| << Previous | Contents | Next >> |
The following are some observations regarding the basic statistics:
It is interesting to note that Virginia does have a lower standard deviation and variance than the other states. These differences point to a higher level of uniformity in Virginia pavement condition.
Table 4.6 presents some of the same basic statistics, except that values have been weighted by segment length. Only the key measures are reported and only the statistics necessary to support calculations of probability and cumulative distributions were calculated.
| State | Statistic | IRI - Average | OPC | CCI |
|---|---|---|---|---|
| DE | Count | 91 | 193 | Not Applicable |
| DE | Average | 125.11 | 67.29 | Not Applicable |
| DE | Std Dev | 81.85 | 15.82 | Not Applicable |
| DE | Variance | 6699.20 | 250.27 | Not Applicable |
| MD | Count | 2177 | Not Applicable | Not Applicable |
| MD | Average | 82.71 | Not Applicable | Not Applicable |
| MD | Std Dev | 46.68 | Not Applicable | Not Applicable |
| MD | Variance | 2179.25 | Not Applicable | Not Applicable |
| VA | Count | 192 | Not Applicable | 190 |
| VA | Average | 83.95 | Not Applicable | 74.17 |
| VA | Std Dev | 21.57 | Not Applicable | 19.81 |
| VA | Variance | 465.18 | Not Applicable | 392.41 |
| ALL | Count | 2459 | Not Applicable | Not Applicable |
| ALL | Average | 84.69 | Not Applicable | Not Applicable |
| ALL | Std Dev | 35.46 | Not Applicable | Not Applicable |
| ALL | Variance | 1257.41 | Not Applicable | Not Applicable |
The following are some observations regarding the weighted statistics:
For the second phase of the pavement analysis, CS measured the correlation between IRI and other condition measures. Table 4.7 presents correlations for Delaware. Table 4.8 shows correlations for Maryland. Table 4.9 presents correlations for Virginia. Because IRI was the only measure reported by all states, CS was unable to produce any correlations between states.
| Statistic | IRI - Right | IRI - Average | OPC |
|---|---|---|---|
| IRI - Left | 0.81 | 0.95 | 0.12 |
| IRI - Right | 0.95 | 0.14 | |
| IRI - Average | 0.14 |
| Statistic | Rut Depth | Rut Count | Friction Number | Cracking Index |
|---|---|---|---|---|
| IRI - Average | 0.19 | -0.02 | -0.07 | -0.19 |
| Rut Depth | 0.87 | -0.14 | -0.11 | |
| Rut Count | -0.03 | -0.08 | ||
| Friction Number | 0.26 |
| Statistic | IRI - Right | IRI - Average | LDR | NDR | CCI |
|---|---|---|---|---|---|
| IRI - Left | 0.86 | 0.96 | -0.40 | -0.37 | -0.44 |
| IRI - Right | 0.97 | -0.39 | -0.38 | -0.42 | |
| IRI - Average | -0.41 | -0.39 | -0.45 | ||
| LDR | 0.72 | 0.94 | |||
| NDR | 0.88 |
The following are some observations regarding the correlation coefficients:
In addition to computing the correlation coefficients, CS also prepared probability and cumulative distributions and associated graphs. A large number of graphs were produced and representative samples are shown below. Figure 4.5 shows probability and cumulative distributions for Delaware. Figure 4.6 shows distributions for Maryland. Figure 4.7 shows distributions for Virginia.
The distribution graphs for Delaware reflect the higher standard deviation and variance encountered for the Delaware IRI readings compared to the other states. For Maryland, the IRI Condition Index graphs show an index computed from the IRI data. The sharp curves reflect the fact that this index can assume values only between 1 and 5. Maryland also computes similar indexes, with similar distribution graphs, for the other condition measures. For Virginia, the similarity between the IRI and CCI graphs is driven by similarities in the averages and standard deviations for these measures. This would indicate that these values, although not well correlated, are related in some way. This would seem to be true even though IRI is not a component of CCI.
Graphs for other condition measures are similar. Most of the graphs for the cracking measures in Virginia are so spread out that they almost appear to be straight lines. This is a function of the extremely high standard deviations for these measures, which were noted above for Table 4.4.
Figure 4.5 Pavement Distributions - Delaware

Figure 4.6 Pavement Distributions - Maryland

Figure 4.7 Pavement Distributions - Virginia

Figures 4.5, 4.6, and 4.7 show values not weighted by segment length. Figure 4.8 compares weighted and not weighted measures in Delaware.
Figure 4.8 Weighted Pavement Distributions - Delaware

With the exception of Delaware, the distributions showing pavement measures that are weighted and not weighted by segment length are virtually identical. Figure 4.9 compares the weighted and not weighted values for IRI across all states.
Figure 4.9 Pavement Distributions - All States

As with the bridge analysis, pavement measures weighted by segment length generally are sharper (i.e., the probability distributions are narrower and the peaks higher). For pavement, these differences are extremely small, which reinforces conclusions associated with Table 4.6.
A key piece of this analysis was focused on comparing algorithms for composite measures across states. Both Delaware and Virginia use composite measures. However, given the complexity of the Virginia algorithm for CCI, CS opted to focus on using the Delaware algorithm for OPC. Also, CS determined that the breadth of data elements provided by Maryland was insufficient to satisfy the requirements of the OPC algorithm. Therefore, CS concentrated on calculating OPC using Virginia data and the Delaware algorithm.
For this analysis, CS performed the following steps:
CS opted for the following mapping:
Other Virginia measures such as lane joints, delaminations, bleeding, potholes, etc., were not used. The most problematic of these assumptions is IRI * Rut Depth = Surface Defects. However, CS assumed that any issues would be covered when an extent and severity for each measure are estimated in Steps 2 and 3. Also, as long as the calculations were performed consistently, CS believes that a meaningful correlation can be obtained regardless of the validity of the mapping.
CS attempted to convert the absolute quantities into percents scaled by the segment length. For each measure, the absolute values for all severities were added and then multiplied by the segment length in feet. The maximum value of this calculation was computed for each measure. Then, the measure for each segment was divided by the maximum. Percentages <= 33.3 were assigned a LOW extent. Percentages >= 66.7 were assigned a HIGH extent. All other values were assigned a MEDIUM extent.
For each segment, CS assumed that the severity with the greatest absolute quantity of distress could be used as the overall severity level. For measures like alligator cracking, where Virginia already defined three severity levels, severity 1=LOW, severity 2=MEDIUM and severity 3=HIGH. For measures like transverse cracking, where Virginia only defined two severity levels, CS "created" an intermediate severity category equal to one-third of severity 1 plus one-third of severity 2. This left severities 1 and 2 with 66 percent of their original value. Again, the overall severity level for the segment was defined as the severity category with the greatest absolute value.
For surface defects, CS observed that IRI * Rut Depth yielded values running approximately from 0 to 50. If this value was <= 16.67, then severity=LOW. If this value was >= 33.33, then the severity=HIGH. Otherwise, the severity=MEDIUM.
Step 4 - Using the HIGH, MEDIUM, LOW severity and extent calculated in Steps 2 and 3 for each Virginia pavement segment, lookup five distress index values using the Delaware tables shown in Figure 4.4.
Figure 4.10 OPC versus CCI in Virginia

This exercise demonstrates that composite measures (i.e., measures that combine multiple distresses into a single value) tend to track well regardless of the algorithm used to produce the measure. And because neither OPC nor CCI correlate well with IRI in Virginia (OPC versus IRI=-0.49 and CCI versus IRI= 0.45), CS concludes that composite values provide a superior measure of pavement condition when compared to IRI.
In Task 1, CS contacted agencies responsible for the collection of bridge and pavement data for Delaware, Maryland, and Virginia. The data collection process is described in Section 2 and the specific individuals that provided the data are documented in Table 2.2.
As part of the data analysis task, CS again contacted these individuals to conduct follow-up interviews. The interviews focused on three main areas:
This section documents the information received from each state.
States inspect and record information on the condition of bridges and pavement annually. This process supports both in-house uses (e.g., determination of maintenance priorities) as well as Federal reporting requirements for the NBI and the HPMS. While all states maintain engineers and other in-house bridge and pavement experts, CS observed that Delaware, Maryland, and Virginia all outsource at least some of their inspection activities.
Every state operates both a bridge management system (BMS) and a pavement management system (PMS) that, at a minimum, allow for storing and reporting of information. These systems also may provide capabilities to assist with inspection, calculate condition measures, and manage assets.
For its bridges, Delaware uses a combination of in-house inspectors and outside consultants. The consultants are used primarily for specialized structures such as moveable bridges. Most inspectors take laptops equipped with the Pontis BMS into the field to record both NBI and element-level inspections. The bridge inspection engineers are responsible for ensuring that information is moved into the production Pontis database. This process usually occurs within one week following the inspection. The bridge inspection engineer is responsible for calculating the sufficiency rating at a later time (i.e., after the inspection has been moved into the production system and reviewed).
For its roads, Delaware previously collected pavement data using a windshield survey but recently has contracted with Applied Research Associates, Inc. (ARA), which will use an instrumented van to collect pavement measurements for future inspections. ARA will be responsible for calibrating the inspection tools. As part of the transition to ARA, Delaware has stated that they will begin measuring IRI on all road segments, not just those required for HPMS reporting. ARA will be responsible for moving all inspection data into the Delaware PMS, which also is provided by ARA. Although this process is expected to be highly automated, it is not clear what sort of time lag will be encountered since there is considerably more data (e.g., images and video logs) to be transferred.
For its bridges, Maryland also uses a combination of in-house inspectors and outside consultants. The situation is identical to Delaware in that the consultants provide expertise on specialized structures (e.g., moveable and fracture critical bridges). NBI and element-level inspection information is captured on paper and entered into a custom BMS on a monthly basis. An outside consultant is used to calculate sufficiency rating for the bridges.
For its roads, Maryland uses its own equipment to automatically inspect approximately 11,000 lane-miles per year. Data are captured every 52 feet and rolled up to one-tenth-mile and one-half-mile values. Maryland contracts with ARA to compute values based on the inspection data, including condition indexes for IRI, cracking, friction, and rutting. On a weekly basis, data are transferred automatically to a custom PMS.
For its bridges, Virginia also uses a combination of in-house inspectors and outside consultants. Consultants are used to compensate for insufficient in-house staff. These inspectors use a combination of paper forms and tablet-style laptops to perform both NBI and element-level inspections. Inspectors are responsible for transferring or entering data into the state's Pontis system on a weekly basis. A bridge safety engineer calculates the sufficiency rating for each bridge using the Pontis functionality.
For its roads, Virginia uses a contractor, Furgo Roadware, to perform automated inspections using an instrumented van. As with ARA in the other states, Furgo Roadware is responsible for calibrating the van and transferring the inspection information weekly into Virginia's Agile Assets PMS. This process is supported by dedicated information technology (IT) personnel.
Quality assurance (QA) involves validating the data, the data collection process, or both to ensure that the information being recorded is accurate. QA can include many types of tests, from looking for missing values to double-checking unexpected results to direct validation of some percentage of the original data. Frequently, the level of QA involves a tradeoff between the desired level of accuracy and the cost, in both time and money, to perform the tests.
Although states usually will provide guidelines for both bridge and pavement inspections, CS believes that bridge inspections rely more on the engineering expertise of the inspector than do pavement inspections. As discussed in the previous section, a pavement inspection primarily is an automated process that directly measures certain attributes of the road. There is a visual component to count/measure defects such as cracks and potholes, but overall the pavement inspection process is fairly mechanical.
The differences in the bridge and pavement inspection processes seem to affect the degree to which the data may be validated by a state. CS observed that the states participating in this study generally invest more effort in reviewing bridge data than pavement data. CS believes that this is a function both of the type of information gathered for pavement sections and the automated processes used to capture this information.
For bridges, the bridge inspection engineer performs the initial QA check at the time data are transferred to the production Pontis database. This generally involves a visual review of the information being transferred. At this point, a team lead may review the information before sending it to a supervisor, who checks for missing data and invalid entries. Changes to inspection data happen infrequently, but if an error is discovered, the inspection engineer reviews the issue and makes any necessary changes before sending the change to the team lead for signoff.
For roads, a supervisor reviews the inspection data both before and after they are moved into the Delaware PMS. It is rare for data to be questioned. The biggest issue that may be encountered are missing records.
For bridges, a supervisor reviews the inspection data based on reports sent by the engineering team lead. These reports are created after the monthly transfer of information to the BMS. Changes to inspections based on this review are rare. Also, an independent internal inspection team will recheck a certain amount of work each year. According to Maryland, approximately 10 percent of the inspections may be verified by this other team.
For roads, office staff review the data received from ARA. It is rare for these data to be questioned or adjusted.
For bridges, a bridge safety engineer reviews data at the end of the inspection process. This happens both at the district and state level. Inspection updates are infrequent but any changes are entered directly into the State's Pontis system.
For roads, the IT team responsible for loading the inspection data performs a QA process that includes comparing data summaries generated both inside and outside the PMS. In addition, a third party will review and verify approximately five percent of the records. Inspection data rarely are questioned. However, the team does look for and check large discrepancies in the year-to-year data for any given segment.
Numerical measures provide one means of quantifying the condition of a bridge or a pavement section. However, there also is a natural desire to classify asset conditions as "good" or "fair" or "poor" in order to obtain a qualitative assessment of the health of a network.
For bridges, the states participating in this study indicated that they rarely use health index to represent asset condition. Instead they rely on the traditional measures of structurally deficient and functionally obsolete. It is true that functional obsolescence is not considered in the health index calculation. When scheduling maintenance and other activities, states deal with bridges as discrete items. However, when expressing the overall condition of their bridge network, states typically would target "less than five percent of all bridges are structurally deficient," which was the goal expressed by Delaware.
For pavement, Delaware defines characteristics for low, medium, and high severity and extent for different pavement types. Table 4.10 shows the definitions used to judge distress severity for flexible pavement. Table 4.11 shows the definitions for distress extent for flexible pavement. Severity and extent for pavement sections feed into the distress conversion tables, shown in Figure 4.4, which are used to compute OPC. OPC is a value between 0 (worse condition) and 100 (best condition). Delaware categorizes OPC as follows: <= 50 is poor, > 50 and <= 60 is fair, and > 60 is good. Because Delaware previously collected IRI only for HPMS sections, the state has not defined any qualitative categories for this measure.
| Distress | Low | Medium | High |
|---|---|---|---|
| Fatigue Cracking | Fine parallel hairline cracks | Alligator crack pattern clearly developed | Alligator crack pattern clearly developed with spalling and/or distortion |
| Transverse Cracking | Crack< 1/4 inch wide | Crack Width > 1/4 and < 3/4 inch and/or spalls less than 3 inches in width or sealed crack with sealant in good condition | Crack Width > 3/4 inch and/or spalls greater than 3 inches in width or significant loss of material |
| Block Cracking | Crack < 1/4 inch wide | Crack Width > 1/4 and < 3/4 inch and/or spalls less than 3 inches in width or sealed crack with sealant in good condition | Crack Width > 3/4 inch and/or spalls greater than 3 inches in width or significant loss of material |
| Patch Deterioration | Patches showing little or no defects with a smooth ride | Patches showing medium severity defects (e.g., cracking) and/or notable roughness | Patches showing high-severity defects and/or distinct roughness |
| Surface Defects | Aggregate has begun to wear away | Aggregate has worn away and surface is becoming rough and/or minor rutting occurring from horse and buggy traffic (less than 1 inch average depth) | Aggregate has worn away and surface is very rough and/or major rutting occurring from horse and buggy traffic (greater than 1 inch average depth) |
Source: Delaware Department of Transportation.
| Distress | Low | Medium | High |
|---|---|---|---|
| Fatigue Cracking | 1-9% (wheel path) | 10-25% | > 25% |
| Transverse Cracking | > 50 foot spacing | 25 foot < spacing <50 foot | < 25 foot spacing |
| Block Cracking | 1-9% | 10-25% | > 25% |
| Patch Deterioration | 1-9% | 10-25% | > 25% |
| Surface Defects | 1-9% | 10-25% | > 25% |
Source: Delaware Department of Transportation.
For pavement, Maryland collects absolute measures and then computes an index measure based on the definitions shown in Table 4.12.
| Distress | Measurement | Condition Description | Condition Index |
|---|---|---|---|
| IRI (inch/mile) | > 0 and < 60 | Very Good | 1 |
| >= 60 and < 95 | Good | 2 | |
| >= 95 and <= 170 | Fair | 3 | |
| > 170 and <= 220 | Mediocre | 4 | |
| > 220 and <= 640 | Poor | 5 | |
| Cracking Index | >= 90 and <= 100 | Very Good | 1 |
| >= 80 and < 90 | Good | 2 | |
| >= 65 and < 80 | Fair | 3 | |
| >= 50 and < 65 | Mediocre | 4 | |
| > 0 and < 50 | Poor | 5 | |
| Friction Number | < 35 | Poor | 1 |
| >= 35 and < 40 | Mediocre | 2 | |
| >= 40 | Acceptable | 3 | |
| Percent Rutting > one-half-inch | < 10% | Very Good | 1 |
| >= 10% and < 20% | Fair | 2 | |
| >= 20% | Poor | 3 |
Source: Maryland State Highway Administration.
For pavement, Virginia provides guidelines, presented in Table 4.13, on how to measure and determine the severity of different types of cracking.
| Distress | Severity Level | Severity Description | How to Measure |
|---|---|---|---|
| Transverse Cracking | Severity 1 | A crack with the sealant in good condition such that the crack width cannot be determined or a closed, unsealed crack. | Record length of transverse cracks at each severity level. Evaluate each crack by highest severity level present on a significant portion of the crack as it is traversed. |
| Severity 2 | An open, unsealed crack or any crack (sealed or unsealed) with adjacent (within one foot) random cracking. | Record length of transverse cracks at each severity level. Evaluate each crack by highest severity level present on a significant portion of the crack as it is traversed. | |
| Longitudinal Cracking | Severity 1 | A crack with the sealant in good condition such that the crack width cannot be estimated or a closed, unsealed crack. | The minimum length of longitudinal cracking counted is one foot. Only longitudinal cracking outside the wheel paths is counted as longitudinal and each occurrence is counted separately. Longitudinal cracking in the wheel paths is counted as Severity 1 alligator cracking. Measure the length of each crack by severity level as it is traversed. Rate each crack at the highest severity level present on a significant portion of the crack. Report the total length of cracking by severity level for the section. |
| Severity 2 | An open, unsealed crack or any crack (sealed or unsealed) with adjacent random cracking. | The minimum length of longitudinal cracking counted is one foot. Only longitudinal cracking outside the wheel paths is counted as longitudinal and each occurrence is counted separately. Longitudinal cracking in the wheel paths is counted as Severity 1 alligator cracking. Measure the length of each crack by severity level as it is traversed. Rate each crack at the highest severity level present on a significant portion of the crack. Report the total length of cracking by severity level for the section. | |
| Alligator Cracking | Severity 1 | A single sealed or unsealed longitudinal crack in the wheel path or an area of cracks with no or few interconnecting cracks with no spalling. | Considering only the left and right wheel paths, measure the affected area (square feet) at each severity level. Consider only one severity level for a given area. If different severity levels in an area cannot be distinguished, rate the area at the highest severity level. The width of alligator cracking shall be the actual width while a minimum width for all severity levels shall be one foot. Report the square feet of alligator cracking by severity level for the section. |
| Severity 2 | An area of interconnecting cracks forming the characteristic alligator pattern; may have slight spalling. | Considering only the left and right wheel paths, measure the affected area (square feet) at each severity level. Consider only one severity level for a given area. If different severity levels in an area cannot be distinguished, rate the area at the highest severity level. The width of alligator cracking shall be the actual width while a minimum width for all severity levels shall be one foot. Report the square feet of alligator cracking by severity level for the section. | |
| Severity 3 | An area of moderately or severely spalled cracks forming the characteristic alligator pattern. | Considering only the left and right wheel paths, measure the affected area (square feet) at each severity level. Consider only one severity level for a given area. If different severity levels in an area cannot be distinguished, rate the area at the highest severity level. The width of alligator cracking shall be the actual width while a minimum width for all severity levels shall be one foot. Report the square feet of alligator cracking by severity level for the section. |
Source: Virginia Department of Transportation.
Virginia also categorizes both IRI and CCI, as shown in Table 4.14. Virginia refers to CCI as "pavement condition" while referring to IRI as "ride quality."
| Category | Measurement | Pavement Condition/Ride Quality |
|---|---|---|
| CCI | >= 90 | Excellent |
| >= 70 and < 90 | Good | |
| >= 60 and < 70 | Fair | |
| >= 50 and < 60 | Poor | |
| < 50 | Very Poor | |
| IRI | < 60 | Excellent |
| >= 60 and < 100 | Good | |
| >= 100 and < 140 | Fair | |
| >= 140 and < 200 | Poor | |
| >= 200 | Very Poor |
Source: Virginia Department of Transportation.
Following the analysis of the bridge and pavement data, CS selected certain measures to be displayed in the ICAT web application (WebCAT). Consistent with the design presented in Section 5, CS selected approximately six measures for bridges and six for pavement. These measures were incorporated as standard ArcGIS-compatible layers that are accessed using functionality already available in the WebCAT.
At the present time, the modified WebCAT system may be accessed at: http://ags.camsys.com/hpm/index.html.
The WebCAT created in conjunction with this project is a modified version of the WebCAT originally developed for the I-95 Corridor Coalition. The intent is to transition production hosting for the I-95 WebCAT at some point in the future to the University of Maryland. At the time of this transition, FHWA and the I-95 Corridor Coalition must determine the future of the modified WebCAT created for this project.
Within the WebCAT interface, bridge measures for this project are contained within the category "Bridges (Mid-Atlantic)" while the pavement measures for this project are under "Pavement (Mid-Atlantic)." The following sections describe each measure. Each description is followed by a table that shows the asset count based on the current data. Pavement tables also include total miles (rounded), which are computed by summing the difference between the beginning and ending milepoint for each segment. Note that the counts are not consistent because of minor variations in the data (e.g., based on its specific data, a bridge may or may not have a valid sufficiency rating and/or health index).
Also note that CS does not characterize any data as "good," "fair," "poor," etc. These characterizations, where they are used, either come from a state participating in this study or an external source, such as NBIAS. In some cases, data are divided into categories arbitrarily for purposes of comparing different measures for the same assets. These ranges are not intended to represent quality ratings.
| State | SD | FO | ND | Total |
|---|---|---|---|---|
| Delaware | 1 | 9 | 52 | 62 |
| Maryland | 1 | 0 | 82 | 83 |
| Virginia | 24 | 33 | 247 | 304 |
| Total | 26 | 42 | 381 | 449 |
| State | Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 34 | 26 | 0 | 60 |
| Maryland | 10 | 33 | 1 | 44 |
| Virginia | 190 | 102 | 6 | 298 |
| Total | 234 | 161 | 7 | 402 |
| State | Green | Blue | Yellow | Orange | Red | Total |
|---|---|---|---|---|---|---|
| Delaware | 8 | 14 | 12 | 24 | 2 | 60 |
| Maryland | 1 | 0 | 9 | 32 | 2 | 44 |
| Virginia | 62 | 36 | 92 | 86 | 22 | 298 |
| Total | 71 | 50 | 113 | 142 | 26 | 402 |
| State | Green | Blue | Yellow | Orange | Red | Total |
|---|---|---|---|---|---|---|
| Delaware | 26 | 21 | 10 | 4 | 0 | 61 |
| Maryland | 9 | 6 | 2 | 5 | 1 | 23 |
| Virginia | 150 | 38 | 55 | 55 | 6 | 304 |
| Total | 185 | 65 | 67 | 64 | 7 | 388 |
| State | Small Diff | Medium Diff | Large Diff | Total |
|---|---|---|---|---|
| Delaware | 46 | 14 | 0 | 60 |
| Maryland | 13 | 3 | 0 | 16 |
| Virginia | 239 | 58 | 1 | 298 |
| Total | 298 | 75 | 1 | 374 |
| State | Small | Sm/Med | Medium | Med/Lg | Large | Total |
|---|---|---|---|---|---|---|
| Delaware | 33 | 22 | 2 | 1 | 3 | 61 |
| Maryland | 20 | 36 | 1 | 1 | 1 | 59 |
| Virginia | 90 | 80 | 11 | 3 | 20 | 204 |
| Total | 143 | 138 | 14 | 5 | 24 | 324 |
| State | Total |
|---|---|
| Delaware | 62 |
| Maryland | 83 |
| Virginia | 304 |
| Total | 449 |
| State | Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Virginia | 117 (228 mi) | 27 (50 mi) | 40 (72 mi) | 184 (350 mi) |
| Total | 117 (228 mi) | 27 (50 mi) | 40 (72 mi) | 184 (350 mi) |
| State | Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 224 (58 mi) | 36 (10 mi) | 10 (2 mi) | 270 (70 mi) |
| Maryland | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Virginia | 171 (319 mi) | 8 (13 mi) | 5 (7 mi) | 184 (339 mi) |
| Total | 395 (377 mi) | 44 (23 mi) | 15 (9 mi) | 454 (409 mi) |
| State | Small Diff | Medium Diff | Large Diff | Total |
|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Virginia | 127 (247 mi) | 52 (94 mi) | 7 (12 mi) | 186 (353 mi) |
| Total | 127 (247 mi) | 52 (94 mi) | 7 (12 mi) | 186 (353 mi) |
| State | Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 58 (21 mi) | 30 (5 mi) | 32 (5 mi) | 120 (31 mi) |
| Maryland | 1627 (163 mi) | 328 (33 mi) | 135 (14 mi) | 2090 (210 mi) |
| Virginia | 118 (231 mi) | 66 (108 mi) | 0 (0 mi) | 184 (339 mi) |
| Total | 1803 (415 mi) | 424 (146 mi) | 167 (19 mi) | 2394 (580 mi) |
| State | Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 59 (21 mi) | 22 (4 mi) | 39 (5 mi) | 120 (30 mi) |
| Maryland | 1662 (166 mi) | 187 (19 mi) | 241 (24 mi) | 2090 (209 mi) |
| Virginia | 126 (247 mi) | 54 (87 mi) | 4 (5 mi) | 184 (339 mi) |
| Total | 1847 (434 mi) | 263 (110 mi) | 284 (34 mi) | 2394 (578 mi) |
| State | Very Good | Good | Fair | Mediocre | Poor | Total |
|---|---|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 804 (80 mi) | 820 (82 mi) | 338 (34 mi) | 86 (9 mi) | 50 (5 mi) | 2098 (210 mi) |
| Virginia | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Total | 804 (80 mi) | 820 (82 mi) | 338 (34 mi) | 86 (9 mi) | 50 (5 mi) | 2098 (210 mi) |
| State | Very Good | Good | Fair | Mediocre | Poor | Total |
|---|---|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 1642 (164 mi) | 153 (15 mi) | 73 (7 mi) | 14 (1 mi) | 0 (0 mi) | 1882 (187 mi) |
| Virginia | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Total | 1642 (164 mi) | 153 (15 mi) | 73 (7 mi) | 14 (1 mi) | 0 (0 mi) | 1882 (187 mi) |
| State | Very Good | Fair | Poor | Total |
|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 1754 (175 mi) | 85 (9 mi) | 258 (26 mi) | 2097 (210 mi) |
| Virginia | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Total | 1754 (175 mi) | 85 (9 mi) | 258 (26 mi) | 2097 (210 mi) |
| State | Poor | Mediocre | Acceptable | Total |
|---|---|---|---|---|
| Delaware | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Maryland | 13 (1 mi) | 49 (5 mi) | 310 (31 mi) | 372 (37 mi) |
| Virginia | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) | 0 (0 mi) |
| Total | 13 (1 mi) | 49 (5 mi) | 310 (31 mi) | 372 (37 mi) |
| State | Best | Med/Best | Med/Worst | Worst | Total |
|---|---|---|---|---|---|
| Delaware | 33 (13 mi) | 52 (12 mi) | 28 (4 mi) | 7 (1 mi) | 120 (30 mi) |
| Maryland | 1322 (132 mi) | 561 (56 mi) | 163 (16 mi) | 44 (4 mi) | 2090 (208 mi) |
| Virginia | 53 (116 mi) | 129 (220 mi) | 2 (3 mi) | 0 (0 mi) | 184 (339 mi) |
| Total | 1408 (261 mi) | 742 (288 mi) | 193 (23 mi) | 51 (5 mi) | 2394 (577 mi) |
The goal of this study was to use pavement and bridge data from a multi-state interstate corridor to analyze performance measures and evaluate how performance data can be used for corridor management. The project team was charged with acquiring data from three states, establishing candidate measures that summarize performance of pavement sections and bridges, and performing any necessary reductions/transformations of the data. In addition to this technical memorandum, the project deliverables include a revised version of ICAT showing pavement and bridge measures for use by FHWA and I-95 Corridor Coalition members.
Historically, sufficiency rating for bridge and IRI for pavement have been the measures that are available, either directly or via calculation by FHWA, to judge the condition of the nation's transportation assets. Based on our review of the pavement and bridge data provided by Delaware, Maryland, and Virginia, CS draws the following conclusions regarding these measures.
Transportation asset management is a set of guiding principles and best practices for making informed resource allocation decisions and improving accountability for these decisions. Performance measures are a fundamental building block for any asset management effort. Defining these performance measures helps organizations support asset management in three basic ways:
When considering existing performance measures for bridges and pavement sections, the analysis performed during this project suggests that adequate measures exist for bridges but not for pavement. The following are the findings and recommendations for this analysis.
At the same time, FHWA should consider whether benefit/cost criteria similar to those used in HERS should be incorporated into the functional obsolescence component of the sufficiency rating calculation for bridges. This change could make the sufficiency rating a more effective measure.
| << Previous | Contents | Next >> |