U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
This report is an archived publication and may contain dated technical, contact, and link information |
|
Publication Number:
FHWA-HRT-05-159
|
Previous | Table of Contents | Next
This chapter presents a summary of the costs associated with pile driving operations on the CA/T project. The costs presented in this report were obtained directly from the contractor and represent the contractor's bid estimates identified in the individual contracts. The primary purpose of the cost data is to document the approximate cost of pile driving on the CA/T project; however, the data may also be useful to design engineers for planning purposes.
The contractor's bid costs for pile driving are summarized in table 13 by pile type. Unless noted, the costs in table 13 do not include costs for preaugering or costs associated with the mobilization or demobilization of the contractor's equipment. Steel pipe piles had the highest unit costs, ranging from $213 per meter for the 81.3-cm pile to $819 for the 154.9-cm pile. Unit costs for the PPC piles were lower, ranging from $72 to $197 per meter for the 30-cm PPC piles and $95 to $262 per meter for the 41-cm piles. As one would expect, the unit costs tended to decrease with the increasing size of the contract. The contractor's bid costs for preaugering are summarized in table 14. Preaugering was not performed in contract C07D1, and preaugering costs were not identified in the contract C07D2 bid. As shown in table 14, the additional cost of preaugering ranged from $33 to $49 per meter.
Contract | Pile Type | Estimated Length of Pile Installed (m) | Estimated Cost of Installation | Cost per meter of Pile1 |
---|---|---|---|---|
C19B1 |
32-cm concrete-filled steel pipe |
550 |
$1,183,650 |
$213.19 |
C09A4 |
41-cm concrete-filled steel pipe |
5,578 |
$1,647,000 |
$295.27 2 |
C19B1 |
61-cm concrete-filled steel pipe |
296 |
$242,500 |
$819.26 |
C08A1 |
30-cm square PPC with stinger |
792 |
$156,000 |
$196.97 |
C19B1 |
30-cm square PPC with stinger |
2,177 |
$285,720 |
$131.24 |
C09A4 |
30-cm square PPC |
3,658 |
$600,000 |
$164.02 2 |
C07D2 |
30-cm square PPC with stinger |
3,981 |
$289,510 |
$72.72 |
C07D1 |
30-cm square PPC with stinger |
7,955 |
$652,500 |
$82.02 |
C19B1 |
41-cm square PPC with stinger |
6,279 |
$824,000 |
$131.23 |
C08A1 |
41-cm square PPC with stinger |
8,406 |
$2,206,400 |
$262.48 |
C09A4 |
41-cm square PPC with stinger |
14,326 |
$3,290,000 |
$229.65 2 |
C07D2 |
41-cm square PPC with stinger |
19,879 |
$2,396,800 |
$120.57 |
C07D1 |
41-cm square PPC with stinger |
32,918 |
$3,132,000 |
$95.15 |
Notes:
1. Unit costs include the costs of materials and labor for pile driving only. Preaugering is not included unless otherwise noted. See table 14 for preaugering unit costs. Mobilization and/or demobilization costs are not included.
2. Unit costs include the costs of preaugering.
Contract | Preaugering Depth Range (m) | Estimated Total Preaugering Depth (m) | Estimated Cost of Preaugering | Estimated Cost per meter |
---|---|---|---|---|
C08A1 |
0 to 30.5 |
2,134 |
$70,000 |
$32.80 |
C19B1 |
0 to 30.5 |
3,712 |
$182,655 |
$49.21 |