Construction Skill Set - Accelerated Construction - Construction - FHWA
Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Construction

ACTT

<< Previous Contents Next >>

ACTT Workshop: Idaho
The I-84 Corridor Improvements Project

Appendix C Construction Skill Set

Construction
Skill Set Roster:
Ed Sloan, Facilitator
George Raymond
David A. Sadler
Clifford Halvorsen
Dave Kuisti
J.J. Johnson
John Sheldon

Idea Name Detailed Description Implementation Details (barriers, skills set coordination, etc.)

Acceleration of bridge construction

  • Accelerate bridge construction to alleviate bottlenecks during construction.
  • Standardize bridge construction; retain existing foundations, abutments and piers, if possible; allow complete bridge closure for up to one month and implement incentive for using less closure time; remove entire span (deck, girders, diaphragms) using SPMTs and demolish bridge on ground; build new structure in median or nearby staging area; slide new structure into place with SPMTs.
  • Traffic may slow or be distracted by construction in median.
  • SPMT availability may be limited.

Separate contracts for roadwork and structure work

  • Package four or more structures into one contract to accelerate construction; require staged construction of structures.
 

I-84 structures

  • Make all I-84 structures overpasses and depress local streets to at-grade.
  • To construct the overpasses, utilize the outside shoulders to shift I-84 traffic away from the median, and use the median area to construct the overpass.
  • Build the overpass up to the adjacent transverse local street underpass; shut down the transverse street on a weekend; demolish the existing underpass; and build the last span of the I-84 overpass.
  • Overpasses could be expanded in the future much more easily than underpasses.
  • This would alleviate clearance issues for over-height vehicles.
  • This could create drainage issues on certain areas of the Interstate.

Pre-cast deck panels on cast-in-place bridges

  • Consider using pre-cast deck panels for cast-in-place bridges.
  • Place a four-inch overlay on precast deck panels.
  • Use fiber board in between pre-cast panel and girder to accommodate the grade/slope of the bridge.
 

Southern Interstate loop

  • Build southern Interstate loop to handle local traffic volumes.
  • Local road network has very little capacity; area around the Interstate loop could eventually develop and create more traffic on the loop.

Different paving methods

  • Try an un-bonded concrete overlay with an asphalt leveling course to improve the existing concrete pavement in lieu of crack and seat.
  • Mill out four to five inches of existing asphalt pavement and replace with six to eight inches of Superpave.
  • Texas and Oklahoma have had good luck with un-bonded concrete overlay.

Clearance changes

  • Raise (or jack) the existing underpasses to increase bridge clearance.
  • May be easier to raise the smaller bridges than excavate the area below the bridges to get clearance.
  • This would not improve Interstate lane capacity.

New drainage configurations

  • Try to send water to outside the shoulder; consider using a mainline storm water system in the median.
  • High ground water in the area; time restrictions on construction due to the irrigation season.
  • Local farmers use flood irrigation, and local irrigation districts do not want water run-off from the highway.

Staging areas

  • Allow staging area adjacent to Interstate.
  • Allow contractor to "break the fence" (put a break in the access control) so that the contractor could have direct access to the Interstate.
  • The staging area could be fenced to keep wildlife off the Interstate.
  • Break-in access requires prior approval from the ITD Board and FHWA.

Incentives/disincentives

  • Use incentives/disincentives, A-plus-B bidding, lane rentals, etc.
  • Include language in the contract to alleviate issues regarding lane impacts during construction.
 

Milestones

  • Create aggressive milestones that the contractor would be required to follow.
  • Incorporate the milestones into the contract language.
  • May scare off contractors.

Contract package

  • Try to get out-of-State and local contractors to bid on the project as one large package.
  • Nearby States also have large projects underway – large contractors could be tied up with these projects.

Utility issues

  • Address utility issues early in the process. Relocate utilities prior to construction.
  • Include utility relocation as part of the contract work, to be cost shared between ITD and the utility company.
  • Using utility relocates as part of the contract will increase the number of owners the contractor will be involved with.

Alternative construction materials for concrete block sound walls

  • Consider post- and pre-cast panel sound walls, which are quicker to construct than block walls.
 

Constructability reviews

  • Conduct constructability reviews prior to bidding a project.
  • At 60 percent design, meet with contractors to review the plans; use open invitation to State-approved contractors.
  • Meet with contractors individually rather than with multiple contractors at once; contractors tend to open up more when approached one-on-one.

Environmental process

  • Complete environmental mitigation and acquire permits for the west end of project (Orchard to Gowen) as soon as possible.
 

State-owned material sources

  • Use State-owned material sources.
  • This may open the door for out-of-State contractors.
  • Lack of State-owned sources in the area; sources could be depleted.

ROW acquisition

  • Acquire ROW as early as possible.
  • Buy out the railroad ROW.
 
<< Previous Contents Next >>

Events

Contact

Chris Schneider
Office of Asset Management
202-493-0551
E-mail Chris

Joe Huerta
Resource Center (Baltimore)
410-962-2298
E-mail Joe

 
 
This page last modified on 07/12/07
 

FHWA
United States Department of Transportation - Federal Highway Administration