U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
REPORT |
This report is an archived publication and may contain dated technical, contact, and link information |
|
![]() |
Publication Number: FHWA-HRT-13-046 Date: October 2013 |
Publication Number: FHWA-HRT-13-046 Date: October 2013 |
The purpose of this chapter is to present the factors that must be considered when developing a cost estimate for a DMM project for embankment or foundation support and to provide the user with a method of estimating the cost of DMM at the feasibility stage of the decision process. Cost estimating for DMM projects differs from that of conventional specialty geotechnical engineering processes because the project costs are heavily dependent on site conditions, construction methods, materials used, project performance requirements, and market conditions, all of which can vary significantly. A range of unit costs for DMM production works are provided that transportation department engineers may use to calculate reliable preliminary cost estimates for comparison with alternative technologies. These unit costs are provided for use in the preliminary stages of engineering design when limited site information is available. It is critical that engineers refine estimates based on project requirements and site-specific data. Engineers are encouraged to solicit cost estimates from qualified DMM contractors to develop more precise project budgets.
The factors that affect the costs of a DMM project are listed in table 21. Comments on how variations in these factors affect unit costs are also provided.
Considering the factors listed in table 21, a range of unit costs may be assumed for estimating purposes. The lower and upper limits of the range reflect the general conditions outlined in table 22. These costs include production (labor and equipment) and binder material costs only. Mobilization/demobilization, QC/QA, and engineering must be estimated separately.
Mobilization/demobilization costs depend on the location of the site relative to locations of qualified contractors. Also, the size of the project dictates the number of rigs to be mobilized to a site. A reasonable suggestion for mobilization/demobilization is approximately $80,000 to $150,000 per rig for a site located up to 200 mi (320 km) from qualified contractors.
QC/QA costs may be estimated as 3 to 5 percent of the production DMM costs. This estimate includes costs associated with the owner's tasks for assuring the quality of the work. The upper end of the range is applicable for projects with higher strength QC/QA criteria or permeability requirements less than 4.72 × 10-5 ft/day (10-6 cm/s) and the lower end may be applied for projects with lower strength acceptance requirements or a higher permeability criterion (greater than 4.72 × 10-5 ft/day (10-6 cm/s)). Pre-construction bench-scale testing may be estimated on a lump sum basis as $10,000 to $20,000.
The owner's engineering costs for conducting the site investigation, considering alternatives, designing the DMM system, developing the specifications, performing a limited bench-scale mixing program during design, and providing QA services are estimated to be about 10 percent of the DMM construction costs. The contractor's engineering costs for preparing as-built drawings, other submittals, and QC services are included in the unit costs listed in table 22.
For a design-build project, the owner's engineering costs should be added to the DMM construction costs.
Table 21. Generalized factors affecting costs of DMM projects for embankment and foundation support.
Factors Affecting DMM Costs |
Comments |
---|---|
Type of mixing |
Wet or dry. |
Presence and type of environmental contamination |
For the purposes of this report, the site soils for DMM work for embankment and foundation support are assumed to be uncontaminated and therefore do |
Binder materials |
|
Site access |
|
Site soils |
|
Project size/quantity of mixing work |
Unit costs ($/yd3 ($/m3)) are lower for larger projects (greater than approximately 26,000 yd3 (20,000 m3)). |
Depth |
Mixing to depths in excess of 25 m (80 ft) increases costs. |
Application |
|
QC/QA |
Excessively rigid QC/QA criteria or more consequences for non-conformance with specifications increase costs. |
Table 22. Unit costs and associated general project conditions.
Unit Production Cost ($/m3) (includes labor, equipment, and materials) |
Factors That Influence Unit Cost |
|
---|---|---|
Approximate low estimate (best case conditions) |
$100/m3 |
|
Approximate higher estimate (significantly more difficult site/project conditions) |
$140/m3 |
|
DMM items are typically measured and paid as indicated in table 19.