Church Street Bridge |
| Location | New Haven Interlocking and Rail Yard |
| State | CT |
| Completion Date | 2003 |
| Contact Person | Larry D'Addio, P.E., Connecticut Department of Transportation |
| Description | This truss-span bridge is 1,280 ft. long with 8 spans including 320-ft. truss span, 50 ft. high and 60 ft. wide. The Church Street South Extension project provided a new steel truss bridge over the New Haven Interlocking and Rail Yard, directly linking downtown New Haven and the Long Wharf and waterfront areas. To minimize disruption in the rail yard and improve work-zone safety for a crew working over active rail lines, ConnDot required that this portion of the bridge be completed in a single weekend night. The 320-ft long, 850 ton prefabricated truss center span was constructed over several months next to the active rail lines and then lifted into place on an early Sunday morning in May 2003 by a single high-capacity crane owned by Lampson International LLC. The crane, which required more than four weeks to assemble, lifted the entire truss span more the 65 ft. and moved it more than 100 ft. to its final position. Specifying prefabrication saved ConnDOT about a year on its overall contract time and at least $1.1 million. Prefabrication of the center span greatly improved constructability for O&G Industries; the center span could not have been built during the limited working hours allowed by the rail yard. Using prefabrication on this project avoided closure of 4 tracks during bridge construction. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | total superstructure prefabrication |
| Advantages | Minimized traffic disruption, |
| Related Document 1 | 850 Ton bridge lifted into place by world's largest mobile crane |
| Photo Credits | Connecticut Department of Transportation |
George P. Coleman Bridge |
| Location | Yorktown |
| State | VA |
| Completion Date | 1995 |
| Contact Person | George Clendenin P.E. Virginia Department of Transportation Phone: (804) 786-4575 Email: George.Clendenin@VirginiaDOT.org |
| Description | In 1995, the largest double-swing bridge in the United States was dismantled and replaced in record time. A major goal was limiting bridge closure to avoid disrupting traffic of more than 27,000 vehicles a day. Lighter-weight modern materials allowed Virginia DOT designers to widen the new bridge but use the existing foundation. While approach spans were widened, truss spans were prefabricated nearby and then barged to the construction site. Six old spans were removed and six new ones placed in only nine days. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | Prefabricated steel truss spans |
| Advantages | Minimized traffic disruption by constructing truss spans off-site and then barging them into place. |
| Photo Credits | Virginia Department of Transportation |
I-10 over Lake Pontchartrain |
| Location | New Orleans |
| State | LA |
| Completion Date | 2002 |
| Contact Person | Lynn Marsalone, P.E., (504) 278-7457 |
| Description | This project replaced a bridge span 65 ft long and 46 ft. wide. As part of a project that included construction of several emergency crossovers between existing twin spans, realignment of 9 existing spans, and approach slab repairs, the Louisiana Department of Transportation and Development (LA DOTD) removed and replaced an entire 350-ton span. With its 7.5-inch concrete slab cast on precast prestressed concrete girders, the new span was built on a barge on the north shore of Lake Pontchartrain and then moved to the bridge site. The single span removal and replacement cost only about 8% of the total project cost under this contract, which allowed the contractor a period of 24 consecutive hours of roadway closure for span removal and replacement under an incentive/disincentive clause. Work was completed in the summer of 2002. The superstructure span was totally prefabricated, and crews removed the old span and replaced it with the new one on a single Saturday in much less time than the contract allowed. Prefabrication enabled LA DOTD to minimize closure of I-10, the main artery into New Orleans and the Gulf coast with average daily traffic of 48,032 vehicles. Prefabrication enabled Johnson Brothers' Louisiana Team to complete its work on the span in less than 24 hours and earn the maximum $20,000 incentive award. Prefabrication minimized traffic disruption for users of the bridge. The designated alternate detour for westbound traffic to New Orleans was approximately 100 miles. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | total superstructure prefabrication |
| Advantages | Minimized traffic disruption |
| Photo Credits | Federal Highway Administration |
I-95/James River Bridge |
| Location | Richmond |
| State | VA |
| Completion Date | 2002 |
| Contact Person | Dina N. Kukreja P.E. Virginia Department of Transportation Phone: (804) 786-5172 Email: Dina.Kukreja@VirginiaDOT.org |
| Description | Minimal impact on motorists was a project goal for replacement of the superstructure of the I-95 James River Bridge, which carries approximately 110,000 vehicles per day through the city of Richmond. After considering alternatives, Virginia DOT opted for night-only construction, most of which occurred between 7 PM and 6 AM Sunday through Thursday nights. During nighttime construction, one lane of traffic was kept open in each direction. For most spans, bridge preconstructed composite units (PCU's), which include an 8-¾-inch deck over steel plate girders, were precast at a nearby casting yard and then transported to the work site. Work crews cut out the old bridge span and removed it, prepared the gap for the new PCU, and set the new PCU in place. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | Preconstructed composite units consisting of precast 8-¾-inch deck over steel-plate girders,prefabricated total superstructure,total superstructure prefabrication |
| Advantages | Minimized traffic disruption by facilitating replacement of the bridge superstructure without ever closing the highway to rush hour traffic. |
| Contract Elements | A system of incentives for early completion and disincentives (charges) for failure to restore all traffic lanes by specific hours of the day. |
| Photo Credits | Virginia Department of Transportation |
Lions' Gate Suspension Bridge |
| Location | First Narrows, Vancouver |
| State | BC |
| Completion Date | 2002 |
| Contact Person | Geoff Freer Regional Director Northern Region Ministry of Transportation 213 - 1011 4th Avenue Prince George Vancouver V2L 3H9 British Columbia Phone: (250) 565-6478 Email: Geoff.Freer@gems3.gov.bc.ca |
| Description | The Lions' Gate Suspension Bridge arches 60 meters above Vancouver's First Narrows, connecting communities on both sides of Burrard Inlet. More than 60 years of constant traffic and corrosive deicing treatments left the steel and concrete roadway in need of improvements. A distinguished landmark, it has average daily traffic of between 60,000 and 70,000 vehicles. Beginning in 1999, a rehabilitation project included replacement of the three-lane bridge deck and trusses encompassing widened lanes for traffic, widened sidewalks for cyclists and pedestrians, and seismic strengthening, as well as a complete upgrade of the traffic control system and lighting. The deck and trusses were replaced simultaneously while allowing traffic to use the bridge during replacement. Most of the reconstruction occurred during 10-hour shifts at night. Individual deck sections between 10 and 20 meters long were cut away and lowered with a jacking traveler (a gantry-like platform that attached directly to the suspenders of the bridge) to a waiting barge, and the replacement section was lifted into place. When assembled on the bridge, each section was connected to its neighboring section with more than 700 high-strength steel bolts. The first of 54 sections was replaced the weekend of September 9 and 10, 2000, and the final one was replaced the weekend of September 29 and 30, 2001. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Advantages | Minimized traffic disruption: No lane closures were scheduled during peak weekday hours. |
| Photo Credits | British Columbia Ministry of Transportation |
Main Street over Metro North Railroad |
| Location | Tuckahoe |
| State | NY |
| Completion Date | 2000 |
| Contact Person | George A. Christian P.E. Acting Director Structures Design and Construction Division New York State Department of Transportation State Campus Building 5, 6th Floor 1220 Washington Avenue Albany NY 12232 Phone: (518) 457-6827 Fax: (518) 485-7826 Email: Gchristian@gw.dot.state.ny.us |
| Description | Replacement of a through-girder bridge over a busy commuter railroad in the village of Tuckahoe presented challenges for NYSDOT: maintaining two way traffic, conducting all work between 2 and 4 AM on weekends to limit disruptions for rail commuters and adjacent stores, maintaining utility lines while relocating them on the new bridge, and raising the railroad vertical clearance five inches without affecting the street profile. NYSDOT chose a commercial system of precast prestressed concrete/steel composite superstructure modules that allowed for smaller beams than conventional construction, which helped attain the increased vertical clearance and had a short installation time. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | Precast prestressed concrete and steel composite superstructure units,precast prestressed deck composite units,prefabricated total superstructure,total superstructure prefabrication |
| Advantages | Improved constructibility by allowing staged construction over a busy commuter railroad, Minimized traffic disruption. |
| Photo Credits | New York State Department of Transportation |
Maritime Off-Ramp at I-80 and I-880 |
| Location | Oakland |
| State | CA |
| Completion Date | 1997 |
| Contact Person | Alfred R. Mangus, P.E. California Department of Transportation 1801 30th Street Sacramento, CA 95816 (916) 227-8926 Al_Mangus@dot.ca.gov |
| Description | The Maritime Off-Ramp at the intersection of I-80 and I-880 in Oakland, North America's first curved welded steel orthogonal isotropic bridge, provides access to the Port of Oakland through a U-turn from westbound I-80. The ramp is 2,356 ft long and has a 250-ft radius horseshoe shape. The California Department of Transportation (Caltrans) chose steel bridges to minimize traffic delays during bridge erection. Designers selected a closed cell structure for the horseshoe shape of the bridge as the most economical shape to resist torsional forces. The substructure includes reinforced concrete "T" bents with a single column with spiral reinforcing ties. Two special bearings connect the superstructure to each "T" bent. The contractor fabricated 13 full-bridge-width orthogonal isotropic sections 7 ft 0 in deep by 35 ft 6 in wide up to 37 ft 6 in wide, with lengths ranging from 123 to 219 ft per section. All sections shipped with a steel orthogonal isotropic deck and with installed steel barrier rails. All fabricated steel totaled 5,014 tons. Installation included special heavy-lift hydraulic platforms to move the bridge sections. Each of the 13 bridge sections was moved three times: from the fabrication facility to the barge, from the barge to the staging area beside the freeway, and from the staging area into its final location. The sections were staged on the east side of the freeway and crossed over during night erection during a 10-hr window beginning at midnight on a Saturday. The contractor faced stiff fines for each minute exceeding the time limit. Installation of three of the sections required closing half of the freeway lanes, below which approximately 500,000 vehicles cross per day. The segment over the westbound lanes was erected around midnight on one Saturday night, and the segment over the eastbound lanes was erected the following Saturday night. Unique seismic detailing includes use of rubber dock fenders as seismic shock absorbers to reduce forces between completed bridge sections. Poly-tetra-fluoro-ethylene (PTFE) spherical bearings allow for rotation and expansion of members and can resist high lateral forces, including seismic forces. A central shear key provides additional lateral capacity. |
| Photo |  |
| Prefabricated Elements | Total superstructure |
| Other Keywords | Orthotropic steel superstructure,total superstructure prefabrication |
| Advantages | Minimized traffic disruption |
| Photo Credits | Caltrans |
Norfolk Southern Railroad Bridge over I 76 |
| Location | Interstate 76 just east of the US Route 202 Interchange in Upper Merion Township, Montgomery County |
| State | PA |
| Contact Person | Andrew Warren P.E. District Administrator District 6 Pennsylvania Department of Transportation Phone: (610) 205-6660 |
| Description | The Pennsylvania Department of Transportation had a 240-foot long, 42-foot high, 740-ton steel truss railroad bridge built adjacent to Interstate 76 and then rolled into place over a weekend in October 2002. The new bridge is part of a multi-year project to widen US 202, which carries between 70,000 and 105,000 vehicles daily, and to improve key interchanges. The truss was built on steel mats that supported the dead load and large flange beams. To move it, crews erected a steel support tower on I 76's westbound side and a runway system to prepare for rolling out the truss bridge. They raised the truss onto four 330-ton Hillman rollers and used hydraulic winches to pull it to its final position over the expressway. The steel truss structure is only half of the new railroad bridge: the other half is being built in place adjacent to I 76's eastbound lanes and has no impact on traffic. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Advantages | Minimized traffic disruption. |
Richville Road Bridge |
| Location | Manchester |
| State | VT |
| Completion Date | 2001 |
| Contact Person | Lee Krohn, Town of Manchester, (802) 362-1313 |
| Description | This single-span bridge 69 ft. long and 32 ft. 8 in. wide has a concrete deck on steel girders. The superstructure of the Richville Road Bridge in the Town of Manchester, Vermont, was in poor condition, but the existing abutments were in good enough shape to be reused with only minimal repairs. The Town limited bridge closure time to 14 days and then compared chose bridge prefabrication after comparing costs. Bridge designers chose total superstructure prefabrication with the Inverset SystemTM constructed off-site and transported to the site on trucks and lifted into place by a crane. Each of three prefabricated units consisted of two rolled beams with a precast reinforced concrete bridge deck. In place, the three units provided a complete superstructure except for the sheet membrane, paving, curb, and railing. Richville Road was closed for only the specified 14 days. Use of total superstructure prefabrication saved the Town of Manchester approximately $20,000 over conventional construction plus a temporary bridge. Use of prefabrication enabled Dubois & King, Inc., to meet the Town of Manchester's 14-day closure requirement. In addition, the contractor received the American Consulting Engineers Council of Vermont's 2001 Grand Award for Engineering Excellence in Transportation for design of the bridge. Because of the prefabrication, bridge users avoided a lengthy detour with its resulting traffic disruption, travel costs, and time delays. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | total superstructure prefabrication |
| Advantages | Minimized traffic disruption |
| Photo Credits | Vermont Department of Transportation |
SH 66 over Mitchell Gulch |
| Location | SH 66 over Mitchell Gulch between Franktown and Castle Rock |
| State | CO |
| Completion Date | 2002 |
| Contact Person | Wes Goff P.E. Phone: (303) 757-9116 Email: wes.goff@dot.state.co.us |
| Description | Originally designed as 3 box culverts, the Colorado Department of Transportation accepted a value-engineering proposal for this replacement bridge to minimize traffic impact. The alternate structure has a single span with side-by-side precast slab girders welded onto precast abutments and wings welded to driven-steel H piles. Piles were driven in advance outside the existing bridge. Railing was precast into the outside girders. Except for the steel H-pile supports, the entire bridge substructure was composed of precast concrete elements. Each abutment consisted of a lower and upper backwall unit. Each of the four wingwalls for the bridge was a separate precast piece. The precast substructure units were attached in the field by welding together embedded plates precast into the elements. The bridge superstructure consisted of eight precast deck girder units each 5'-4" wide, 1'-6" deep, and 38'-4" long. The deck girders were placed on the completed abutments and then transversely post-tensioned and grouted together. The outside deck girders were constructed with integrated bridge railing to avoid the need for a separate railing installation operation in the field. Construction detours as a result of this project were reduced by the value-engineering proposal from an estimated two-to-three months to less than 48 hours. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems; bent caps |
| Other Keywords | Precast railing, precast retaining walls,totally prefabricated bridges |
| Advantages | Minimized traffic impact, improved work-zone safety by reducing work-zone time from several months to a weekend. |
| Related Document 1 | Construction Photos (PDF, 0.4 mb) HTML Version |
| Photo Credits | Colorado Department of Transportation |
Wells Street Bridge |
| Location | Chicago |
| State | IL |
| Completion Date | 2002 |
| Contact Person | Thomas Powers, P.E.; Chicago Department of Transportation, (312) 744-3591 |
| Description | This bridge with 3 spans (111-ft. center span) is a steel through truss in the city center. Part of a large project to rebuild Chicago's Wacker Drive involved rebuilding an 1899 steel bridge for the Chicago Transit Authority's elevated trains. The original specification required rebuilding the bridge in section on weekends in one month; however, the bridge owner approved the contractor's value-engineering proposal to pre-build the bridge and then moved it into position over a single weekend. The center span was constructed near the site and moved on a special hydraulic carrier about 75 ft. west and 5 ft. north, where it was placed on new foundations and connected to two shorter spans on either side. In spite of stiff contractual penalties for any delay ($1,000/minute), work was completed over a weekend in May 2002 with 2 hours to spare. The 425-ton, 111 ft. long and 25 ft. high center-span superstructure was prefabricated. Chicago Transit Authority (CTA) avoided significant disruption to travelers commuting into the city from the north. CTA would have had to provide additional, costly shuttle services. Prefabrication allowed Walsh Construction to operate in a more controlled environment and to avoid the major shoring effort that would have accompanied rebuilding the existing structure while keeping it open for weekday traffic, thus limiting company liability for financial penalties. The use of prefabrication reduced disruption to vehicle drivers from 6 months to a single weekend; it reduced disruption to transit users from four to six weekends to a single weekend. |
| Photo |  |
| Prefabricated Elements | Total superstructure systems |
| Other Keywords | total superstructure prefabrication |
| Advantages | Minimized traffic disruption |
| Photo Credits | Chicago Department of Transportation |