At-Grade Intersection Improvement MD Route 97 Georgia Avenue at Randolph Road
Skill Set Recommendations
3.1 Construction
The construction skill set offered the following recommendations:
Social and Environmental Issues
- Evaluate using 4f properties for temporary construction activities
- Pedestrian mobility
Public Relations
- Community liaison
- Community meetings
- Project Web sites
Phasing
- Think "outside the box" for retaining wall design/bridge design and MOT with the intent for reducing project and phase duration
Advanced Construction Contract
- Utilities
- Storm drain/roadway reconstruction to be completed at Judson and Sheraton Streets
- Advertise utility contract, hold roadway construction contract
- Subsurface utility engineering
Reduce Congestion within Work Zone
- Explore detour options
- Bus route alternatives (Public Transit/School Buses)
Right of Way
- Advanced right-of-way acquisitions
- Monitoring Wells for the purpose of identifying possible contaminated soils
Innovative Contracting
- Incentive/disincentive at critical path milestones
- Design/build
- A+B
Construction Management
- Use of construction management and inspection contracts
- Use of conventional SHA administration and inspection of project
Agency Coordination and Public Involvement
- Start discussions with organizations early
- Restrictions on design and construction must be coordinated into plans
3.2 Geotechnical Engineering Utilities
The geotechnical engineering/accelerated materials testing skill set discussed the strength of the clay and the potential instability of various slopes along MD-97 before offering their recommendations:
3.3 Public Relations/Public Involvement
The public relations/involvement crew centered their recommendations on the "Identify, Involve, and Inform" model:
- Key Concepts
- Budget for public information activities
- Comprehensive community outreach
- Reach a diverse audience
- Informational vs. promotional
- Elected officials support
Public Relations Skill Set Recommendations
- On-site community liaison
- Informational public meetings
- Establish database for outreach
- Project Web site
- Community outreach
- Media outreach
- On-site community liaison
- Hire a public relations consultant at the outset of the project
- Funding must be set aside out of the construction budget
- Located at project field office.
- Informational public meetings
- Pre-meeting with local officials
- Several months prior to construction host one or more open houses.
- Regular update meetings throughout life of the project
Establish Database for Outreach
- Set up a database of all stakeholders, interested parties, and individuals that need to be informed about the project
- Ability to provide updates through e-mails, phone messages, and text messages
- Disseminate timely information to a mass audience
- Project Web site
- Communicate project news and changes on SHA's Traffic Management website (CHART) and Montgomery County's Traffic Management Center
- Purchase domain names
- Web site must be kept current
Community Outreach
- Fliers, door hangers, newsletters (print and electronic), brochures, giveaways
- Speakers bureau (project staff, local officials)
- Information on city and county web pages,
- Drop-in center, kiosks,
- Advertising for display at transit facilities (i.e. METRO, bus) and on grocery bags
- TAR/VMS, static project information signs
Media Outreach
- Limited media attention from DC-area T.V. and radio
- local cable access programs
- Press releases, traffic reports, blogs, radio/TV/print interviews, PSAs, letters to the editor, editorials
- Coordination with traffic reporters
- Outreach to Hispanic organizations, Spanish language radio stations (99.1 El Zol)
3.4 Roadway/Geometric Design
The roadway/geometric design group reviewed the Value Engineering study completed in May 2004 and concluded that the proposals presented are valid design items, noting that they do not appear to accelerate construction or significantly reduce costs. The team then offered the following recommendations:
Roadway/Geometric Design
- Change of utility relocation
- Original plan to relocate along Sheraton and Judson
- Proposed: relocate along MD 97 and Randolph Rd
Concerns:
- Possible 4F issue to be created
- Purchase of residence on northwest corner of the existing intersection. The property is currently for sale.
Other Details
- There are still some utilities to be relocated at Sheraton and Judson
- The house on main intersection could be offered as 4F mitigation
Roadway/Geometric Design
- Hold existing vertical (MD 97)
- Keep MD 97 at the current elevation
Concerns
- While MOT may be simplified, Randolph Rd. may need to be lowered
Coordination
Structures
- Roadway/Geometric Design
- Geometrics
- Eliminate the jug-handle and the tunnel left turn lane.
- Provide the left turn lane from eastbound Ramp B.
Concerns
- Need for advanced signing
- Modification of the vertical curve to shorten the walls on the east end
Other
- Eliminates impact to police lot
- Walls are parallel
Coordination
- Structures, traffic, and construction
Structures
The structures team offered the following recommendations:
 |  | Figure 1: Proposed elevated structure for Randolph Road | Figure 2: Typical retaining walls that may be used in trenching Randolph Road |
Viaduct Bridge for Randolph over MD 97
Advantages
- Minimize utility impacts (no underground relocations)
- Reduce right-of-way impacts (eliminate some total takes)
- Lanes can be tucked under structure
- Carrying heavier traffic movements, improving Level of Service (LOS)
- Less impact on residents
Aesthetics
- Significant time savings for construction
- Reduce construction stages
- Minimize hazardous material impacts
- Minimize impacts to surrounding structures
- Saves money (ROW/Utility impacts)
Disadvantages
- Visual intrusion
- Long-term maintenance costs
- Planning process will require revisiting
- Possible conflicts with WMATA Metro Tunnel (foundations)
Accelerated Construction of Current Designed Bridge
- Weekend Closure to Construct Bridge
- Install foundation elements during short term lane closures. Cover with steel plates.
- Close intersection for weekend.
- Excavate as required depth over the bridge area.
- Install pre-cast abutment caps.
- Place pre-cast superstructure elements.
- Place temporary waterproofing membrane and HMA wearing surface.
- Open to traffic
Accelerated Construction of Current Designed Bridge
Advantages
- Minimize MOT phases
- Shorter construction time frame
- Less temporary pavement
- Potentially less ROW/Easements
Disadvantages
- Closes intersection for a weekend
Issues
- Coordinate foundation with WMATA tunnel
- Superstructure types
- Extensive Public Awareness campaign required
- Dependent on amount of work, could be expanded to two weekends
- Staging area will be needed close by
Secant/Tangent Wall (Top Down)
Advantages
- Can be constructed using lane closures
- May not require tie-backs
- Can be used for a vertical load carrying element at bridge
Disadvantages
- Requires special details at WMATA crossing
- High costs - $110 to $150 per SF
- Potential challenges removing decomposed rock material
Accelerated Construction of Retaining Walls
Soldier Piling/Lagging (Top Down Driven H-Piles)
Advantages
- Lower costs
- Less caisson drilling
Disadvantages
- More extensive MOT
- Requires special details at WMATA crossing (tie-backs)
Soil Nail
Advantages
Disadvantages
- Longest construction time
- Possible conflicts with drainage and tie-backs
- Long term durability concerns (soil PH requires investigation)
- Other structure Issues
Shift Bridge/Md 97 Alignment East
Advantages
- Less phases for construction
- Less impact to traffic
Disadvantages
- 4f impacts associated with temporary roadway in Greenway
- Issues with temporary roadway intersecting vertical grade of Randolph Road
Materials
- Self-consolidating concrete (drilled shafts)
- Automated computer control of concrete placement operations
- High-performance overlays
- High-performance rebar
- Utilizing pre-cast elements
3.6 Traffic Engineering/Safety/ITS
Challenges of current design
- Signing
- Shifts congestion to adjacent intersections
- Utility relocations along Judson Road and Sheraton Street
- Length of construction period
- Redirection of local roadway traffic
- Median nose impeding turning movements
- Access management issues
- Growth of shopping center
- Redirect of Inner-County Connector traffic
Skill set goals
- Reduction of construction time and cost
- Minimize impact to traffic during construction
- Provide safe pedestrian access through construction phasing
- Keeping stakeholders (system users, TMC, adjacent residents, businesses, etc.) Informed of traffic and construction conditions
- Real-time monitoring and conveying that information to the public
- Maximize the benefit of the ultimate facility
- Minimize crashes during maintenance of traffic
Reduction of construction time and cost
- Consider two- or three -lane tunnel with reversible lanes for peak direction
- Reconsider alternative grade widening – consider pedestrian bridge/tunnel with elevators
- Consider short term closures for certain activities to reduce construction time and phasing need to perform modeling to determine impact
Minimize impact to traffic during construction
- Signal timing at adjacent intersections within the area network
- Additional traffic monitoring equipment beyond the project limits. Need to determine what Montgomery County currently has in place.
- Reduce or eliminate conflicting turning movements in work zone
Provide safe pedestrian/bicycle access during construction
- Provide positive protection
- Pedestrian/bicycle detours
- Signing
- Local information outreach
- Reduce construction phasing
- Coordination with WMATA and consider moving bus stops
- Provide acceptable riding surface for cyclists
- Maintain adequate lighting
Keeping stakeholders informed of traffic and construction conditions
- Maintain open line of communication with media
- Coordinate closures with property owners and businesses
- Community liaison
- Coordination with ICC construction and other nearby construction projects
- Maintain accurate traffic control devices
- Real-time monitoring and conveying that information to the public
- Provide and maintain monitoring and its devices throughout the area network and include in project cost
- Coordinate construction phasing and signal timing with Montgomery County traffic management center (TMC)
- Coordinate construction activities with WMATA bus operations
- Use existing resources to provide real-time data (WMATA, WTOP, Mont. Co., etc.)
- TAR – travel advisory radio
Maximize the benefit of the ultimate facility
- Simulation modeling of ultimate facility for traffic flow improvements
- Access management to village center
- Remove Randolph Road left turn lanes to Village Center
- Consider second cut and cover at Glenmont Circle and Randolph Rd
- Consider impacts of ICC
- Provide additional left-turn lane out of the shopping center
Minimize crashes during maintenance of traffic
- Clear and accurate use of traffic control
- Routine WZTC inspection
- Reduce or eliminate conflicting turning movements in work zone
- Provide contractor incentives for maintaining safe work zone
- Remove vehicles quickly in the event of a crash or incident – consider performance specifications for contractor
|