U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

Report
This report is an archived publication and may contain dated technical, contact, and link information
Publication Number: FHWA-HRT-06-078
Date: June 2006

Job Site Evaluation of Corrosion Resistant Alloys

APPENDIX F FHWA Project NUMBER NH-02-03

TEA-21 INNOVATIVE BRIDGE CONSTRUCTION PROGRAM

Evaluation Report

October 27, 2004

State: New Hampshire.

State DOT Contact: Mr. Paul Nadeau [(603) 645-1760].

NBI Bridge Number: 016101850007700.

Project Type: Replacement.

Location: Bridges on I-293 over Frontage Rd. and Brown Ave., Manchester, NH.

Innovative Material: Galvanizing reinforcing steel.

Bridge Description: These two bridges are discussed in a single report because of construction and innovative reinforcement commonalities and their proximity to one another. In each case, there are two-lane east- and westbound bridges that are part of a number of bridge reconstructions and replacements along I-293. The Frontage Road Bridge is about 300 mi east of the Brown Avenue Bridge. Figure 44 shows a perspective view of the latter bridge where the girders are set but the deck formwork has not been placed. Note job site storage of the galvanized reinforcement (circled) to the right of the in-place girders. Figure 45 provides a closer view. The deck specifications call for longitudinal #5 bars with 8-inch spacing and transverse #6 at 6-inch spacing. While a pavement overlay is normally employed for New Hampshire bridges, this is not being called for on the Frontage Road or Brown Avenue Bridges.

Click For Alternative Text

Figure 44. General view of the Brown Avenue Bridge under construction.

Click For Alternative Text

Figure 45. View of the in-place girders on the Brown Avenue Bridge.Note ECR extending from the top of the backwall.

Classification of galvanized reinforcement as innovative is conjecture, since this material has been available for decades, although its use as reinforcement in bridge construction has been limited. The fact that results from both research and field experience have been mixed from the corrosion performance standpoint, however, warrants its being included in this program.

Construction Sequence: At the time of the site visit (May 6, 2004), only the girders were in place on the Brown Avenue Bridge as noted above in conjunction with figures 44 and 45. Construction was more advanced at Frontage Road as explained below. Figure 46 shows a general view of the galvanized bar placement on the Frontage Road deck.

Click For Alternative Text

Figure 46. In-place galvanized reinforcement on the Frontage Road Bridge deck.

Reinforcement Specification: Initially, Type 316L or 316LN reinforcement conforming to AASHTO M 31M (M31) in accordance with ASTM A-955M-96 was specified for both Brown Avenue Bridges and 316L clad black bars (AASHTO M 31M (M31)) for the Frontage Road ones. The two east bound bridges were replaced in 2003; but because suppliers were unable to provide the stainless steel, ECR was substituted. This same supply problem arose for the clad reinforcement in 2004, and galvanized reinforcement was used as a substitute here.

Material Cost: Table 11 lists the as-bid costs for both the originally specified stainless and stainless clad reinforcement and for the replacement galvanized reinforcement for both bridges.

Table 11. Reinforcing steel costs.

Reinforcement Type

Bridge

Est. Quantity, kg

Unit Price

Est. Cost

Type 316L or 316LN

Brown Avenue

59,977

$5.15/kg

$308,882

Galvanized

$2.92/kg

$175,133

Clad Type 316L

Frontage Road

51,340

$4.15/kg

$213,061

Galvanized

$3.54/kg

$181,743

Concrete Specification: The concrete mix design is shown in table 12. This requires a minimum 30 MPa (4,000 psi) compressive strength at 28 days.

Table 12. Concrete mix design.

 

Sat'd Weight

Surface Dry Yield, m3

Cement Quebec Type II

173 kg

0.055

Blue Circle NewCem

173 kg

0.059

Manch. S&G Fine Aggr.

700 kg

0.264

Manch. S&G 0.75 inches

864 kg

0.327

Manch. S&G 0.375 inches

211 kg

0.080

Water

155 liters

0.155

Total Air

6.0%

0.060

Total

1.001


Daracem-100

3460 ml

Micro Air

2.0 ml

Water/cement ratio

0.45

Slump

127–203 mm

Unit Weight

2274 kg/m3

Prime Job Contractor:

George R. Cairns & Sons
8 Ledge Road
Windham, NH 03087
(603) 421-1888

Subcontractor:

E.D. Swett, Inc.

8 Industrial Park Dr.

Concord, NH 03301

(603) 224-7401

Steel Supplier:

Barker Steel Company, Inc.

55 Sumner Street

Milford, MA 01757

Job Site Storage: The galvanized steel for both bridges was delivered in plastic wrapping just prior to the placement schedule for the Frontage Road Bridge. Figures 47 and 48 show views of bar storage at this latter site. A distant view of bars at the Brown Avenue Bridge was indicated in figure 44, and figures 49 and 50 show closer views of straight and fabricated bars, respectively, at this location.

Click For Alternative Text

Figure 47. Bundled/wrapped bars at the Frontage Road job site.

Click For Alternative Text

Figure 48. Fabricated galvanized bars at the Frontage Road Bridge job site.

Click For Alternative Text

Figure 49. Stored galvanized bars at the Brown Avenue Bridge job site.

Click For Alternative Text

Figure 50. As-delivered galvanized bars at the Brown Avenue site after pulling back the plastic wrap.

Presence of Carbon Steel: Shear studs on the top girder flanges are carbon steel. A distant view of these can be seen in figure 46, and figure 51 provides a closer view. While no instances of electrical contact between the two metal types were apparent, this could inadvertently occur. Because potential of galvanized steel can be active to passive black steel, a corrosion cell could be established.

Click For Alternative Text

Figure 51. Closeup view of the in-place galvanized reinforcement relative to carbon steel studs.

Innovation Justification: Northern bridge decks in New Hampshire endure heavy winter precipitation and deicing salt use. Innovative reinforcements that provide enhanced corrosion resistance relative to that of black steel are being increasingly recognized as competitive on a life-cycle cost analysis basis.

Problems: The following difficulties and potential difficulties were cited for these two bridge projects:

  1. The problems associated with acquisition of both the 316L/316LN stainless steel reinforcement (Frontage Road Bridge) and clad 316L stainless reinforcement (Brown Avenue Bridge) were noted above.
  2. The potential galvanic corrosion problem that could arise from the galvanized reinforcement contacting the carbon steel studs that project from the top of girders was mentioned above.
  3. Many of the as-delivered galvanized bars had a brown-greenish surface deposit. Examples of this can be seen on some of the bars in figure 51, and a closer view is shown in figure 52 This caused delays and additional effort in that the contractor was told to remove the deposits to the extent possible. It was later determined that the deposits were residuals from a chromate pretreatment. It is not unexpected for such “lack of prior experience” problems to arise with innovative reinforcement.
  4. A concern was expressed that concrete cracking along the plastic mat spacers could occur because the openings in these may be too small to pass the coarse aggregate as the concrete is placed. Figure 53 shows a spacer in place. This, of course, is not related to the use of innovative reinforcement.

Click For Alternative Text

Figure 52. Deposits on galvanized reinforcing bars.

Click For Alternative Text

Figure 53. In-place bottom galvanized rebar mat with plastic mat spacer.

  1. Fabricated bars for the Brown Avenue Bridge, in particular, exhibited areas of disbonded zinc coating. This apparently resulted when bars were bundled together as the galvanized layer dried and the bars were subsequently pulled apart. Zinc layer dendrites (or icicles) were also present. Examples of the former are shown in figure 54 (circled regions) and of the latter in figure 55.

Click For Alternative Text

Figure 54. Examples of disbonding of the galvanized layer on fabricated bars for the Brown Avenue Bridge.

Click For Alternative Text

Figure 55. Galvanized layer disbonding and icicle on reinforcing bars. Examples of disbonding are also apparent.

Material Acquisition: The project team was able to acquire samples of the galvanized bars from the job site for analysis.

Previous    Table of Contents    Next

 

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101