U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content U.S. Department of Transportation/Federal Highway AdministrationU.S. Department of Transportation/Federal Highway Administration

Bridges & Structures

Appendix C - Calculations of Creep and Shrinkage Effects

See Design Step 5.3 for the basic information about creep and shrinkage effects. Design Step 5.3 also contains the table of fixed end moments used in this appendix.

Design Step C1.1 - Analysis of creep effects on the example bridge

Calculations are shown for Span 1 for a deck slab cast 450 days after the beams are made. Span 2 calculations are similar. See the tables at the end of this appendix for the final results for a case of the slab and continuity connection cast 30 days after the beams are cast. All calculations are made following the procedures outlined in the publication entitled "Design of Continuous Highway Bridges with Precast, Prestressed Concrete Girders" published by the Portland Cement Association (PCA) in August 1969.

The distance from the composite neutral axis to the bottom of the beam is 51.54 in. from Section 2. Therefore, the prestressing force eccentricity at midspan is:

ec = NAbottom-CGS = 51.54-5.0 = 46.54 in.

Design Step C1.2 Calculate the creep coefficient, ψ(t, ti), for the beam at infinite time according to S5.4.2.3.2.

Calculate the concrete strength factor, kf

kf = 1/[0.67 + (f′c/9)] = 1/[0.67 + (6.0/9)] = 0.748 (S5.4.2.3.2-2)

Calculate the volume to surface area factor, kc

k sub c equals quantity numerator t divided by quantity 26 times e raised to the 0.36 times V divided by S for the beam plus t end quantity divided by the denominator t divided by the quantity 45 plus t end quantity end quantity times quantity 1.80 plus 1.77 times e raised to the -0.54 times V divided by S for the beam end quantity divided by 2.587. (SC5.4.2.3.2-1)

where:

t = maturity of concrete = infinite days

e = natural log base (approx. 2.71828)

(V/S)b = volume to surface ratio for the beam = beam surface area is 2,955.38 in2/ft (see Figure 2-3 for beam dimensions) and the volume is 13,020 in3/ft = (13,020/2,955.38) = 4.406 in.

k sub c equals 1 times quantity 1.80 plus 1.77 times e raised to the -0.54 times 4.406 for the beam end quantity divided by 2.587.

kc = 0.759

The creep coefficient is the ratio between creep strain and the strain due to permanent stress (SC5.4.2.3.2)

Calculate creep coefficient according to Eq. S5.4.2.3.2-1.

ψ(∞,1) = 3.5kckf(1.58-H/120)ti-0.118[(t-ti)0.6/(10.0 + (t-ti)0.6]

where:

kc = 0.759 (see above)
kf = 0.748 (see above)
H = relative humidity = 70%
ti = age of concrete when load is initially applied = 1 day
t = infinite days

ψ(∞,1) = 3.5(0.759)(0.748)(1.58-70/120)(1)(-0.118)[1] = 1.98

Design Step C1.3 Calculate the creep coefficient, ψ(t,ti), in the beam at the time the slab is cast according to S5.4.2.3.2.

t = 450 days (maximum time)

Calculate the volume to surface area factor, kc

k sub c equals quantity numerator t divided by quantity 26 times e raised to the 0.36 times V divided by S for the beam plus t end quantity divided by the denominator t divided by the quantity 45 plus t end quantity end quantity times quantity 1.80 plus 1.77 times e raised to the -0.54 times V divided by S for the beam end quantity divided by 2.587. (SC5.4.2.3.2-1)

where:

t = 450 days
e = natural log base (approx. 2.71828)
(V/S)b= 4.406 in.

k sub c equals quantity numerator 450 divided by quantity 26 times e raised to the 0.36 times 4.406 plus end quantity divided by the denominator 450 divided by the quantity 45 plus 450 end quantity end quantity times quantity 1.80 plus 1.77 times e raised to the -0.54 times 4.406 end quantity divided by 2.587.

kc = 0.651

Calculate the creep coefficient, ψ(t,ti), according to Eq. S5.4.2.3.2-1.

ψ(450,1) = 3.5kckf(1.58-H/120)ti-0.118[(t-ti)0.6/[10.0 + (t-ti)0.6]]

where:

kc = 0.651 (see above)
kf = 0.748 (see above)
H = 70%
ti = 1 day
t = 450 days

ψ(450,1) = 3.5(0.651)(0.748)(1.58-70/120)(1)(-0.118)[(450-1)0.6/[10 + (450-1)0.6]] = 1.35

Calculate the restrained creep coefficient in the beam, Φ, as the creep coefficient for creep that takes place after the continuity connection has been established.

Φ = ψ- ψ450(from PCA publication referenced in Step 5.3.2.2) = 1.98-1.35 = 0.63

Design Step C1.4 - Calculate the prestressed end slope, θ.

For straight strands (debonding neglected). Calculate the end slope, θ, for a simple beam under constant moment.

Moment = Pec

θ = PecLspan/2EcIc

where:

P = initial prestressing force after all losses (kips) = 1,096 kips (see Design Step 5.4 for detailed calculations of the prestressing force)
ec = 46.54 in. (calculated above)
Lspan = 110.5 ft. (1,326 in.) (taken equal to the continuous beam span length)
Ec= the modulus of elasticity of the beam at final condition (ksi)
Ec = 4,696 ksi
Ic = moment of inertia of composite beam (in4) = 1,384,254 in4

θ = [1,096(46.54)(1,326)]/[2(4,696)(1,384,254)] = 0.0052 rads

Design Step C1.5 - Calculate the prestressed creep fixed end action for Span 1

The equation is taken from Table 5.3-9 for prestressed creep FEA, left end span, right moment.

FEMcr = 3EcIcθ/Lspan
FEMcr = [3(4,696)(1,384,254)(0.0052)]/1,326
FEMcr = 76,476/12
FEMcr = 6,373 k-ft

End forces due to prestress creep in Span 1:

Left reaction = R1PScr
Left reaction = FEMcr/Lspan
Left reaction = (6,373)/110.5
Left reaction = 57.7 k

Right reaction = R2PScr
Right reaction = -R1PScr
Right reaction = -57.7 k

Left moment = M1PScr
Left moment = 0.0 k-ft

Right moment = M2PScr
Right moment = FEMcr
Right moment = 6,373 k-ft

Figure showing prestressed creep restraint moments. Value starts at zero at end supports and reaches 6373 k-ft. at intermediate support. Reactions are 57.7 k at end supports and -57.7 k from each span at intermediate support.
Figure C1-Presstress Creep Restraint Moment

Design Step C1.6 - Calculate dead load creep fixed end actions

Calculate the total dead load moment at the midspan

Noncomposite DL moment = MDN
Noncomposite DL moment = 42,144 k-in (3,512 k-ft) (see Section 5.3)

Composite DL moment = MDC
Composite DL moment = 4,644 k-in (387 k-ft) (see Section 5.3)

Total DL moment = MDL
Total DL moment = MDNC + MDC
Total DL moment = 42,144 + 4,644
Total DL moment = 46,788/12
Total DL moment = 3,899 k-ft

End forces due to dead load creep in Span 1:

Left reaction = R1DLcr
Left reaction = -MDL/Lspan
Left reaction = -3,899/110.5
Left reaction = -35.3 k

Right reaction = R2DLcr
Right reaction = -R1DLcr
Right reaction = 35.3 k

Left moment = M1DLcr
Left moment = 0.0 k-ft

Right moment = M2DLcr
Right moment = -MDL
Right moment = -3,899 k-ft


Figure showing dead load creep restraint moments. Value starts at zero at end supports and reaches -3899 k-ft. at intermediate support. Reactions are -35.3 k at end supports and 35.3 k from each span at intermediate support.
Figure C2-Dead Load Creep Restraint Moment

Calculate the creep correction factor, Ccr

Ccr = 1-e-Φ (from PCA publication referenced in Step 5.3.2.2) = 1-e-0.63= 0.467

Calculate the total creep (prestress + dead load) fixed end actions for 450 days.

Left reaction = R1cr
Left reaction = Ccr(R1PScr + R2DLcr)
Left reaction = 0.467(57.7 - 35.4)
Left reaction = 10.41 k

Right reaction = R2cr
Right reaction = -R1cr
Right reaction = -10.41 k

Left moment = M1cr
Left moment = 0.0 k-ft

Right moment = M2cr
Right moment = Ccr(M2PScr + M2DLcr)
Right moment = 0.467[6,373 + (-3,899)]
Right moment = 1,155 k-ft

Figure showing total creep fixed end moments. Value starts at zero at end supports and reaches 1155 k-ft. at intermediate support. Reactions are 10.41 k at end supports and -10.41 k from each span at intermediate support.
Figure C3-Total Creep Fixed End Actions

Design Step C1.7 - Creep final effects

The fixed end moments shown in Figure C3 are applied to the continuous beam. The beam is analyzed to determine the final creep effects. Due to the symmetry of the two spans of the bridge, the final moments at the middle support are the same as the applied fixed end moments. For a bridge with more than two spans or a bridge with two unequal spans, the magnitude of the final moments would be different from the fixed end moments.

Figure showing creep final moments. Value starts at zero at end supports and reaches 1155 k-ft. at intermediate support. Reactions are 10.41 k at end supports and -20.82 k at intermediate support.
Figure C4-Creep Final Effects for a Deck and Continuity Connection Cast 450 Days After the Beams were Cast

Design Step C2.1 - Analysis of shrinkage effects on the example bridge


Calculate shrinkage strain in beam at infinite time according to S5.4.2.3.3

Calculate the size factor, ks.

k sub s equals quantity numerator t divided by quantity 26 times e raised to the 0.36 times V divided by S for the beam plus t end quantity divided by the denominator t divided by the quantity 45 plus t end quantity end quantity times quantity 1064 minus 94 times V divided by S for the beam end quantity divided by 923. (SC5.4.2.3.3-1)

where:

t = drying time = infinite days

e = natural log base (approx. 2.71828)

(V/S)b = 4.406 in.

k sub s equals 1 times the quantity 1064 minus 94 times 4.406 end quantity divided by 923.

ks = 0.704

Calculate the humidity factor, kh

Use Table S5.4.2.3.3-1 to determine kh for 70% humidity, kh = 1.0.

Assume the beam will be steam cured and devoid of shrinkage-prone aggregates, therefore, the shrinkage strain in the beam at infinite time is calculated as:

εsh,b, = -kskh[t/(55.0 + t)](0.56 x 10-3) (S5.4.2.3.3-2)

where:

ks = 0.704
kh = 1.0 for 70% humidity (Table S5.4.2.3.3-1)
t = infinite days

εsh,b, = -(0.704)(1.0)[1](0.56 x 10-3) = -3.94 x 10-4

Design Step C2.2 - Calculate shrinkage strain in the beam at the time the slab is cast (S5.4.2.3.3)

t = time the slab is cast = 450 days (maximum value)

Calculate the size factor, ks.

Ks = k sub s equals quantity numerator t divided by quantity 26 times e raised to the 0.36 times V divided by S for the beam plus t end quantity divided by the denominator t divided by the quantity 45 plus t end quantity end quantity times quantity 1064 minus 94 times V divided by S for the beam end quantity divided by 923. (SC5.4.2.3.3-1)

where:

t = 450 days
e = natural log base (approx. 2.71828)
(V/S)b = 4.406 in.

k sub s equals quantity numerator 450 divided by quantity 26 times e raised to the 0.36 times 4.406 plus 450 end quantity divided by the denominator 450 divided by the quantity 45 plus 450 end quantity end quantity times quantity 1064 minus 94 times 4.406 end quantity divided by 923.

ks = 0.604

Assume the beam will be steam cured and devoid of shrinkage-prone aggregates, therefore, the shrinkage strain in the beam at infinite time is calculated as:

εsh,b,450 = -kskh[t/(55.0 + t)](0.56 x 10-3) (S5.4.2.3.3-2)

where:

ks = 0.604
kh = 1.0 for 70% humidity (Table S5.4.2.3.3-1)
t = 450 days

εsh,b,450 = -(0.604)(1.0)[450/(55.0 + 450)](0.56 x 10-3) = -3.01 x 10-4

Design Step C2.3 - Calculate the shrinkage strain in the slab at infinite time (S5.4.2.3.3)

Calculate the size factor, ks

k sub s equals quantity numerator t divided by quantity 26 times e raised to the 0.36 times V divided by S for the beam plus t end quantity divided by the denominator t divided by the quantity 45 plus t end quantity end quantity times quantity 1064 minus 94 times V divided by S for the beam end quantity divided by 923. (SC5.4.2.3.3-1)

where:

t = infinite days

e = natural log base (2.71828)

Compute the volume to surface area ratio for the slab.

(V/S)s = (bslab)(tslab)/(2bslab-wtf)

where:

bslab = slab width taken equal to girder spacing (in.)
tslab = slab structural thickness (in.)
wtf = beam top flange width (in.)
(V/S)s = 116(7.5)/[2(116)-42] = 4.58 in.

k sub s equals 1 times the quantity 1064 minus 94 times 4.58 end quantity divided by 923.

ks = 0.686

The slab willnot be steam cured, therefore, use

εsh,s, = -kskh[t/(35.0 + t)](0.51 x 10-3) (S5.4.2.3.3-1)

where:

ks = 0.686
kh = 1.0 for 70% humidity (Table S5.4.2.3.3-1)
t = infinite days

εsh,s, = -(0.686)(1.0)[1.0](0.51 x 10-3) = -3.50 x 10-4

Design Step C2.4

Calculate the differential shrinkage strain as the difference between the deck total shrinkage strain and the shrinkage strain of the beam due to shrinkage that takes place after the continuity connection is cast.

Δεsh = εsh,s, - (εsh,b, - εsh,b,450)
Δεsh = -3.50 x 10-4-[-3.94 x 10-4-(-3.01 x 10-4)]
Δεsh = -2.57 x 10-4

Design Step C2.5 - Calculate the shrinkage driving end moment, Ms

Ms = ΔεshEcsAslabe′ (from PCA publication referenced in Design Step 5.3.2.2)

where:

Δεsh= differential shrinkage strain
Ecs = elastic modulus for the deck slab concrete (ksi)
Aslab = cross-sectional area of the deck slab (in2)
e′ = the distance from the centroid of the slab to the centroid of the composite section (in.)
e′ = dbeam + tslab/2-NAbeam bottom
e′ = 72 + 7.5/2-51.54 = 24.21 in.

Ms = (-2.57 x 10-4)(3,834)(116)(7.5)(24.21)
Ms = 20,754/12
Ms = 1,730 k-ft (see notation in Table 5.3-9 for sign convention)

Figure showing shrinkage driving moment. Value constant at 1730 k-ft along full length.
Figure C5-Shrinkage Driving Moment

For beams under constant moment along their full length, the restraint moment may be calculated as shown above for the case of creep due to prestressing force or according to Table 5.3-9.

Shrinkage fixed end actions = -1.5Ms
Shrinkage fixed end actions = -1.5(1,730)
Shrinkage fixed end actions = -2,595 k-ft

Figure showing shrinkage fixed end actions. Value of moment starts at zero at end supports and reaches -2595 k-ft. at intermediate support. Reactions are -23.6 k at end supports and 23.6 k from each span at intermediate support.
Figure C6-Shrinkage Fixed End Actions

Design Step C2.6 - Analyze the beam for the fixed end actions

Due to symmetry of the spans, the moments under the fixed end moments shown in Figure C6 are the same as the final moments (shown in Fig. C7). For bridges with three or more spans and for bridges with two unequal spans, the continuity moments will be different from the fixed end moments.

Figure showing shrinkage continuity moments. Value of moment starts at zero at end supports and reaches -2595 k-ft. at intermediate support. Reactions are -17.51 k at end supports and 35.02 k at intermediate support.
Figure C7-Shrinkage Continuity Moments

Design Step C2.7 Calculate the correction factor for shrinkage.

Csh = (1-e-Φ)/Φ (from PCA publication referenced in Step 5.3.2.2)
Csh = [1-e-0.63]/0.63
Csh = 0.742

Design Step C2.8

Calculate the shrinkage final moments by applying the correction factor for shrinkage to the sum of the shrinkage driving moments (Figure C5) and the shrinkage continuity moment (Figure C7) fixed end actions.

End moments, Span 1:

Left end moment = M1sh
Left end moment = Csh(Msh,dr + shrinkage continuity moment)
Left end moment = 0.742(1,730 + 0)
Left end moment = 1,284 k-ft

Right end moment = M2sh
Right end moment = Csh(Msh,dr + shrinkage continuity moment)
Right end moment = 0.742(1,730-2,595)
Right end moment = -642 k-ft

Figure showing final shrinkage effects. Moment starts at -1284 k-ft at end supports and reaches +642 k-ft. at intermediate support. Reactions are -23.6 k at end supports and 47.2 k at intermediate support.
Figure C8-Final Total Shrinkage Effect

Tables C1 and C2 provide a summary of the final moments for the case of the deck poured 30 days after the beams were cast.

Table C1 - 30 Day Creep Final Moments

Span M1
(k-ft)
M2
(k-ft)
R1
(k)
R2
(k)
1 0 1,962 17.7 -17.7
2 1,962 0 -17.7 17.7

Table C2 - 30 Day Shrinkage Final Moments

Span M1
(k-ft)
M2
(k-ft)
R1
(k)
R2
(k)
1 75.9 -37.9 -1.035 1.035
2 -37.9 75.9 1.035 -1.035

When a limit state calls for inclusion of the creep and shrinkage effects and/or the design procedures approved by the bridge owner calls for their inclusion, the final creep and shrinkage effects should be added to other load effect at all sections. The positive moment connection at the bottom of the beams at the intermediate support is designed to account for the creep and shrinkage effects since these effects are the major source of these moments.

Notice that when combining creep and shrinkage effects, both effects have to be calculated using the same age of beam at the time the continuity connection is established.

<< Previous | Contents
Updated: 06/27/2017
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000