2007 ABC Workshop Follow up
Archived: Appendix E - Brainstorm Ideas: Seismic Connection Detailing Focus
| CATEGORY/NO. | RAW VOTE TALLY | CATEGORY | BREAKOUT GROUP ASSIGNMENT |
|---|---|---|---|
| B1 | 1 | --- | --- |
| B2 | 6 | A | 1 |
| B31 | 2 | D | 1 |
| B4 | 2 | D | 3 |
| B5 | 2 | D | 2 |
| B6 | 5 | B | 3 |
| C1 | 8 | A | 2 |
| C2 | 0 | --- | --- |
| C3 | 5 | B | 4 |
| C4 | 4 | C | 2 |
| C5 | 2 | D | 4 |
| C6 | 5 | B | 1 |
| C7 | 0 | --- | --- |
| C8 | 4 | C | 1 |
| C9 | 0 | --- | --- |
| C10 | 2 | D | 1 |
| D2 | 5 | B | 2 |
| E13 | 2 | D | 2 |
| F1/F2² | 15 | A | 3 |
| F3 | 5 | B | 3 |
| F6 | 2 | D | 3 |
| G1 | 5 | B | 4 |
| G2 | 3 | C | 4 |
| H3 | 1 | --- | --- |
| H6 | 6 | A | 4 |
- ¹ No action; pending publication of PCI seismic report.
- ² Received the most votes, thereby rising to the top of the list.