TECHBRIEF |
This TechBrief is an archived publication and may contain dated technical, contact, and link information |
Publication Number: FHWA-HRT-13-049 Date: March 2010 |
Publication Number: FHWA-HRT-13-049 Date: March 2010 |
PDF files can be viewed with the Acrobat® Reader®
FHWA Publication No.: FHWA-HRT-13-049 |
This document is a technical summary of the Federal Highway Administration (FHWA) report FHWA LTBP Workshop to Identify Bridge Substructure Performance Issues: March 4–6, 2010, in Orlando, FL (FHWA-HRT-11-037). Copies are available through the National Technical Information Service (NTIS).
NTIS Accession No. of the report covered in this TechBrief: PB2013-107742
This TechBrief provides an overview of the proceedings and findings of the “FHWA Workshop to Identify Bridge Substructure Performance Issues” held in Orlando, FL, from March 4 to 6, 2010. The purpose of the workshop was to consider overall bridge performance and identify geotechnical performance metrics that may correspond to good and poor performance. The issues identified and the recommendations made at the workshop are being used in the design and implementation of the Long-Term Bridge Performance (LTBP) program.
FHWA launched the LTBP program to improve understanding of bridge performance. The program’s mission is to foster improved bridge performance, health, stewardship, and management through the analysis of data collected over a 20-year period on representative samples of highway bridges in the United States. To achieve this mission, the program is designed to produce or support improved deterioration models, reliable life-cycle cost and forecasting models, design procedures, and decisionmaking tools. One of the earliest steps in the implementation of the LTBP program was determining which aspects of bridge performance to study
.After the LTBP program was initiated in April 2008, FHWA conducted a series of focus group meetings with bridge experts from State transportation departments in different regions of the country. The conclusions from those meetings are the subject of future TechBriefs. Among the general bridge performance issues identified, the following issues related to structural foundation elements or geotechnical factors were documented:
In order to further evaluate, prioritize, and refine these geotechnical issues, FHWA sponsored a workshop in Orlando, FL, from March 4 to 6, 2010. FHWA invited participants with different backgrounds and perspectives to ensure diversity of input. The 43 workshop attendees included bridge/geotechnical experts from State transportation departments, FHWA, academia, and industry groups.
The workshop served as an opportunity to define how geotechnical issues could be incorporated in the LTBP program, what geotechnical data should be collected under the LTBP program, and what tools and technologies would be needed for collection of that data. The workshop consisted of a plenary session followed by three breakout sessions with the following objectives:
The workshop began with a plenary session at which a series of speakers provided an overview of the LTBP program, summarized the findings from the focus group meetings, described the general LTBP research approach, discussed the pilot bridge phase, and gave an overview of geotechnical factors related to bridge performance. This session was intended to provide context for the subsequent breakout session discussions.
Several examples of geotechnical issues affecting bridge performance were described, including mechanically stabilized earth (MSE) walls, foundations on rock, abutment issues (in particular, settlement at the bridge-abutment interface and its effects on the superstructure), and scour.
The purpose of the breakout sessions was to consider overall bridge performance and identify geotechnical performance indicators that may correspond to good and poor performance. The information generated was to be provided to the LTBP program as recommendations to accommodate collection of additional data as well as to identify methods to collect and evaluate the data.
The focus group meetings held by the LTBP program had identified a few general topics related to substructures and foundations. The participant groups were asked to consider these and other geotechnical issues related to bridges that could merit consideration and to identify and define the key bridge performance issues related to substructures and foundations, data needs and gaps related to these key issues, and tools, technology development, and monitoring necessary to collect critical geotechnical performance data for the LTBP program.
Breakout Session I: Bridge Performance Issues
The first breakout session focused on identifying the most important bridge performance issues related to foundations, substructures, and geotechnical features. This breakout session developed and prioritized the key geotechnical issues that affect critical aspects of bridge performance as well as performance of the bridge as a whole.
Following brainstorming on bridge performance issues in the three breakout groups, the lists and priorities from each group were collected and presented. Despite different approaches to identifying and rating the importance of the issues, the groups generally identified the same issues and priorities. A summary of the priorities identified by each group is presented in table 1. Common issues identified by multiple groups were the bump at end of the bridge, integral abutments, settlement of abutments and piers, material corrosion, and scour.
Table 1. Breakout session I: Summary of priority geotechnical performance issues identified by each group.
Group 1 |
Group 2 |
Group 3 |
---|---|---|
|
|
|
Breakout Session II: Data Needs and Gaps Related to Geotechnical Performance Issues for Bridges
The second breakout session focused on discussing the data needs and gaps related to the key performance issues identified in the first breakout session. Each breakout group developed a list of data that can currently be collected, data that need to be collected during the course of the 20 year research program, and data that cannot currently be collected but would be important to the objectives of the program.
Following brainstorming on data needs and gaps in the three breakout groups, the lists and priorities from each group were presented to the larger group. The complete list of data needs and gaps identified by the three groups is available in the full report, FHWA LTBP Workshop to Identify Bridge Substructure Performance Issues: March 4–6, 2010, in Orlando, FL. Table 2 provides some of the data needs identified by the groups for the performance issues identified at the workshop. It was recommended that a follow-up task group formulate research needs related to data needs and gaps for the LTBP program.
Table 2. Breakout session II: Data needs and gaps related to priority geotechnical performance issues for bridges.
Performance Issue |
Data Needs |
|||
---|---|---|---|---|
Construction Records |
Inspection and Maintenance History |
Characterization of Service Environment |
Post-Construction Monitoring |
|
Approach- |
|
|
|
|
Material degradation |
|
|
|
|
MSE walls |
|
|
|
|
Hydraulics |
|
|
|
|
Breakout Session III: Tools, Technology Development, and Monitoring Needed for Geotechnical Performance Data
The third breakout session focused on how geotechnical performance data can be collected. The breakout groups identified tools and technologies that are currently available and should be used in the LTBP program as well as technology development and monitoring that are needed to address identified data gaps.
Following brainstorming on tools, technology development, and monitoring in the three breakout groups, the lists and assessments from each group were presented to the larger group. The benefit of this session was that the breakout groups identified a comprehensive list of tools and technologies for data collection and, in some measure, mapped the tools/technologies to specific data needs as well as future and long-term needs. Table 3 provides some of the ideas developed on tools, technology development, and monitoring; the complete list is provided in the full report, FHWA LTBP Workshop to Identify Bridge Substructure Performance Issues: March 4–6, 2010, in Orlando, FL. It was recommended that a follow-up task group better define the tools, technology development, and monitoring of geotechnical-related bridge assets for the LTBP program.
Table 3. Breakout session III: Needed tools, technology development, and monitoring.
Geotechnical Performance Issue |
Tools Currently Available |
Short-Term Technology Development |
Long-Term Technology Development and Monitoring |
---|---|---|---|
Bump at the end of the bridge |
|
|
|
Foundations |
|
|
|
Deterioration |
|
|
|
Earth-retaining structures |
|
|
|
Hydraulics (scour) |
|
|
|
GPS = Global Positioning System.
LIDAR = Light detection and ranging.
MEMS = Microelectromechanical systems<
TDR = Time domain reflectometry.
WIM = Weigh in motion.
A number of short-term geotechnical bridge performance priorities emerged from the workshop. These priorities can be summarized in four categories. For each of the performance issues, assessments of the cause and effect of the issue, the quality control and quality assurance aspects,
the detection and monitoring aspects, and the remedial actions to overcome the issues need to
be completed.
Approach/bridge interface issues included the following:
Material degradation/corrosion/long-term deterioration issues included the following:
MSE wall issues (material degradation and assessment of wall integrity) included the following:
Hydraulic issues included the following:
From the results of this workshop and other available information, these issues can be considered for inclusion on the LTBP list of study topics. Each issue will have to be further studied for the state of practice, related research, and identification of key questions that might be addressed under the LTBP program.
A number of data needs were identified for the short-term bridge performance issues identified. Some data needs, such as as-built plans and climate data, cut across all the performance issues.
The workshop participants did an outstanding job of identifying the data needs. The identification of needed tools, technology development, and monitoring was helpful to FHWA.
Researchers—This study was performed by Rutgers, the State University of New Jersey, Highway R&D Services; the Virginia Center for Transportation Innovation and Research; Iowa State University; and Parsons Brinckerhoff. For additional information, contact Dr. Hamid Ghasemi in the FHWA Office of Infrastructure Research and Development, located at 6300 Georgetown Pike, McLean, VA 22101-2296. Distribution—This TechBrief is being distributed according to a standard distribution. Direct distribution is being made to the Divisions and Resource Center. Availability—Report No. FHWA-HRT-11-037, FHWA LTBP Workshop to Identify Bridge Substructure Performance Issues: March 4–6, 2010, in Orlando, FL, is available. It can be obtained from the National Technical Information Service, www.ntis.gov. Key Words—LTBP program, Bridge performance, Bridge substructure, Substructure performance, Long-term bridge performance. Notice—This document is disseminated under the sponsorship of the U.S. Department of Transportation in the interest of information exchange. The U.S. Government assumes no liability for the use of the information contained in this document. The U.S. Government does not endorse products or manufacturers. Trademarks or manufacturers’ names appear in this report only because they are considered essential to the objective of the document. Quality Assurance Statement—The Federal Highway Administration (FHWA) provides high-quality information to serve Government, industry, and the public in a manner that promotes public understanding. Standards and policies are used to ensure and maximize the quality, objectivity, utility, and integrity of its information. FHWA periodically reviews quality issues and adjusts its programs and processes to ensure continuous quality improvement. |