Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram
Office of Planning, Environment, & Realty (HEP)
HEP Events Guidance Publications Glossary Awards Contacts

Analysis and Abatement Guidance

Appendix F: Determining the Reasonable Cost of Abatement

23 CFR 772.13(d)(2)(ii) requires highway agencies to determine the basis for the reasonable cost of abatement on actual construction costs. One way to determine the reasonable cost of abatement to evaluate the actual unit costs of recently constructed noise barriers in the State and identifying a range of unit costs. This information, coupled with data on the range of costs per residence of constructed noise barriers or in some cases, the square footage of noise barrier per residence will help guide the highway agency to develop the cost reasonableness criteria for the State. The regulation requires reevaluation of the cost reasonableness criteria at a minimum of every five years. States may choose to incorporate an inflation adjustment based on historical or projected trends. One benefit of using the maximum square feet per benefited residence approach is that this value remains constant. Actual costs may increase, but the highway agency guards against stepping away from perceived commitments to provide noise abatement due to escalating costs.

It may be difficult to get a grasp of the actual constructed cost of noise abatement. There are costs associated with a project that a line item in project bid tabulations does not capture. Each highway agency should determine what expenses to include in noise abatement cost valuations. It is valid to simply look at the bid cost of post and panels, but it is equally valid to include other items directly related to providing noise abatement such as design, purchase of right-of-way, maintenance of traffic, deployment costs, clearing and grubbing, grading, reseeding and mulching, cost of safety barriers and any other project costs related to the constructed noise abatement measure. The examples below do not provide all possible cost categories for States to consider, but are illustrative of possible items to include in the cost estimate.

Standalone noise abatement projects, such as Type II projects, can help identify the full unit cost of noise abatement. In a Type II project, the entire project is usually about construction of noise abatement, usually in the form of a noise barrier. The project includes all the associated costs of design and construction, making it pretty easy to divide the total project cost by the square footage of constructed noise barrier to find the unit cost of the project.

The following tables follow an option for project cost projections. Determining project construction cost is the starting point to identifying future costs. Users could also apply these tables at the program level or for future projects help get a better idea of whether a project that is cost reasonable today, will remain cost reasonable years from now given the projection of cost increases predicted to occur between design and construction.

Highway agencies may identify a typical unit cost for noise abatement and identify other features that are project specific. For example, several items shown in the tables below, such as foundations, clearing and grubbing, reseeding, drilled shafts, grading and the barriers, are typical for most projects. Other expenditures, such as purchase of right-of-way, installation of safety barriers and utility relocations are specific to some projects. The noise barrier input function in the TNM provides users with the ability to establish a cost per square foot of wall area, which could include all the typical costs, plus an additional value based on the length of the barrier, which could include atypical costs. This approach avoids assuming the worst case scenario for all projects, but allows highway agencies to account for additional expenses that occur with some projects.

NOTE: The values in the table are illustrative and do not necessarily reflect actual costs.

Noise Barrier Construction Project
Table C1: Summary of Base Cost ($)
 ItemUnit
Acre
Unit Cost
($)
Number
of
Units
Total Cost
($)
1.6Right of Wayacre10,000.01.111,478.4
1.7Clearing and Grubbingsf3.5050,000.0175,000.0
1.8Road and Accesscf5.005,000.025,000.0
1.9Gradingcf5.008,000.040,000.0
1.10Noise Barriersf7.3155,860.0408,108.0
1.11Foundationsunit1,760.0250.0440,000.0
1.12Seeding and Mulchingsf0.11100,000.011,000.0
1.13Landscapinglump sum  84,173.6
1.14Drilled Shaftsunit100.00250.025,000.0
1.15Total1,219,760.0
 
1.16Wall Area (sf)55,860#
Residences
112 
1.17Barrier Length (ft)5,000 
1.18Average Height11.17100.00250.0
1.19Average (sf) Barrier Cost7.31Max.
Cost/Res
35,000.0
 
 Input Values 

This table shows the summary of base costs for a noise barrier project without consideration for physical or financial contingencies. The project includes program elements for a standalone noise barrier project.

Noise Barrier Construction Project - Detailed Program
Table C1.1: Program Item Cost Calculations ($)
 ItemUnitUnit Cost
($)
Number
of
Units
Total
Cost
($)
1.1Right of Way 
1.1aPurchase Strip right-of-waysf 50,000.0 
 Totalacre10,000.01.111,478.4
1.2Clearing and Grubbing 
1.2aCut existing vegetationsf1.50 75,000.0
1.2bRemove existing vegetationsf1.00  50,000.0
1.2cSmooth disturbed soilsf1.00  50,000.0
 Totalsf3.550,000.0175,000.0
1.3Road and Accesscf 
1.3aGrade access roadcf5.05,000.025,000.0
 Total 5.05,000.025,000.0
1.4Grading 
1.4aCutcf5.003,000.015,000.0
1.4bFillcf5.005,000.025,000.0
  Totalcf5.008,000.040,000.0
1.5Noise Barrier <10'sf7.255,400.039,150.0
1.6Noise Barrier 10-16'sf7.3038,460.0280,758.0
1.7Noise Barrier > 16'sf7.3512,000.088,200.0
  Total 7.3155,860.0408,108.0
1.8Foundations (see table below) 
1.8aStructural Steellf3.50100,000.0350,000.0
1.8bConcretecy100.00650.065,000.0
1.8cSoil Boringsunit25.001,000.025,000.0
Totalunit1,760.00250.0440,000.0
1.9Seeding and Mulching 
1.9aType 4a grass seed mixturesf0.1550,000.07,500.0
 Straw mulchsf0.0750,000.03,500.0
 Total 0.11100,000.011,000.00
1.10Landscapingsf 
1.10a4" Deciduous trees unit175.00225.039,375.0
1.10b5' Conifersunit100.00175.017,500.0
1.10c#2 Deciduous shrubsunit350.0018.86,562.5
1.10dDayliliesunit1,275.0010.012,750.0
1.10eLandscape mulch (see table below)cy5.751,388.97,986.1
 Total   84,173.6
1.11Drilled Shafts
Equipment Rental
unit100.00250.025,000.0
 Totalunit100.00250.025,000.0
Table C1.1.1 Right-of-way required
Length of Barrier5,000
Width needed for construction10
Total Area Required50,000
Table C1.1.2 Foundation Table
 Unit# Units/Foundation
(10' depth typical)
Structural Steellf400
concretecy2.6
Table C1.1.3 Mulch Table
  Depth in feetArea in sfArea in syVolume
cy
Landscape Mulchcy0.2550,0005,555.561,388.89

Tables C1.1 - C1.1.3 provide the input values for the cost of the project program elements. The gray boxes are input values for the number of units needed and the unit cost.

Table C2 Derivation of Total Cost in Constant Prices ($)
 ItemBase Cost
($)
Physical
Contingencies
Percent
($)Design
Percent
($)Supervision
Percent
($)Total Cost
($)
2.5Right of Way11,478.45%573.97%843.73%361.613257.6
2.6Clearing and Grubbing175,000.05%8,750.07%12862.53%5512.5202125.0
2.7Road and Access25,000.05%1,250.07%1837.53%787.528875.0
2.8Grading40,000.05%2,000.07%2940.03%1260.046200.0
2.9Noise Barrier408,108.05%20,405.47%29995.93%12855.4471364.7
2.12Foundations440,000.05%22,000.07%32340.03%13860.0508200.0
2.13Seeding and Mulching11,000.05%550.07%808.53%346.512705.0
2.14Landscaping84,173.65%4,208.77%6186.83%2651.597220.5
2.15Drilled Shafts25,000.05%1,250.07%1837.53%787.528875.0
2.16Total1,219,760.0 60,414.1 88,808.7 38,060.91,395,565.3

Table C2 gives the opportunity to capture some costs that are not captured in the previous tables. Physical contingencies represent an extra amount to account for changes in project quantities or other added expenses directly related to changes in a particular program element.

Table C3 Distribution of Cost (Percent of Work Completed)
 Item200520062007200820092010Total
3.6Design0%50%50%0%0%0%100%
3.7Supervision0%0%10%40%40%10%100%
3.8Right of Way25%50%25%0%0%0%100%
3.9Clearing and Grubbing0%0%100%0%0%0%100%
3.10Road and Access0%0%100%0%0%0%100%
3.11Grading0%0%50%50%0%0%100%
3.12Noise Barrier0%0%0%25%50%25%100%
3.15Foundations0%0%0%50%50%0%100%
3.16Seeding and Mulching0%0%0%0%0%100%100%
3.17Landscaping0%0%0%0%0%100%100%
3.18Drilled Shafts0%0%0%50%50%0%100%
3.19Total        0%

Table C3 provides the opportunity to identify the distribution of cost based on the percentage of work completed in each year of the project. This information is not necessary for all projects, or likely, the information is not known during project planning. The information in this table feeds into some of the following tables.

Table C4 Distribution of Cost, In Constant Prices ($)
 Item200520062007200820092010Total
4.6Design0.044,404.344,404.30.00.00.088,808.70
4.7Supervision0.00.03,806.115,224.315,224.33,806.138,060.87
4.8Right of Way3,013.16,026.23,013.10.00.00.012,052.34
4.9Clearing and Grubbing0.00.0183,750.00.00.00.0183,750.00
4.10Road and Access0.00.026,250.00.00.00.026,250.00
4.11Grading0.00.021,000.021,000.00.00.042,000.00
4.12Noise Barrier0.00.00.0107,128.4214,256.7107,128.4428,513.40
4.15Foundations0.00.00.0231,000.0231,000.00.0462,000.00
4.16Seeding and Mulching0.00.00.00.00.011,550.011,550.00
4.17Landscaping0.00.00.00.00.088,382.388,382.29
4.18Drilled Shafts0.00.00.013,125.013,125.00.026,250.00
4.19Total3,013.150,430.5282,223.5387,477.7473,606.0210,866.71,407,617.60

Table C4 give the distribution of cost in constant prices across the life of the project.

Table C5 Distribution of Cost, In Constant Prices ($)
Item200520062007200820092010Total
Inflation Rate 4.0%4.0%4.0%4.0%4.0%
Price Index1.0001.0401.0821.1251.1701.217  
        
Design0.046,180.548,027.70.00.00.094,208.27
Supervision0.00.04,116.717,125.317,810.34,630.743,683.01
Right of Way3,013.16,267.23,259.00.00.00.012,539.26
Clearing and Grubbing0.00.0198,744.00.00.00.0198,744.00
Road and Access0.00.028,392.00.00.00.028,392.00
Grading0.00.022,713.623,622.10.00.046,335.74
Noise Barrier0.00.00.0120,504.8250,650.0130,338.0501,492.88
Foundations0.00.00.0259,843.6270,237.30.0530,080.91
Seeding and Mulching0.00.00.00.00.014,052.314,052.34
Landscaping0.00.00.00.00.0107,530.6107,530.57
Drilled Shafts0.00.00.014,763.815,354.40.030,118.23
Total3,013.152,447.7305,253.0435,859.7554,052.1256,551.61,607,177.21

Table C5 provides the opportunity to account for inflation across the life of the project. This information carries into Table C6 as the project financial contingencies.

Table C6 Cost Summary ($)
 SummaryBase CostPhysical
Contingency
Financial
Contingency
Total Cost
Current $
% of
Total
6.5 Design 88,808.7 5,399.6 94,208.27 5.9%
6.6 Supervision 38,060.9 5,622.1 43,683.01 2.7%
6.7 Right of Way 11,478.4 573.9 486.9 12,539.3 0.8%
6.8 Clearing and Grubbing 175,000.0 8,750.0 14,994.0 198,744.00 12.4%
6.9 Road and Access 25,000.0 1,250.0 2,142.0 28,392.00 1.8%
6.1 Grading 40,000.0 2,000.0 4,335.7 46,335.74 2.9%
6.11 Noise Barrier 408,108.0 20,405.4 72,979.5 501,492.88 31.2%
6.14 Foundations 440,000.0 22,000.0 68,080.9 530,080.91 33.0%
6.15 Seeding and Mulching 11,000.0 550.0 2,502.3 14,052.34 0.9%
6.16 Landscaping 84,173.6 4,208.7 19,148.3 107,530.57 6.7%
6.17 Drilled Shafts 25,000.0 1,250.0 3,868.2 30,118.23 1.9%
6.18 Total 1,346,629.6 60,988.0 199,559.6 1,607,177.21 100.0%
6.19 Cost Distribution  
6.20 as % of base cost 100.0% 4.5% 14.8% 119.3%  
6.21 as % of total cost 83.8% 3.8% 12.4% 100.0%
6.22  
6.23 Cost Indicators Cost  
6.24 Base Cost  
6.25 Construction 873,108.00
6.26 Site Preparation 240,000.00
6.27 Landscaping/Site Finishing 95,173.61
6.28 Right of Way 11,478.42
6.29 Total Base Cost 1,219,760.03
6.30 Design + Supervision 126,869.57
6.31 Phys Contingencies 60,988.00
6.32 Financial Contingencies 199,559.61
6.33 Total Current Cost 1,607,177.21
6.34 Barrier Square Footage 55,860.00
6.35 Avg cost/sf of noise barrier ($) 28.77
6.36 Cost per Residence 14,349.80
6.37 Cost Reasonable ? Yes

Table C6 provides a summary of total project costs and an outcome of the projects cost reasonableness based on projected costs.

Updated: 6/28/2017
HEP Home Planning Environment Real Estate
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000