Patrick DeCorla-Souza
P3 Program Manager
Office of Innovative Program Delivery
Wim Verdouw
Financial Modeler
IMG/Rebel
Part 1 Recap of Value for Money (VfM) Assessment
Part 2 P3-VALUE 2.1 Enhancements
Part 3 Illustrative Application VfM Assessment
1. Planning - High level screening for financial viability and VfM
2. Project Development - More detailed quantitative assessment of financial viability and VfM
3. Procurement - Refine financial and VfM analyses as cost and revenue estimates are refined and bids are received
Please stand by while we open the P3-VALUE 2.1 tool to show the enhanced features
Project Delivery Inputs | PSC | P3 | |
---|---|---|---|
Facility tolled? | TRUE | ||
P3 delivery model | ///////////////////////// | Toll concession | |
Project Timing Inputs | PSC | P3 | |
Pre-construction start year | 2018 | 2018 | |
Pre-construction duration (in years) | 2 years | 2 years | |
Construction duration (in years) | 4 years | 3 years | |
Operations duration (in years) | 40 years | 41 years | |
Delayed PSC pre-construction start year | 2023 | ||
Capital Cost Inputs (Risk Adjusted)* | PSC | P3* | |
Public procurement cost (in million $) | $5.0M | $10.0M | 0% |
Private procurement cost (in million $) | $5.0M | $10.0M | 100% |
Pre-construction cost (in million $) | $25.0M | $22.5M | 100% |
Construction cost (in million $) | $400.0M | $367.5M | 100% |
Financing Inputs | PSC | P3 |
---|---|---|
Subsidy/milestone payment (in million $) | $100.0M | $100.0M |
Cost of equity (in percent) | ////////////////////// | 12.00% |
Gearing (in percent) | ////////////////////// | 75.00% |
Debt maturity (from start construction, in years) | 35 years | 30 years |
Debt interest rate (in percent) | 4.00% | 6.00% |
Equity bridge loan interest rate (in percent) | ////////////////////// | 6.00% |
Minimum required DSCR (multiple of debt service) | 1.30x | 1.30x |
Interest rate on reserves (in percent) | 2.00% | 2.00% |
Debt issuance/arrangement fee (in percent) | 1.00% | 1.00% |
Financing Inputs | PSC | P3 |
---|---|---|
Subsidy/milestone payment (in million $) | $100.0M | $100.0M |
Cost of equity (in percent) | ////////////////////// | 10.00% |
Gearing (in percent) | ////////////////////// | 85.00% |
Debt maturity (from start construction, in years) | 35 years | 30 years |
Debt interest rate (in percent) | 4.00% | 6.00% |
Equity bridge loan interest rate (in percent) | ////////////////////// | 6.00% |
Minimum required DSCR (multiple of debt service) | 1.30x | 1.20x |
Interest rate on reserves (in percent) | 2.00% | 2.00% |
Debt issuance/arrangement fee (in percent) | 1.00% | 1.00% |
Lifecycle Performance Risk & Revenue Uncertainty Adjustment Inputs | |
---|---|
Lifecycle performance risk calculation method (see options below) | Option 1 |
Lifecycle performance risk aggregate premium (in million $, option 2 only) | $400.0M |
Revenue uncertainty adjustment calculation method (see options below) | Option 1 |
Delta between availability payment & toll concession WACC (in percent, option 1 only) | 1.60% |
Revenue uncertainty adjustment (% of toll revenue collection, option 2 only) | 28.00% |
Guidance for Valuation Options | |
Option 1: WACC-based risk premium is calculated to determine the value of lifecycle performance risks/revenue uncertainty adjustment | |
Option 2: User to provide a risk premium for the value of lifecycle performance risks/revenue uncertainty adjustment | |
Option 3: Lifecycle performance risks/revenue uncertainty adjustment are ignored in the analysis |
Taxation Inputs | State | Federal |
---|---|---|
Tax rate (in percent) | 10.00% | 25.00% |
Tax considered for competitive neutrality adjustment? | TRUE | TRUE |
Competitive Neutrality Adjustment Inputs | ||
Value of construction self-insurance (% of transferred construction costs) | 0.00% | |
Value of O&M and major maintenance self-insurance (% of transferred costs) | 0.00% | |
Value of credit subsidy or tax benefits under PSC delivery (in million $) | $0.0M | |
Value of credit subsidy or tax benefits under P3 delivery (in million $) | $0.0M |
REVENUES & COSTS (NPV @ 4.00%, 2018) | PSC | P3 | ||
---|---|---|---|---|
Toll revenues | ||||
Toll revenues to Agency | $784M | - | ||
Toll revenues to P3 Developer | //////////// | $806M | ||
Toll revenues subtotal | $784M | $806M | ||
Cost component 1a: Total/transferred base costs (including risks transferred to subcontractors) | ||||
Total (PSC)/Transferred (P3) pre-construction (including private procurement costs) | ($28M) | ($30M) | ||
Total (PSC)/Transferred (P3) construction costs | ($374M) | ($347M) | ||
Total (PSC)/Transferred (P3) O&M costs (including private procurement costs) | ($129M) | ($120M) | ||
Base cost subtotal 1a | ($531M) | ($497M) | ||
Cost component 1b: Retained base costs (P3 only) | ||||
Retained pre-construction costs | //////////// | - | ||
Retained construction costs | //////////// | - | ||
Retained O&M costs (including P3 oversight costs) | //////////// | - | ||
Retained base cost subtotal 1b | - | - | ||
Base costs subtotal (1a + 1b) | ($531M) | ($497M) | ||
Cost component 2: Financing costs | ||||
Financing cost | ($3M) | ($397M) | ||
Financing cost subtotal | ($3M) | ($397M) | ||
P3 Shadow Bid (Revenues to P3 minus cost components 1a & 2) | N.A. | ($88M) | Shadow Bid |
REVENUES & COSTS (NPV @ 4.00%, 2018) | PSC | P3 | ||
---|---|---|---|---|
Cost component 3: Long-term risks retained by Agency | ||||
Calculated market value of lifecycle performance risk | ($105M) | //////////// | ||
Calculated market value of revenue uncertainty adjustment | ($162M) | - | ||
Long-term risks retained by Agency subtotal | ($267M) | - | ||
Cost component 4: Ancillary costs & cost savings | ||||
Procurement & oversight cost in the design-build phase | ($5M) | ($9M) | ||
No Build cost savings | $250M | $259M | ||
Ancillary costs & cost savings subtotal | $245M | $250M | ||
Cost component 5: Competitive neutrality adjustment | ||||
State taxes | //////////// | $36M | ||
Federal taxes | //////////// | $81M | ||
Value of public agency self-insurance | //////////// | - | ||
Net credit subsidy adjustment (NPV of PSC credit subsidy - NPV of P3 credit subsidy) | //////////// | - | ||
Competitive neutrality adjustment subtotal | - | $116M | ||
Total net value after revenue | $228M | $278M | VfM Comparison |
|
Note: Calculated market value of lifecycle performance risk | ($105M) | //////////// | ||
Note: Calculated market value of revenue uncertainty adjustment | ($162M) | //////////// | ||
Social welfare benefits due to P3 delivery (excluding No Build cost savings) | $166M | |||
Social welfare benefits due to project acceleration | $431M |
REVENUES & COSTS (NPV @ 4.00%, 2018) | PSC | P3 | ||
---|---|---|---|---|
Toll revenues | ||||
Toll revenues to Agency | $784M | $806M | Revenue risk borne by Agency |
|
Toll revenues to P3 Developer | //////////// | - | ||
Toll revenues subtotal | $784M | $806M | ||
Cost component 1a: Total/transferred base costs (including risks transferred to subcontractors) | ||||
Total (PSC)/Transferred (P3) pre-construction (including private procurement costs) | ($28M) | ($30M) | ||
Total (PSC)/Transferred (P3) construction costs | ($374M) | ($347M) | ||
Total (PSC)/Transferred (P3) O&M costs (including private procurement costs) | ($129M) | ($120M) | ||
Base cost subtotal 1a | ($531M) | ($497M) | ||
Cost component 1b: Retained base costs (P3 only) | ||||
Retained pre-construction costs | //////////// | - | ||
Retained construction costs | //////////// | - | ||
Retained O&M costs (including P3 oversight costs) | //////////// | - | ||
Retained base cost subtotal 1b | - | - | ||
Base costs subtotal (1a + 1b) | ($531M) | ($497M) | ||
Cost component 2: Financing costs | ||||
Financing cost | ($3M) | ($180M) | ||
Financing cost subtotal | ($3M) | ($180M) | ||
P3 Shadow Bid (Revenues to P3 minus cost components 1a & 2) | N.A. | ($677M) | Shadow Bid |
REVENUES & COSTS (NPV @ 4.00%, 2018) | PSC | P3 | ||
---|---|---|---|---|
Cost component 3: Long-term risks retained by Agency | ||||
Calculated market value of lifecycle performance risk | ($142M) | //////////// | ||
Calculated market value of revenue uncertainty adjustment | ($184M) | ($190M) | Retained revenue risk |
|
Long-term risks retained by Agency subtotal | ($326M) | ($190M) | ||
Cost component 4: Ancillary costs & cost savings | ||||
Procurement & oversight cost in the design-build phase | ($5M) | ($9M) | ||
No Build cost savings | $250M | $259M | ||
Ancillary costs & cost savings subtotal | $245M | $250M | ||
Cost component 5: Competitive neutrality adjustment | ||||
State taxes | //////////// | $15M | ||
Federal taxes | //////////// | $34M | ||
Value of public agency self-insurance | //////////// | - | ||
Net credit subsidy adjustment (NPV of PSC credit subsidy - NPV of P3 credit subsidy) | //////////// | - | ||
Competitive neutrality adjustment subtotal | - | $49M | ||
Total net value after revenue | $169M | $239M | VfM Comparison |
|
Note: Calculated market value of lifecycle performance risk | ($142M) | //////////// | ||
Note: Calculated market value of revenue uncertainty adjustment | ($184M) | //////////// | ||
Social welfare benefits due to P3 delivery (excluding No Build cost savings) | $166M | |||
Social welfare benefits due to project acceleration | $424M |
P3 Program Manager
USDOT Build America Bureau
& FHWA Center for Innovative Finance Support
(202) 366-4076
Patrick.DeCorla-Souza@dot.gov