testing performed by the QC personnel, the taking of additional samples for testing, and the monitoring of the required QC summary sheets and control charts. Lot size varies based on the contract quantity. Verification tests are conducted once per day on all production parameters. AcceptanceAcceptance is based on the QC tests as verified by Minnesota DOT's tests for gradation, asphalt content, maximum specific gravity, Gmb, air voids, VMA, and density. Pay FactorsPay factors are assigned for nonconforming mixes for the following properties: gradation, FA angularity, CA angularity, VMA, asphalt content, and Gmm @ Ndes. For these characteristics, the lowest single payment applies according to the following table: Payment Schedule
The pay factor for in-place density is determined on a lot-by-lot basis, with the number of lots determined by the following table: Determination of Lots for Density
1 ton = 0.907 Mg The pay factor is then computed using the following table: Payment Schedule for Density
The profile index is determined using a California-type profilograph. Profiles will be made for segments of 0.1 km. The following table determines the pay factor for smoothness: Payment Schedule for Smoothness
QC/QA Tests for Minnesota
NA = Not applicable MississippiQuality ControlThe contractor is responsible for developing the mix design for the project. In addition, the contractor is responsible for providing a QC plan that must be approved by the engineer prior to construction. The contractor must also provide qualified personnel and equipment to conduct QC testing. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated on the following properties: gradation, asphalt content, asphalt properties, voids @ Ndes, VMA @ Ndes, fractured faces, TSR, Ndes, Nini, Nmax, stripping, RAP gradation, FA angularity, MSG, and dust-to-asphalt ratio. The contractor must exercise control over the following properties: asphalt content, gradation, voids @ Ndes, mix moisture, VMA @ Ndes, FA angularity, density, fractured faces, MSG, stripping, and RAP gradation. In addition, the contractor must provide split samples to the engineer for verification testing. Sampling frequency for QC of voids, VMA, gradation, MSG, FA angularity, CA angularity, RAP gradation, stripping, and asphalt content is as follows: Sampling Frequency
1 ton = 0.907 Mg Determination of the lots for density testing is as follows: Lot Determination for Density
1 ton = 0.907 Mg Quality AssuranceMississippi DOT is responsible for QA and acceptance of the material. QA is accomplished by verification testing on split samples, testing additional samples at any time, and observing the QC tests. Lot size varies based on the contract quantity. AcceptanceAcceptance is based on the QC tests as verified by Mississippi DOT's tests for total voids, VMA @ Ndes, gradation, asphalt content, and density. Acceptance for smoothness is based on the observed contractor QC tests. Should the QC tests and the verification tests fail to meet the allowable differences, the engineer's test results will be used for acceptance. Pay FactorsPay factors are assigned for gradation, in-place density, total voids @ Ndes, smoothness, and VMA @ Ndes. Pay factors for these properties can be determined from the following tables: Pay Factors for Mixture Quality
* Minimum single pay factor applies. Pay Factors for Density
Pay Factors for Smoothness
1 inch/mi = 16 mm/km QC/QA Tests for Mississippi
NA = Not applicable New YorkQuality ControlThe contractor is responsible for developing the mix design for the project. In addition, the contractor is responsible, through the mix manufacturer, for providing a QC plan that must be approved by the engineer prior to construction. The contractor must allow the engineer access to all testing procedures, calculations, test documentation, and plotting of results. Mix design verification is evaluated on the following properties: gradation, asphalt content, compaction @ Nini, Ndes, Nmax, VMA, VFA, dust-to-asphalt ratio, CA angularity, FA angularity, sand equivalent, and flat or elongated particles. The contractor must exercise control over the following properties: asphalt content, gradation, MSG, BSG, air voids, VMA, VFA, moisture content, RAP extraction, mix temperature, and density. Additionally, the contractor must provide split samples for verification testing by the New York State DOT. The lot size is 1 day's production of a JMF with equal sublots not to exceed 1150 metric tons. Quality AssuranceNew York State DOT is responsible for QA and acceptance of the material. New York State DOT's assurance tests are independent of the contractor's QC tests. The contractor's control tests are used to assign a quality adjustment factor (QAF) for pay factors if the results agree with the verification test results. If New York State DOT's tests and the contractor's tests are not within specified tolerances, referee testing is conducted on independent samples and these results will be used for the determination of the QAF. AcceptanceAcceptance for density is based on the PWL of the percent MTD. Acceptance for gradation, air voids, mix moisture, asphalt content, VMA, VFA, MSG, and BSG is based on the contractor's QC tests if the results are within specified tolerances of New York State DOT's tests. Pay FactorsPay factors are assigned for gradation, asphalt content, in-place density, and air voids. The method for determining the pay factors is currently being researched. QC/QA Tests for New York
NA = Not applicable North CarolinaQuality ControlThe contractor is responsible for developing the mix design for the project and providing a QC plan that must be approved by the engineer prior to construction. The QC program will include process control inspection, sampling and testing, and necessary adjustments in the process that are related to the production of a pavement that meets all of the requirements of the specification. The contractor must also provide qualified personnel and equipment to conduct QC testing. The contractor must allow the engineer access to the laboratory to observe any and all testing procedures, calculations, test documentation, and plotting of results. The contractor must exercise control over the following properties: asphalt content, gradation, air voids @ Ndes, VMA @ Ndes, VFA @ Ndes, Gmm, Gmb @ Ndes, dust-to-asphalt ratio, percentage of MSG @ Nini, and aggregate moisture content. In addition, the contractor must provide split samples to the engineer for assurance testing. Testing frequency is as follows: Testing Frequency
Quality AssuranceNorth Carolina DOT is responsible for QA and for acceptance of the material. The verification tests are conducted on split samples. Testing frequency is equal to or greater than 10 percent of the contractor's control testing. QA is accomplished by conducting verification tests on split samples, observing tests conducted by the contractor, monitoring control charts, and conducting assurance testing on samples independent of the QC tests. AcceptanceAcceptance is based on the QC tests as verified by North Carolina DOT's tests for asphalt content, Gmm, Gmb @ Ndes, and density. Pay FactorsPay factors are assigned for gradation, binder content, air voids, VMA @ Ndes, density, and profile index. Pay factors are determined as follows: Payment for Mix Produced in Warning Bands*
* Minimum single payment applies. The pay factor for density is determined using the following formula: (63)PF = 100 - 10 (D)1.465 where: PF = pay factor computed to the nearest 0.1 percent The pay factor for smoothness is determined on a lot-by-lot basis, where a lot is 25 test sections of 100 ft (30 m) of single lane. Measurements are made using a North Carolina Hearne Straightedge. The pay factor is assigned as follows:
QC/QA Tests for North Carolina
NA = Not applicable FHWA-HRT-04-046
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
This page last modified on 06/09/06 |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||