Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram
Office of Planning, Environment, & Realty (HEP)
HEP Events Guidance Publications Glossary Awards Contacts

Context Sensitive Solutions Technical Assistance: Florida Department of Transportation

Meeting Summary

Welcome from FHWA and Introductions

DeWayne Carver, FDOT, kicked off the meeting by welcoming everyone and letting all participants introduce themselves. He explained that FHWA had sponsored the meeting to engage FDOT Division Directors in FDOT’s Complete Streets implementation efforts.

Fleming El-Amin of FHWA thanked the FHWA Florida Division for helping to make the meeting possible, and provided all participants with two handouts. He explained that one of the handouts offered information on FHWA’s CSS website, including information on CSS as it relates to Complete Streets. The handout also provided a list of related program websites and contact information for FHWA personnel on the livability team. The other handout listed FHWA pedestrian and bicycle resources, including publications, guidance, and websites. Fleming explained that most of the resources were produced very recently and covered a wide range of topics relevant to CSS and Complete Streets.

Fleming indicated that Florida was the sixth State to receive technical assistance under the current FHWA CSS technical assistance effort. He also announced that FHWA was preparing to host virtual peer exchanges among the States that received TA and others, including one focused on Complete Streets on October 25.

Presentation on Complete Streets Best Practices from Other DOTs

A national overview of Complete Streets and CSS practice, including examples of what other States were doing, was provided. Key items mentioned during the presentation included:

View of Route 202, winding through a rural area.
Figure 1: Pennsylvania DOT used the Smart Transportation process to rescope the Route 202 bypass from a four-lane controlled access freeway with a 65-mph design speed to a two-lane multimodal parkway with a 35-mph design speed. Lower speeds allowed for bending the road to fit into the surrounding context as well as eliminating the need to clear cut wide swaths of adjacent woodland. The design also eliminated large overpasses and reduced the number of lanes. Thus, the rescoping led to dramatically fewer impacts, and at less than one-half of the original project cost. Source: Al Biehler, Former Secretary, Pennsylvania DOT

Description of the FDOT Complete Streets Policy and Guidance

DeWayne Carver, FDOT, provided an overview of Complete Streets policy implementation at the meeting. Key items mentioned during the presentation included:

Challenges to Implementation Discussion

Participants were divided into four breakout groups and given instructions to come up with any challenges they associated with FDOT’s Complete Streets implementation plan. Participants first had to rapid-fire list any challenges, and those are listed below from each group.

Table 1: Challenges to Complete Streets Implementation
Group 1 Group 2
  • Staff to do context classifications
  • Maintain project schedules
  • Local input
  • Cost impacts to planning budget
  • Cost impacts to individual projects
  • 3R targets
  • Local visions of corridors versus current use
  • Freight versus bike/pedestrian
  • Long term maintenance commitment
  • Politics – high turnover in local governments
  • Training for staff
  • Statewide consistency
  • Realistic timeframe for implementation
  • Buy-in – internal and external
  • Staff – Who? How Many?
  • Funding – non-capacity program
  • Coordination with L/A (limited access) or high-capacity roads
  • Managing local expectations
  • Decision making/managing expectations (ability to say no)
  • Staff training, buy-in/role
  • Not done in silo – coordination with technology
  • Future land use
  • Future technology – automated vehicles/connected vehicles?
  • Is it about just bikes? Pedestrians? Or mobility?
  • Property owner engagement
  • Not silver bullet
Group 3 Group 4
  • Funding
  • Right-of-way challenges
  • Classification determination/local agreement
  • Design speed?
  • Escalation matrix
  • Resurfacing – scoping
  • People/organizations involved/city/county
  • Bike lanes versus parking
  • Metropolitan planning organization/county priorities
  • Picking the context – Where do you draw the lines? Future conditions? How included? Minimum length of a segment?
  • Local government expectations – what level of engagement is expected?
  • Perception of Complete Streets
  • Maintenance questions
  • Doing the context classification with existing resources
  • How does context classification affect project development and environment (PD&E)?
  • Culture change in FDOT – silos
  • How do we balance the function/purpose of the roadway?
  • Revisiting the status/role of level of service

Once each group came up with their list of challenges, they discussed them and wrote down their top ideas, rephrasing as necessary. All breakout groups then came back together as one big group and posted their challenges on the wall, categorized them, and discussed. Clarifying notes are provided as needed.

Table 2: Categorized Complete Streets Implementation Challenges
Category Challenges
Implementation Phasing
  • How does context classification affect/relate to PD&E [Clarification: The Districts noted that once a project enters PD&E, if they have to do context classifications it would break the schedule and budget.]
  • Doing context classification within existing resources [Clarification: Where do Districts get the staff or consultant funding for this new layer of work?]
  • Maintain project schedules
  • Context class determination
  • Realistic time frame for implementation
  • The effort to obtain local input
  • How to staff context classification
  • Cost impact to projects
  • Planning and budget impact for eight classifications
  • County/MPO requests don’t match priorities (MPOs set priorities then later ask FDOT to do something not in the original list)
  • Statewide consistency for classifications and funding
Funding
  • Additional right-of-way (R/W) needs (when to draw the line if completing a street requires new R/W) [Clarification: The concern was that often a community could ask for a feature that cannot be accommodated without buying new R/W.]
  • Managing local expectations
  • Decision-making matrix: How do you say no?
  • Funding: who pays?
  • 3R targets -> funding shortfall
  • Funding non-capacity infrastructure (RRR, Bridge Replacement)
Managing expectations
  • Long term maintenance commitment – locals [Clarification: The concern was that FDOT should not be responsible for maintaining everything that is built as part of a project, for instance decorative lighting or perhaps a short walking connector to a local facility.]
  • Local government expectations – what level of engagement is expected
  • Future land use – if FDOT agrees to complete a street based on future land use changes, how does FDOT ensure the locals do what they say
  • Local visions of the corridor versus current use (Dreams versus reality)
  • Politics – High turnover in local elected officials results in changing visions
Project Delivery Process – Scoping
  • How do we balance the function/purpose of the roadway…e.g. Strategic Intermodal System (SIS), level of service (LOS) [Clarification: Since road space is finite, often times, there is not enough space to layer in a bike lane, for instance, without reallocating space from other uses (e.g. take out a lane from through traffic)]
  • MPO: Realizing SIS needs in addition to Complete Streets
  • Bike lanes versus on-street parking
  • Design/target speeds
  • Funding non-capital
Training/Culture change
  • Culture change in FDOT – silos [Clarification: The structure of FDOT, in which units are specialized to match production needs, sometimes insulates staff in certain units from understanding the big picture.]
  • Training for staff and consultants (need to get training at all levels)
  • Staff: who, how many?
  • Staff training (internal buy-in, understanding roles)

Strategies to Address Challenges

The participants were once again divided into the original four breakout groups and each assigned one of the first four categories listed above. The training/culture change category was not assigned to a breakout group but was instead provided to DeWayne so he could brainstorm solutions from the FDOT Headquarters perspective. The strategies developed by each of the groups are shown below. Clarifying notes are provided as needed.

Table 3: Strategies to Address Complete Streets Implementation Challenges
Group 1: Managing Expectations Group 2: Project Delivery Process – Scoping
  • 4P – Priority project programming process → helps manage expectations
  • Timeframes for data collection/ground truth (input by partners)
  • Timeframe for implementation (input by partners)
  • Guidance would be helpful, a checklist (input by partners)
  • Coordination with locals
  • Transition timeframe
  • Capacity – process works, no impacts, MPO prioritize [Clarification: implementing the Handbook for capacity increase projects where the MPO has matched scope requests to the budget, will not impact project delivery.]
  • Non-capacity – FDOT owns currently, we prioritize – no input, context requires input [Clarification: Historically, FDOT has “owned” the process for non-capacity 3R projects, meaning that the scope and budget are relatively cut and dry and FDOT has not shared a lot of the decision-making with stakeholders.]
  • Funding not on five year
  • State funds – not on priority, but data-driven, not recurring, always changing
  • Some problems not complete street friendly: 3R, bridge
  • Safety – only what data-driven, highway safety improvement program (HSIP) funds
  • LAP (local agency program) projects – federal funds
  • TA (transportation alternatives) funds – TPO (transportation planning organization) priority
  • Trail funds
Group 3: Funding Group 4: Implementation Phasing
  • Better clarification that additional funding will be local/federal, MPO
  • 3R projects would need local funding during scoping process – commitment
  • Reallocation of 3R dollars (excess 3R)
  • More time to phase-in [Clarification: More time is needed particularly for projects requiring primary or secondary context classification measures].
  • Enhanced education for all
  • Clarify only context during planning for projects [Clarification: Impacts on project schedules and budgets will accrue as the need to do context classifications are retroactively applied to projects in or past PD&E.]
  • Clarify current and future classification

Prioritization of Strategies/Closing Discussion

At the conclusion of the workshop, each breakout group was asked to report out on one of their proposed strategies to overcome the challenges discussed earlier. The highlights of the reporting out are indicated below. In addition to the strategies, an action item emerged out of the discussion for DeWayne to investigate the wording on local engagement in the flow charts of the Handbook to ensure that it is clear. Additionally, District Directors agreed that they should meet more regularly to discuss progress on implementing the Complete Streets Handbook. Clarifying notes are provided as needed.

Table 4: Priority Strategies to Address Complete Streets Implementation Challenges
Challenge Priority Strategies
Managing Expectations
  • 3R projects already in the system should be grandfathered in prior to Handbook adoption.
  • Following the 4P process helps manage expectations. [Clarification: The 4P process is a scope development process used by two of the seven FDOT Districts to establish project features, budget and schedule, prior to the project being programmed.]
Project Delivery Process – Scoping
  • In the Handbook, a distinction should be made between capacity and non-capacity projects, regarding how to apply the Handbook’s strategies.
  • Complete streets mesh well with capacity projects. However, FDOT owns non-capacity projects, which are based on design criteria and public engagement is not incorporated into every step of these projects.
  • The concept of “no new funding” needs to be reinforced in the Handbook. [Clarification: For 3R projects, the public needs to understand that these are on a fixed budget with a tight schedule and that only Complete Streets elements that can be accommodated within the original budget can be implemented.]
  • More time needs to be allotted for phasing in.
Funding
  • The Handbook should clarify that funding for anything that adds to the 3R project scope needs to come from the local community, the federal government, or MPOs.
  • The local funding commitment needs to come during scoping. [Clarification: Once the project scope is set, it is entered into the Capital Program, which is a public document. The budget and schedule for that project needs to be established prior to being programmed to avoid politically troublesome budget reallocations or schedule delays from one project to another.]
Implementation Phasing
  • The Handbook should clarify the role of existing and future context classifications. [Clarification: Determining future land-use classifications is a complicated process relying on speculative growth and development projections and should be limited to major FDOT projects.]

[1] Indiana Department of Transportation. “Open Roads (Practical Design).” (website) Available online:

http://www.in.gov/indot/3261.htm, last accessed August 16, 2017.

[2] Colorado Department of Public Health and Environment, Colorado Department of Local Affairs, and Colorado Department of Transportation. (2016). Colorado Downtown Streets: A Tool for Communities, Planners, and Engineers. Available online:

https://drive.google.com/file/d/0B-vz6H4k4SESQk9vSGRlQll5dnM/view, last accessed August 16, 2017.

Updated: 10/27/2017
HEP Home Planning Environment Real Estate
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000