Financing: bonds |
- In order to reduce interest expense, consider:
- Using bond anticipation notes (BANs).
- Combining variable rate with fixed rate
debt.
|
- Long-term interest rate risk. Generally will
result in lower interest costs.
|
Generating additional revenue |
- Establish a State Infrastructure Bank (SIB) to operate
as a revolving fund for the State to make loans to
Cities/Counties.
- Consider high occupancy toll (HOT) lanes.
- Require developers to pay for some of these
improvements through development impact fees
and/or special assessments.
|
- Provides flexibility with loans.
- Local option
taxes could be imposed to repay SIB loans.
- Technology of enforcement is a challenge.
- Determine whether use of toll revenue would
be restricted to I-84 corridor.
|
Multi year financing plan
(priority 4) |
- Note that other State legislatures have approved
multi year GARVEE bonds to finance corridor
programs.
|
- Requires legislative approval.
- Multi year
financing increases flexibility and expedites
construction delivery.
|
Stewardship agreement |
- Develop a separate agreement to allow
concurrent PS&E and ROW obligational authority
(advance construct).
|
- Determine if stewardship agreement
with division can be revised or if Special
Experimental Project (SEP) 15 is necessary.
|
Contract sizing |
- Consider size of contract to facilitate speed of
delivery.
|
- Larger contracts may facilitate earlier delivery.
- Local contractors' capabilities need to be
considered.
|
Phased early work opportunities
(priority 3) |
- Look at phasing sound walls, utilities, grading
and drainage.
- Consider job order contracting
(pre-procurement of materials and equipment).
|
- Address the early critical path items in
accordance with cash flow.
- Provides
opportunity for smaller contracts.
- Enables
award before design is 100 percent complete.
- Provides disadvantaged business enterprise
(DBE) opportunities and small business
opportunities.
|
Incentive contracting |
- Consider A-plus-B bidding, multiple milestone
incentives (i.e., travel time, worker and vehicular
safety, incident response, etc.) and a "no excuse"
bonus (priority 2).
|
- Do a cost-benefit analysis.
- Note incentives
may be difficult to administer because of
acceleration of the job.
- Promote public
relations and highway user benefits.
- Research
other States' experiences, i.e., Florida, Texas,
Indiana, etc.
|
Contractor involvement in preconstruction
activities |
- Do constructability reviews.
- Hold mandatory pre-bid
meetings to explain the project and speed up
the production process.
- Conduct a VE workshop
prior to advertisement.
|
- Determine if contractor participation
in constructability reviews will preclude
participation in the bidding process.
- Obtain
contractor input on production sequencing,
phasing and opportunities for accelerating
construction.
|
Special prequalification |
- Check contractor capabilities to deliver the project
in an accelerated construction environment in
advance of bid.
- Review equipment, materials,
safety record, financial strength, etc.
|
- Ensures appropriate bidders for this type of
project.
- Need to coordinate with the AGC.
|
Going to bid prior to final design
(non D-B) |
- Advertise initial bid package before final
design and select contractor based on low bid.
- Contractor then provides input on completion of
design.
|
- May be prohibited by permitting restrictions.
- List 100 percent packages on major bid items,
and put estimates for design details that are
not complete. (Use contingency amounts.)
- Get to finalize the design with the contractor
building the project.
- Need to include a
quantity variation clause in the contract.
- Can
handle bid adjustments using bid escrow.
|
Design standardization and compatibility |
- Utilize standard designs for all bridges.
- Would
cut down the proposal, design, fabrication and
erection time.
|
- Depict snappy logos on the bridges.
|
Performance-based contracting |
- Consider performance-based contracts for
construction of the sound walls, MSE walls and
canal structures as well as for MOT.
|
- Implement with measurable criteria.
- Give
the contractor flexibility to meet given
performance standards for MOT.
|
D-B and best value
(priority 1) |
- Use this: it's a proven strategy for project
acceleration.
|
- Requires legislative approval.
- Could set up
trial project before seeking blanket legislation.
- CIP could initiate discussions with legislature
for trial project.
|
Contract administration |
- Have program manager handle construction
oversight and coordinate corridor-wide contracts.
- Implement change management structure to fit
the project.
|
- Need ITD personnel to be engaged in project
decision-making.
- Need specific timelines for
decisions, design reviews, etc.
|
QC/QA, material testing requirements |
- Streamline testing requirements.
|
- Requires further study by technical teams.
|