Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Construction

ACTT

<< Previous Contents Next >>

ACTT Workshop: Idaho
The I-84 Corridor Improvements Project

Appendix C Innovative Contracting Skill Set

Skill Set Roster: Jim Phillips, Facilitator
Erika Stoddard
Craig Actis
Thomas W. Pelnik III
Sidney Scott
Frederick Werner
Damon Allen
Pam Golden
Larry Boyd

Idea Name Detailed Description Implementation Details (barriers, skills set coordination, etc.)

Financing: bonds

  • In order to reduce interest expense, consider:
    1. Using bond anticipation notes (BANs).
    2. Combining variable rate with fixed rate debt.
  • Long-term interest rate risk. Generally will result in lower interest costs.

Generating additional revenue

  • Establish a State Infrastructure Bank (SIB) to operate as a revolving fund for the State to make loans to Cities/Counties.
  • Consider high occupancy toll (HOT) lanes.
  • Require developers to pay for some of these improvements through development impact fees and/or special assessments.
  • Provides flexibility with loans.
  • Local option taxes could be imposed to repay SIB loans.
  • Technology of enforcement is a challenge.
  • Determine whether use of toll revenue would be restricted to I-84 corridor.

Multi year financing plan (priority 4)

  • Note that other State legislatures have approved multi year GARVEE bonds to finance corridor programs.
  • Requires legislative approval.
  • Multi year financing increases flexibility and expedites construction delivery.

Stewardship agreement

  • Develop a separate agreement to allow concurrent PS&E and ROW obligational authority (advance construct).
  • Determine if stewardship agreement with division can be revised or if Special Experimental Project (SEP) 15 is necessary.

Contract sizing

  • Consider size of contract to facilitate speed of delivery.
  • Larger contracts may facilitate earlier delivery.
  • Local contractors' capabilities need to be considered.

Phased early work opportunities (priority 3)

  • Look at phasing sound walls, utilities, grading and drainage.
  • Consider job order contracting (pre-procurement of materials and equipment).
  • Address the early critical path items in accordance with cash flow.
  • Provides opportunity for smaller contracts.
  • Enables award before design is 100 percent complete.
  • Provides disadvantaged business enterprise (DBE) opportunities and small business opportunities.

Incentive contracting

  • Consider A-plus-B bidding, multiple milestone incentives (i.e., travel time, worker and vehicular safety, incident response, etc.) and a "no excuse" bonus (priority 2).
  • Do a cost-benefit analysis.
  • Note incentives may be difficult to administer because of acceleration of the job.
  • Promote public relations and highway user benefits.
  • Research other States' experiences, i.e., Florida, Texas, Indiana, etc.

Contractor involvement in preconstruction activities

  • Do constructability reviews.
  • Hold mandatory pre-bid meetings to explain the project and speed up the production process.
  • Conduct a VE workshop prior to advertisement.
  • Determine if contractor participation in constructability reviews will preclude participation in the bidding process.
  • Obtain contractor input on production sequencing, phasing and opportunities for accelerating construction.

Special prequalification

  • Check contractor capabilities to deliver the project in an accelerated construction environment in advance of bid.
  • Review equipment, materials, safety record, financial strength, etc.
  • Ensures appropriate bidders for this type of project.
  • Need to coordinate with the AGC.

Going to bid prior to final design (non D-B)

  • Advertise initial bid package before final design and select contractor based on low bid.
  • Contractor then provides input on completion of design.
  • May be prohibited by permitting restrictions.
  • List 100 percent packages on major bid items, and put estimates for design details that are not complete. (Use contingency amounts.)
  • Get to finalize the design with the contractor building the project.
  • Need to include a quantity variation clause in the contract.
  • Can handle bid adjustments using bid escrow.

Design standardization and compatibility

  • Utilize standard designs for all bridges.
  • Would cut down the proposal, design, fabrication and erection time.
  • Depict snappy logos on the bridges.

Performance-based contracting

  • Consider performance-based contracts for construction of the sound walls, MSE walls and canal structures as well as for MOT.
  • Implement with measurable criteria.
  • Give the contractor flexibility to meet given performance standards for MOT.

D-B and best value (priority 1)

  • Use this: it's a proven strategy for project acceleration.
  • Requires legislative approval.
  • Could set up trial project before seeking blanket legislation.
  • CIP could initiate discussions with legislature for trial project.

Contract administration

  • Have program manager handle construction oversight and coordinate corridor-wide contracts.
  • Implement change management structure to fit the project.
  • Need ITD personnel to be engaged in project decision-making.
  • Need specific timelines for decisions, design reviews, etc.

QC/QA, material testing requirements

  • Streamline testing requirements.
  • Requires further study by technical teams.
<< Previous Contents Next >>

Events

Contact

Chris Schneider
Office of Asset Management
202-493-0551
E-mail Chris

Joe Huerta
Resource Center (Baltimore)
410-962-2298
E-mail Joe

 
 
This page last modified on 07/12/07
 

FHWA
United States Department of Transportation - Federal Highway Administration