U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
TECHBRIEF |
This techbrief is an archived publication and may contain dated technical, contact, and link information |
Publication Number: FHWA-HRT-13-105 Date: December 2013 |
Publication Number: FHWA-HRT-13-105 Date: December 2013 |
PDF files can be viewed with the Acrobat® Reader®
FHWA Publication No.: FHWA-HRT-13-105 |
This document is a technical summary of the unpublished Federal Highway Administration (FHWA) report Evaluation of Member and Load-Path Redundancy on the US-421 Bridge over the Ohio River, available through the National Technical Information Service at www.ntis.gov.
The sudden collapse of the Silver Bridge in 1967 demonstrated that failure of a single member could result in failure of the entire bridge. This failure and other fractures led to the development of fracture critical member (FCM) provisions for design, fabrication, and inspection. The design and fabrication aspects were originally published by the American Association of State Highway Transportation Officials (AASHTO) as a guide specification in 1978.(1) The guide specification was withdrawn in 1989 and largely adopted into the AASHTO Load and Resistance Factor Design (LRFD) Bridge Design Specifications, and American Welding Society (AWS) D1.5 Bridge Welding Code.(2, 3) Regulations regarding the field inspection requirements of fracture critical members are mandated by federal law.(4)
The AASHTO LRFD Bridge Design Specifications describe an FCM as “a component in tension whose failure is expected to result in the collapse of the bridge or the inability of the bridge to perform its function.”(2) Bridges containing FCMs require a “hands-on” inspection every 24 months.(4) These inspections are more rigorous than routine inspection and often require closing down portions of the bridge to traffic to gain access. As of December 2011, there were 18,770 bridges with FCMs, out of a total 91,850 steel bridges in the National Bridge Inventory (approximately 20 percent).(5)
Under the AASHTO specification, FCMs are non-redundant steel members either partially or wholly in tension. The specification defines redundancy as “the quality of a bridge that enables it to perform its design function in the damaged state,” and redundant members are those in which “failure does not cause failure of the bridge.”(2) However, determining redundancy is often difficult, as demonstrated by bridges in service where full-depth fracture of an FCM did not result in collapse of the structure as described in detail within NCHRP Synthesis 354.(6) In fact, many bridges have carried traffic for some time prior to a fracture being discovered. The performance of these structures after fracture implies that redundancy, though unaccounted for, does exist by backup mechanisms not considered in the engineering design.
Redundancy is often separated into three different types: internal redundancy, structural redundancy, and load-path redundancy, described as follows:
A technical memo published by FHWA with the subject “Clarification of Requirements for Fracture Critical Members,” dated June 20, 2012, provides guidance and recognition regarding structural redundancy for members traditionally classified as FCMs.(7) This memo for the first time recognizes system performance (i.e., structural redundancy) as a method to assess redundancy and classify FCMs. The memo also encourages the use of internal redundancy as good detailing practice but does not allow it for classifying whether a member is fracture critical.
The objective of the project was to assess the after-fracture performance of a two-line, simple-span truss bridge. The bridge was slated for explosive demolition and offered the ability to examine both internal and structural redundancy. Since this study focuses on a single bridge, the results and methodologies developed through this research are rather specific. Nevertheless, as will be discussed, they do show that the universal assumption of collapse following failure of an FCM is not always valid.
The US-421 bridge spans over the Ohio River between Madison, IN, and Milton, KY, and is referred to as the Milton-Madison Bridge. It was constructed in 1921 and consisted of 19 spans of riveted, built-up members. An overall view of the bridge is shown in figure 1.
Figure 1 does not capture the approach-span trusses leading up to the river span. The first approach-span truss on the Indiana shore is the focus of this research effort. A picture of a test truss is shown in figure 2; the lower chord is close to the ground and spans over a city park property, making access for instrumentation easy. The test truss spans 149 ft and is in a Pratt configuration as shown in figure 3. The truss had some corrosion throughout, which was quite severe in some places and left holes and partially severed members, as seen in figure 4.
Figure 1. Photo. Overall view of bridge from Indiana shore.
Figure 2. Photo. View of the test span.
Figure 3. Illustration. Elevation view of truss.
Figure 4. Photo. Severe corrosion in lower chord near abutment.
A simple, three-dimensional analysis model of the bridge was created with beam elements, and shell elements for the deck. The bridge deck was replaced with a filled grid deck in 1996, and this was modeled with shell elements with different longitudinal and transverse properties. The model indicated which members should be removed in a simulated fracture event and guided placement of strain gauges.
Forty-eight weldable strain gauges were applied to select members on the truss. Remote monitoring was performed for five months under ambient traffic loading before the truss was removed from service. These data were used to conduct fatigue analysis from rain-flow stress histograms, which is covered in detail within the full report.
Additionally, static-load and slow-crawling tests were performed on the bridge with a sand truck of a known weight.
Controlled load testing was performed on the bridge to understand its behavior, determine stresses in the bridge under a known load, and calibrate the finite element analysis. The two-part test included crawl tests and park tests, which were used to examine the response of the bridge to moving loads and to obtain static data (i.e., with the loading at defined locations) that are helpful in calibrating the FE model. The gross vehicular weight of the test truck exceeded the posting on the bridge in order to ensure that sufficiently large stresses were produced. Analysis showed that the weight of the truck would not produce any overstressing in the bridge.
The results of the monitoring revealed that a substantial number of trucks that crossed the bridge produced stresses that were equal to or greater than those that the test truck produced. It was concluded that random vehicles crossing the bridge must have been at least as heavy as the test truck and that the posted weight limit for the bridge was exceeded on a daily basis.
The park tests were used to determine if the model could accurately capture the behavior of the bridge. The field measured stresses that were later compared to those predicted by the FE model for all nine park test locations. In general, the model yielded a conservative prediction of the stresses in the members.
As far as this project was concerned, the controlled demolition plan was to completely sever the L3-L4 bottom chord on the upstream truss while monitoring the strain gauges. Sand was placed on the bridge to represent about 2/3 the original design live load. It was difficult to select this loading, as there is no guidance regarding what amount of live load a fractured bridge should be able to sustain. After much consideration, the selected load was deemed reasonable, as it is much higher than any loads seen during long-term monitoring and was thought to be a reasonable upperbound load. This resulted in 145 kips of sand distributed over the deck. However, this load was focused over the three interior panels of the truss (i.e., between nodes U2 and U5) and resulted in stresses in members that were approaching the original design loading. Figure 5 is a photo of the sand atop the bridge.
The chord member was fabricated from built-up channels that were laced together. Each built-up channel was comprised of two angles and a plate that served as the web. In some locations, two web plates were utilized. Each built-up channel was severed separately to evaluate the internal redundancy of the member (i.e., each half of the member was cut separately). To facilitate this, the lacing was flame cut between the two sets of shape charges to ensure that no load was carried through the lacing. Shape charges, as shown in figure 6, were used to instantaneously sever the entire built-up channel, in order to represent a fracture event as much as possible. Figure 7 is a photograph taken after one half of the lower chord was severed.
Figure 8 shows a record from one of the strain gauges installed on the L3-L4 chord on the downstream truss during the two explosive events on the same member of the upstream truss. The plots include the effects of dead load and sand loads. Therefore, this plot shows the total stress in the member. The dead-load stresses were obtained from the computer model, while the stress from the sand load was measured. With the sand in place, the member was subjected to 9.4 ksi prior to the simulated fracture. After the first half of the upstream chord was severed, the stress increased to 9.9 ksi. After the member was completely severed, the stress further increased to 11.9 ksi. The dynamic amplification due to the instantaneous load release following the simulated fracture events was also observed. For all members that were instrumented, the dynamic amplification from the first blast ranged from 1.08 to 1.30. For the second blast event, the amplification factors ranged from 1.17 to 1.41.
Vertical displacements were also monitored during the two blast events using high-resolution pictures and surveying equipment. Four truss nodes were monitored, and the results are shown in table 1. The measurements were taken at a distance of 164 ft and have a resolution of approximately 0.16 inches. The measured displacements were close to the resolution but are still thought to be representative of the real displacement. The agreement between the simple analysis model and the real bridge in terms of vertical displacement were reasonably close after the first blast event. However, after the second blast event, the model over-predicted vertical displacement by a factor of almost two. The breakdown in the correlation between the model and the test was likely due to the inability of the model to capture the complex alternate load paths used by the structure following removal of a member and the transfer of shear forces in the truss. This is believed to be a major result of the difficulty associated with modeling the filled grid deck and the rigidity of the connections to the primary members and floor system.
Figure 5. Photo. Sand placed on deck before simulated fracture event.
Figure 6. Photo. Shape charges applied to one web plate of chord member.
Figure 7. Photo. Web plate fracture after first explosive event.
Figure 8. Graph. Data record of L3-L4 downstream chord during both explosion events.
Table 1. Comparison of measured and predicted vertical deflections.
|
Joint |
Measured Vertical Displacement |
Predicted Vertical Displacement |
First Blast Event |
U4 |
-0.08 |
-0.09 |
U3 |
-0.08 |
-0.09 |
|
L4 |
-0.16 |
-0.08 |
|
L3 |
-0.12 |
-0.08 |
|
Second Blast Event |
U4 |
-0.35 |
-0.71 |
U3 |
-0.35 |
-0.71 |
|
L4 |
-0.39 |
-0.65 |
|
L3 |
-0.39 |
-0.65 |
The following important conclusions were derived from this project:
As a result of this research, recommendations for future research have been developed. These recommendations are as follows:
Researchers—This work was conducted by Purdue University under the direction of Dr. Robert Connor, Lindsey Digglemann, and Ryan Sherman. The work was performed under contract DTFH61-10-D-00017-T-11004.
Distribution—This TechBrief is being distributed according to a standard distribution. Direct distribution is being made to the Divisions and Resource Center.
Availability—This TechBrief may be obtained from the FHWA Product Distribution Center by email to report.center@dot.gov, fax to (814) 239-2156, phone to (814) 239-1160, or online at https://www.fhwa.dot.gov/research.
Key Words—Fracture critical, steel bridges, truss, internal redundancy, structural redundancy.
Notice—This document is disseminated under the sponsorship of the U.S. Department of Transportation in the interest of information exchange. The U.S. Government assumes no liability for the use of the information contained in this document. The U.S. Government does not endorse products or manufacturers. Trademarks or manufacturers’ names appear in this report only because they are considered essential to the objective of the document.
Quality Assurance Statement—The Federal Highway Administration (FHWA) provides high-quality information to serve the Government, industry, and public in a manner that promotes public understanding. Standards and policies are used to ensure and maximize the quality, objectivity, utility, and integrity of its information. FHWA periodically reviews quality issues and adjusts its programs and processes to ensure continuous quality improvement.