NASA Road 1 over I-45: Keys to Accomplishing Rapid Bridge Replacement
- Incentive of $10,000.00 per day for each day less than 31 days to open the bridge to traffic (maximum $100,000.00)
- Seven calendar day definition of working day regardless of weather conditions, materials or supplies
- Maximize use of precast components with generous tolerance for construction error (precision takes time)
- Delay start time to allow for fabrication of precast components
- Ability of contractor to mobilize manpower and equipment
- Relief from time related contract provisions to the maximum extent possible
- Using alternative curing methods (membrane cure)
- Eliminating concrete surface treatment (takes time to dry the deck)
- Determining lowest concrete strength required for sequential loading (2000 psi for beam placement on bent caps)
- Use temporary pavement markings (permanent markings require a dry deck for installation)
- Close coordination and planning between the area office and contractor and between the area office and district and division support
- High performance concrete (both strength and durability definition)
|