U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
![]() | REPORT | ![]() |
This report is an archived publication and may contain dated technical, contact, and link information |
![]() |
Publication Number: FHWA-HRT-12-051 Date: August 2012 |
Publication Number: FHWA-HRT-12-051 Date: August 2012 |
PDF files can be viewed with the Acrobat® Reader®
This guide was issued to provide guidelines for construction of the geosynthetic reinforced soilintegrated bridge system (GRS-IBS). Refer to Geosynthetic Reinforced Soil Integrated Bridge System Interim Implementation Guide for GRS-IBS design and construction guidelines.(1)
This guide serves as the technical basis for agency-developed standard specifications. Local experience and practice shall be incorporated as applicable.
SI* (Modern Metric) Conversion Factors
SECTION 1. GENERAL REQUIREMENTS
1.1. GUIDELINES FOR USING THIS DOCUMENT
1.2. QA RESPONSIBILITIES
1.3. STANDARD REFERENCE DOCUMENTS
1.4. DESCRIPTION OF WORK
SECTION 2. MATERIAL REQUIREMENTS
2.1. CMU FACING ELEMENT
2.2. BACKFILL MATERIAL
2.3. GEOSYNTHETICS
2.4. MISCELLANEOUS MATERIALS
SECTION 3. CONSTRUCTION REQUIREMENTS
3.1. LABOR AND EQUIPMENT
3.2. SITE LAYOUT
3.3. EXCAVATION
3.4. RSF
3.5. PLACEMENT OF BACKFILL AND COMPACTION
3.6. PLACEMENT OF GEOSYNTHETIC REINFORCEMENT
3.7. WALL FACING
3.8. LEVELING COURSE
3.9. BEAM SEAT
3.10. PLACEMENT OF SUPERSTRUCTURE
3.11. APPROACH INTEGRATION
3.12. SITE DRAINAGE
4.1. DESCRIPTION
4.2. CONTRACTOR QC PLAN
4.3. QC PERSONNEL REQUIREMENTS
4.4. QC LABORATORY FACILITY REQUIREMENTS
4.5. QC OF STANDARD MANUFACTURED ITEMS
4.6. QC INSPECTION
4.7. QC SAMPLING AND TESTING
4.8. QC DOCUMENTATION AND DATA EVALUATION
4.9. QC RECORDS SYSTEM
SECTION 5. AGENCY ACCEPTANCE, MEASUREMENT, AND PAYMENT