Acceleration of bridge construction |
- Accelerate bridge construction to alleviate
bottlenecks during construction.
- Standardize
bridge construction; retain existing foundations,
abutments and piers, if possible; allow complete
bridge closure for up to one month and
implement incentive for using less closure time;
remove entire span (deck, girders, diaphragms)
using SPMTs and demolish bridge on ground;
build new structure in median or nearby staging
area; slide new structure into place with SPMTs.
|
- Traffic may slow or be distracted by
construction in median.
- SPMT availability may
be limited.
|
Separate contracts for roadwork and structure work |
- Package four or more structures into one contract
to accelerate construction; require staged
construction of structures.
|
|
I-84 structures |
- Make all I-84 structures overpasses and depress
local streets to at-grade.
- To construct the
overpasses, utilize the outside shoulders to shift
I-84 traffic away from the median, and use the
median area to construct the overpass.
- Build the
overpass up to the adjacent transverse local street
underpass; shut down the transverse street on a
weekend; demolish the existing underpass; and
build the last span of the I-84 overpass.
|
- Overpasses could be expanded in the future
much more easily than underpasses.
- This
would alleviate clearance issues for over-height
vehicles.
- This could create drainage issues on
certain areas of the Interstate.
|
Pre-cast deck panels on cast-in-place bridges |
- Consider using pre-cast deck panels for cast-in-place
bridges.
- Place a four-inch overlay on precast
deck panels.
- Use fiber board in between
pre-cast panel and girder to accommodate the
grade/slope of the bridge.
|
|
Southern Interstate loop |
- Build southern Interstate loop to handle local
traffic volumes.
|
- Local road network has very little capacity; area
around the Interstate loop could eventually
develop and create more traffic on the loop.
|
Different paving methods |
- Try an un-bonded concrete overlay with an asphalt
leveling course to improve the existing concrete
pavement in lieu of crack and seat.
- Mill out four
to five inches of existing asphalt pavement and
replace with six to eight inches of Superpave.
|
- Texas and Oklahoma have had good luck with
un-bonded concrete overlay.
|
Clearance changes |
- Raise (or jack) the existing underpasses to increase
bridge clearance.
- May be easier to raise the
smaller bridges than excavate the area below the
bridges to get clearance.
|
- This would not improve Interstate lane capacity.
|
New drainage configurations |
- Try to send water to outside the shoulder;
consider using a mainline storm water system in
the median.
|
- High ground water in the area; time restrictions
on construction due to the irrigation season.
- Local farmers use flood irrigation, and local
irrigation districts do not want water run-off
from the highway.
|
Staging areas |
- Allow staging area adjacent to Interstate.
- Allow
contractor to "break the fence" (put a break in the
access control) so that the contractor could have
direct access to the Interstate.
- The staging area
could be fenced to keep wildlife off the Interstate.
|
- Break-in access requires prior approval from the
ITD Board and FHWA.
|
Incentives/disincentives |
- Use incentives/disincentives, A-plus-B bidding,
lane rentals, etc.
- Include language in the contract
to alleviate issues regarding lane impacts during
construction.
|
|
Milestones |
- Create aggressive milestones that the contractor
would be required to follow.
- Incorporate the
milestones into the contract language.
|
- May scare off contractors.
|
Contract package |
- Try to get out-of-State and local contractors to bid
on the project as one large package.
|
- Nearby States also have large projects
underway – large contractors could be tied up
with these projects.
|
Utility issues |
- Address utility issues early in the process.
Relocate utilities prior to construction.
- Include
utility relocation as part of the contract work,
to be cost shared between ITD and the utility
company.
|
- Using utility relocates as part of the contract
will increase the number of owners the
contractor will be involved with.
|
Alternative construction materials for concrete
block sound walls |
- Consider post- and pre-cast panel sound walls,
which are quicker to construct than block walls.
|
|
Constructability reviews |
- Conduct constructability reviews prior to
bidding a project.
- At 60 percent design, meet
with contractors to review the plans; use open
invitation to State-approved contractors.
|
- Meet with contractors individually rather than
with multiple contractors at once; contractors
tend to open up more when approached one-on-one.
|
Environmental process |
- Complete environmental mitigation and acquire
permits for the west end of project (Orchard to
Gowen) as soon as possible.
|
|
State-owned material sources |
- Use State-owned material sources.
- This may open
the door for out-of-State contractors.
|
- Lack of State-owned sources in the area;
sources could be depleted.
|
ROW acquisition |
- Acquire ROW as early as possible.
- Buy out the
railroad ROW.
|
|