Utilization of Recycled Materials in Illinois Highway Construction

APPENDIX

2001 Recycled Materials Quantities
MaterialMetric UnitCodeQuantityEng. UnitCodeQuantity
ACBFSMTon014CMM183,416Tons014CM18168
MTon033CMM1361,652Tons043CA06617
MTon033FAM214,329---- 
MTon043CAM06626---- 
MTon053CAMO6809---- 
Sub-Total (Tons)78,127  785
Total (Tons)78,912   
Cost@$15.25/Ton$1,203,411   
By- Product LimeMTon003FAM016,477Tons003FA019,807
MTon003FAM02380Tons003FA02249
MTon004MFM0218,712Tons004MF021,321
MTon004MFM035,441Tons004MF031,183
Sub-Total (Tons)34,204  12,560
Total (Tons)46,764   
Cost@$15/Ton$701,457   
Fly AshMTon37801M41,080CYD21605111,896
MTon37802M5,136CYD2162213,220
CM21605M422,981CYD218031,327
CM21614M258---- 
CM218032,432LBS/CYDAvg. Unit Wt. In PCC130
CM21622M1,644
Sub-Total (MTons)2179,186  7,456
Total (MTons)86,642   
Total (Tons)95,566   
Cost@$27.50/Ton$2,628,070   
Glass BeadsLBS604019,768,000LBS706013,880,800
LBS60407968,000LBS70602
LBS706091,380---- 
Sub-Total (LB.S)10,737,380  3,880,800
Total (LB.S)14,618,180   
Total (Tons)7,309   
Cost@$0.17/LB$2,485,091   
GGBFS2MTons37821M479---- 
Sub-Total (MTons)479   
Total (Tons)528   
Cost@$57/Ton$30,090   
Micro- silicaKG37852M111CYD216091,620
CM21609M2,436LBS/CYDAvg. Unit Wt. In PCC33
CM21622M1,644
Sub-Total (LB.S)176,443  53,460
Total (Tons)115   
Cost@$440/Ton$50,579   
RAP3MTon017CAM0614,430Tons017CM0124,026
MTon017CAM101,027Tons017CM112,107
MTon017CMM0147,601Tons017CM1337,675
MTon017CMM102,059---- 
MTon017CMM1182,773---- 
MTon017CMM12449---- 
MTon017CMM13283,106---- 
MTon017CMM1661,894---- 
MTon017CMM1813,610---- 
Sub-Total (Tons)559,165  63,808
Total (Tons)622,973   
Cost@$32/Ton$19,935,128   
2001 Recycled Materials Quantities
MaterialMetric UnitCodeQuantityEng. UnitCodeQuantity
RCP4MTon014CMM18209Tons019CA0614,245
MTon019CAM0614,096Tons019CM1847,309
MTon019CAM0718Tons059CA0622,529
MTon019CMM18162,418---- 
MTon059CAM0637,715---- 
MTon059CAM10394---- 
MTon059CMM06229---- 
Sub-Total (Tons)14237,233  84,083
Total (Tons)15321,316    
Cost@$5/Ton16$1,606,578   
Steel SlagMTon039CMM115,965Tons039CM116,227
MTon039CMM13115,625Tons039CM1325,113
MTon039CMM1610,364Tons039FA208,412
MTon039FAM206,552Tons039FM20380
MTon039FMM201,659---- 
Sub-Total (Tons)17154,601  40,131
Total (Tons)18194,733   
Cost@$16.2519$3,164,409   
R
E
I
N
F
O
R
C
E
M
E
N
T

S
T
E
E
L
Welded Wire FabricSM62803M01531SYD62803015,632
SM62803M0222,023SYD628030231,934
---- SYD6280304179
Sub-Total (SYD)2026,975  37,746
Total (SF)21582,484   
Cost@$0.35/SF22$203,869   
RebarKG62901M408,910LBS629014041,415
KG62901M300812LBS62901604,965,656
KG62901M40035,201LBS6290940133,209
KG62904M500204LBS629096013,055,840
KG62901M60897,510---- 
KG62909M403,471---- 
KG62909M400379,214---- 
KG62909M604,163,026---- 
Sub-Total (LBS)2312,101,808  18,196,120
Total (Tons)2415,149   
Cost@$690/Ton25$10,452,785   
WBBS5
Total (Tons)260.00   
$0.00   
  1. ACBFS: Air-Cooled Blast Furnace Slag
  2. GGBFS: Ground Granulated Blast Furnace Slag
  3. RAP: Recycled Asphalt Pavement
  4. RCP: Recycled Concrete Pavement