U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations
REPORT |
This report is an archived publication and may contain dated technical, contact, and link information |
|
![]() |
Publication Number: FHWA-HRT-17-082 Date: December 2017 |
Publication Number: FHWA-HRT-17-082 Date: December 2017 |
This evaluation included an economic analysis on the installation of a signalized RCUT. The results of this analysis can help inform transportation agencies on the benefits and costs of this countermeasure.
To conduct the analysis, the project team employed annualized benefits and costs. Benefits included fewer crashes and shorter travel times. The costs included construction of the RCUT and maintenance of the extra traffic signals required by the RCUT. These benefits and costs should entail the majority of all quantifiable impacts of RCUT installation. The analysis essentially estimated the effects of signalized RCUT installation at a site that has characteristics that are average compared to the 11 test sites in this research.
The project team obtained construction cost data for 9 of the 11 test sites, as shown in table 15. Officials in Alabama emphasized that cost estimates were for RCUT-related items only, while officials in Ohio stated that cost estimates included items that were indirectly related to the RCUT. In that regard, underestimates from Alabama might balance overestimates from Ohio and still provide what looks to be a reasonable average.
AL = Alabama; OH = Ohio; TX = Texas.
The following assumptions were made during the analysis:
The analysis resulted in a $354,000 annualized construction cost. When added to the annual maintenance cost for three extra signals at $15,000, this yielded a total annualized RCUT cost of $369,000. For benefits, using several of the assumptions above, the project team estimated the operations to save 103 hours of motorist time per workday, which equates to $388,000 per year. The safety benefit was a savings of 3.0 property-damage-only crashes per year and 2.3 injury and fatal crashes per year, which results in an annual monetary savings of $948,000. Thus, the B/C ratio was 2.6 to 1.0 considering the safety benefits only and 3.6 to 1.0 considering the safety and operational benefits.
The U.S. Department of Transportation (USDOT) recommends testing the sensitivity of economic analysis results to differences in crash costs by examining the results with 0.57 and 1.41 times the recommended crash costs.(10) Table 16 provides the results from that test. Even at the low levels of crash cost, considering safety only, installing a signalized RCUT at sites like those tested under the assumptions previously listed will be beneficial, and at high crash cost levels, the effort is very beneficial.