Concrete Inspector's Check List
Site of Delivery
Word Version (42 kb) | PDF Version (21 kb)
- Assemble all test equipment
- Thermometers
- Air meter
- Scales
- Slump Cone
- Buckets
- Cylinder molds
- Measuring Tape
- Wheel Barrow
- Obtain Haul Tickets
- Check revolution count
- Check total water added at plant
- Check time of beginning of mixing
- Check Mix Consistency
- Allow contractor to add additional water if slump of mix is to low provided maximum water to cement ratio is not exceeded
- Mix additional 30 revolutions is water is added at site
- Allow discharge when required mixing revolutions have been completed
- Test air content
- Determine unit weight
- Test slump
- Check mix temperature
- Check atmospheric temperature
- Mold and cure concrete cylinders for strength tests
- Monitor time from introduction of cement at mixer to time of discharge (1 hour max.)
- Complete haul ticket data
- Fill out daily report