Value for Money Analysis for Public-Private Partnerships (P3s)

Download as PDF

Under a Public-Private Partnership (P3) for highway projects, a private partner may participate in some combination of design, construction, financing, operations and maintenance, including collection of toll revenues. Value for Money (VfM) analysis is a process used to compare the financial impacts of a P3 project against those for the traditional public delivery alternative. The methodology for carrying out a VfM analysis involves:

traffic on freeway
  • Creating a Public Sector Comparator which estimates the whole-life cost of carrying out the project through a traditional approach
  • Estimating the whole-life cost of the P3 alternative (either as proposed by a private bidder, or a hypothetical "shadow bid" at the pre-procurement stage)
  • Completing an "apples-to-apples" comparison of the costs of the two approaches

The Public Sector Comparator (PSC)

The PSC estimates the hypothetical risk-adjusted cost if a project were to be financed, built and operated by the public sector using its traditional procurement approach. It includes the baseline PSC cost, ancillary costs, financing costs, retained risk, transferable risk and competitive neutrality.

The baseline PSC includes all capital and operating costs associated with building, owning, maintaining and delivering the service over the pre-determined period of time. Ancillary costs include other costs such as right-of-way and procurement costs. Financing costs are those associated with interest costs on public debt and issuance fees. Retained risk refers to the value of any risk that is not transferable to the bidder, and transferable risk refers to the value of any risk that is transferable to the bidder. Competitive neutrality adjustments remove any competitive advantages and disadvantages that accrue to a public agency by virtue of its public ownership, such as its freedom from taxes. The present value of forecasted toll revenue is generally subtracted from total PSC costs to get net present cost (NPC).

The P3 Option

The cost elements of a P3 option are: (1) the present value of payments to be made to the private partner, which account for transferred risks and financing costs; (2) the value of any risks retained by the public sector; and (3) any ancillary costs borne by the public agency. At the pre-procurement stage, a "shadow bid" is constructed to estimate what the private sector would bid in response to a P3 Request for Proposals (RFP).

Comparing the PSC to the P3 Option

Generally, a P3 proposal must cost less than the PSC in order to be preferable to a traditional procurement approach. However, even if P3 costs are higher, qualitative factors not included in the quantitative analysis may still make the P3 approach preferable. When a P3 presents overall savings, it is said to provide "value for money." This value is usually expressed as the percent difference by which the PSC cost exceeds the P3 cost. Small changes in the assumptions underlying the analysis can tip the balance. So it is important to undertake a sensitivity analysis to understand the critical assumptions.

An Example: Comparing a Public Sector Comparator against a P3 Shadow Bid

The example depicted in the bar chart portrays a comparison between a public procurement with a baseline present cost of $60 million and a P3 shadow bid for which the baseline present cost (net of financing costs) is $65 million. While the baseline P3 cost is $5 million more and imposes an additional $6 million in ancillary and financing costs, the $13 million reduction in the costs of risk due to transfer of some risks to the private sector and $8 million in competitive neutrality adjustments overcome these cost differences and result in a net savings to the government of $9 million overall, offering 7% in Value for Money. This example illustrates the central trade-offs that often characterize P3 procurement: the government trades away significant risks in exchange for higher baseline costs and financing costs in the P3 scenario.

Figure 1. Comparison Between a Public Procurement and a P3 Shadow Bid.
PSC = Public Sector Comparator, P3 = public-private partnership

Figure 1

Text of Figure 1. Comparison Between A Public Procurement and a P3 Shadow Bid chart

  • Public Sector Comparator
    • Base Cost $60M
    • Financing $15M
    • Ancillary Costs $11M
    • Retained Risk $20M
    • Competitive Neutrality $8M
      • Total Public Sector Comparator = $114M
  • Public-Private Partnership
    • Base Cost $65M
    • Financing $17M
    • Ancillary Costs $15M
    • Retained Risk $7M
    • Competitive Neutrality $0
      • Total Public-Private Partnership = $105M

Program Areas of the Center for Innovative Finance Support

The Center for Innovative Finance Support is a one-stop clearinghouse for expertise, guidance, research, decision tools, and publications on program delivery innovations. Our website, workshops, and myriad resources support transportation professionals in the delivery of innovative approaches.

Public Private Partnerships (P3s)

The Center for Innovative Finance Support's P3 program focuses on the potential of design-build-operate-finance maintain (DBFOM) concessions funded through tolls or availability payments to reduce project cost, improve quality outcomes, and provide additional financing options.

Alternative Project Delivery

The Center for Innovative Finance Support's Alternative Project Delivery program provides information on contractual arrangements that allow for greater private participation in infrastructure development by transferring risk and responsibility from public project sponsors to private sector engineers, contractors and investors.

Project Finance

Center for Innovative Finance Support's Project Finance program focuses on alternative financing, including State Infrastructure Banks (SIBs), Grant Anticipation Revenue Vehicles (GARVEEs), and Build America Bonds (BABs).

Tolling And Pricing

The Center for Innovative Finance Support's Federal Tolling and Pricing program focuses on the use of tolling and other road user charges as a revenue source to fund highway improvements, and the use of variably-priced tolls as a tool to manage congestion.

Value Capture

The Center for Innovative Finance Support's Value Capture program explores strategies for tapping into the added value that transportation improvements bring to nearby properties as a means to provide new funding for surface transportation improvements.

Quick Facts

Value for Money (VfM) analysis is a process used to compare the financial impacts of a P3 project against those for the traditional public delivery alternative.

The PSC estimates the hypothetical risk-adjusted cost if a project were to be financed, built and operated by the public sector using its traditional procurement approach.

With P3 procurement, the government trades away significant risks in exchange for higher baseline costs and financing costs in the P3 scenario.