CIFS Tool Categories: Value Capture (Transportation Utility Fees)
Project Name | Juniper Complete Street Project | |
---|---|---|
Location | Atlanta, GA | |
Project Sponsor / Borrower | Midtown Alliance | |
Program Areas | ||
Value Capture Techniques | Development Impact Fees / Mobility Fees & Community Improvement Districts | |
Mode | Local Road / Multimodal (Pedestrian / Bicycle / Light Rail Transit) | |
Description | The Juniper Complete Street Project is a complex construction plan that spans 12 blocks between 14th Street and Ponce de Leon. It involves public agencies and organizations, and includes significant design and construction challenges with unique funding streams. The project will create a bikeway with improved pedestrian amenities to keep traffic moving at a steady pace. New construction will include wider sidewalks, lighting, trash and recycling receptacles, and a network of stormwater planters that will direct pedestrians between Midtown’s commercial and residential areas. The planters will manage rainwater and reduce demand on the city’s infrastructure. Plans also include building a six- to seven-foot separated bike lane adjacent to the western sidewalk that will be protected by a wide, raised and/or planted barrier at each intersection. The bike lane buffer will include vertical landscape planters, striping, and bollards. |
|
Cost* | $8.7 million *Cost may change upon project completion |
|
Funding Sources |
|
|
Project Delivery / Contract Method | Design-Bid-Build | |
Private Partner | Midtown Alliance | |
Project Advisors / Consultants | TSW Design | |
Lenders | State SRTA/GTIB grant | |
Duration / Status | Duration: The project began in 2011 when the Midtown Alliance hired the design team and the estimated project completion date is in 2022. Since its conception, the following has been completed:
Status: Construction procurement is estimated to begin in late-2020, with an estimated 18 to 24 months to complete. |
|
Financial Status/Financial Performance | The Juniper Complete Street Project was awarded $3.3 million by the Atlanta Regional Commission through their Livable Centers Initiative (LCI) Implementation Program to be administered by the Federal Transit Administration. Later, a $1.3 million state SRTA/GTIB grant was awarded, and the City of Atlanta committed $1.3 million developer impact fees. The Midtown Improvement District is providing $2.8 million additional funding, bringing total project design and construction funding to approximately $8.7 million. | |
Innovations |
|
|
Related Links / Articles | ||
Contact | Name | Dan Hourigan |
Title | Director, Transportation & Sustainability, Midtown Alliance | |
Phone # | ||
dan@midtownatl.com |