THIS EARLY DEVELOPMENT AGREEMENT ("EDA" or "Agreement"), made and entered into this 9th day of December 2014, by and between the COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (hereinafter "PennDOT') and the FEDERAL HIGHWAY ADMINISTRATION, UNITED STATES DEPARTMENT OF TRANSPORTATION, (hereinafter "FHWA"):
WITNESSETH
WHEREAS, on October 6, 2004, FHWA announced, in the Federal Register at 60 Fed. Reg. 59983, a new special experimental project to explore alternative and innovative approaches to the overall project development process known collectively as Special Experimental Project Number 15 ("SEP-15") pursuant to the authority in 23 U.S.C. § 502(b)(l)(B);
WHEREAS, SEP-15 is designed to permit tests and experimentation in the project development process for title 23 projects that are specifically aimed at attracting private investment and lead to increased project management flexibility, more innovation, improved efficiency, timely project implementation, and new revenue streams;
WHEREAS, under SEP-15, in order to facilitate tests and experimentation in the project development process, FHWA may grant modifications or deviations from the current requirements contained in title 23 of the United States Code and title 23 of the Code of Federal Regulations;
WHEREAS, on July 15, 2014, PennDOT, submitted an application under SEP-15 requesting a deviation from 23 CFR 636.109(b)(6) and 23 CFR 636.109(b)(7) for PennDOT's Rapid Bridge Replacement Project ("the Project") in order to allow a private partner to prepare draft environmental documentation for PennDOT's review, which currently is prohibited under FHWA's Design-Build Contracting regulations;
WHEREAS, the Project is a key component of PennDOT's effort to address the Commonwealth's systemic backlog of almost 4,800 structurally deficient bridges and to save costs on design, permitting, construction and ultimately maintenance. PennDOT intends to select a private partner (Development Entity or DE) to design, build, finance, and maintain 558 bridges ("Replacement Bridges") throughout the Commonwealth of Pennsylvania using newly granted Commonwealth authority under Pennsylvania's Public-Private Transportation Partnership Law, 74 Pa. C.S. §§91101-91124;
WHEREAS, if PennDOT were to replace each of these bridges individually, using its traditional procurement schedule, PennDOT estimates that the process could take 10 - 15 years; however, bringing the resources of a private sector partner to bear, PennDOT estimates it will be able to deliver the replacement of 99 percent of the bridges in the Project in just 42 months;
WHEREAS the Replacement Bridges included in the Project are categorized as either (1) Early Completion Bridges ("ECB"), which are the replacement bridges for which PennDOT will obtain all NEPA related approvals and applicable environmental permits, or (2) Remaining Eligible Bridges ("REB") as defined in section 2.5 of this EDA, and
WHEREAS, on July 31, 2014, FHWA accepted PennDOT's SEP-15 application for the Project; and
WHEREAS, under SEP-15, fill EDA between PennDOT and FHWA is required in order to specify the conditions relating to the modifications or deviations from Federal requirements that are granted for the Project as well as to identify the reporting requirements that will be used to evaluate the extent to which the modifications or deviations contributed to the success of the process.
NOW THEREFORE, PennDOT and FHWA hereby agree as follows:
The DE will conduct environmental studies, prepare environmental documentation, and complete the required preliminary engineering for the 470 REB which are part of the Project and which are covered by a Level 1 or Level 2 categorical exclusion (CE). The DE will obtain the necessary permits and approvals for each REB included in the Project. PennDOT conducted initial screenings and scoping field reviews to make sure that the bridges selected for this Project are eligible for a CE under the Bridge and Roadway Programmatic Agreement (BRPA) between PennDOT and FHWA Pennsylvania Division, a Level 1 CE or a Level 2 CE. This scoping included a determination that an environmental assessment or an environmental impact statement is not required under applicable law.
This EDA is intended to identify and establish the parameters of the modifications or deviations from title 23 Code of Federal Regulations for the Project, which shall be hereinafter referred to as the "experimental features." Nothing in this EDA shall be construed as a relinquishment of any Federal oversight or stewardship responsibility.
"Applicant" means PennDOT.
"DE" means the Development Entity (private sector partner) that is awarded the contract for the Project.
"NEPA" means the National Environmental Policy Act of 1969, codified at 42 U.S.C. §§ 4321, et seq.
"PPA" means the Public Private Partnership Agreement for the Project executed by PennDOT and the DE.
"Remaining Eligible Bridges" means the approximately 470 replacement bridges for which the DE must obtain the environmental approvals from PennDOT or FHWA along with any applicable permits through the permitting agencies.
"Section 106" means Section 106 of the National Historic Preservation Act of 1966, as amended, 16 U.S.C. §470f.
"Section 4(f)" means Section 4(f) of the U.S. Department of Transportation Act of 1966, as amended, 49 U.S.C §1653f
A. All Federal laws, rules and regulations shall be applicable to any project using Federal funds, including, but not limited to, the requirements set fo1ih in titles 23 and 49 of the United States Code, and titles 23 and 49 of the Code of Federal Regulations, the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended, 42 U.S.C. §§ 4601 to 4655, and the FHWA's implementing regulations found at 49 C.F.R. Part 24, and the NEPA, with respect to any related facility, except as otherwise specified herein.
B. With respect to title 23 of the United States Code and title 23 of the Code of Federal Regulations, PennDOT may apply to the REBs included in the Project the SEP-15 experimental features described in Section 4 of this EDA. PennDOT's use of such experimental features shall be deemed to be in full compliance with Federal law, rules and regulations.
FHWA's approval of the SEP-15 experimental features may be withdrawn at any time by the FHWA if the FHWA determines that the experimental features are not in the public interest. Prior to any such withdrawal, the FHWA will issue a written notice to PennDOT describing the FHWA's concerns and give PennDOT a reasonable period of time to address the FHWA's concerns. However, during such period of time, no further work shall be conducted based on the approval at issue until such time as the FHWA determines that PennDOT has fully addressed the FHWA' s concerns. Upon withdrawal of approval of an experimental feature, the applicable requirements of 23 CFR 636.109(b)(6) and/or 636.109(b)(7) shall immediately apply. Any withdrawal of approval under this EDA shall apply only to bridge replacement projects that have not received final NEPA approval from FHWA/PennDOT as of the date of the FHWA notice. With respect to prior final FHWA/PennDOT NEPA decisions on replacement bridges subject to this EDA, the withdrawal of approval will not cause the prior final NEPA decisions to become invalid or require modification of those decisions based on non-compliance with sections 636.109(b)(6) and/or 636.109(b)(7).
However, FHWA may identify corrective action(s) that must be taken on such replacement bridge projects as a condition of any required FHWA approval and/or Federal-aid participation. Nothing in this EDA permits deviation from applicable requirements of title 23 of the United States Code and title 23 of the Code of Federal Regulations except as specified in Section 4, and nothing in this paragraph shall prevent the FHWA from performing any of its obligations or regulatory functions pursuant to applicable law, or undertaking any lawful action or remedy to enforce applicable law.
As provided in 23 C.F.R. § 1.5, PennDOT shall furnish, or make available, to the FHWA such information as the FHWA deems necessary to administer the Federal-aid program in connection with the Project and ensure compliance with the applicable Federal requirements. PennDOT must make available to the FHWA, upon reasonable notice, any documents and communications, in whatever format or media, that is pertinent to the Project or to performance of this EDA. This provision applies to documents and communications of both PennDOT and the DE. PennDOT is responsible for ensuring its contract with the DE contains appropriate provisions that provide PennDOT with the necessary access to the DE's documents and communications.
Except as otherwise specified herein, this EDA supersedes the July 15, 2014, PennDOT SEP-15 application and the FHWA July 31, 2014, SEP-15 acceptance letter. The July 15, 2014, PennDOT SEP-15 application and the July 31, 2014, FHWA SEP-15 acceptance letter are attached to this EDA as Exhibits A and B, and may be used for historical and interpretive purposes, provided that this EDA shall be given effect to the extent there is any conflict. Any modifications to this EDA shall supersede any conflicting provisions of the July 15, 2014, SEP-15 application, the July 3l, 2014, SEP-15 acceptance letter and any prior modifications to this EDA.
A. FHWA acknowledges and agrees to PennDOT's deviation from 23 CFR 636.109(b)(6) and 23 CFR 636.109(b)(7) for the Project, as provided in the FHWA July 31, 2014. SEP-15 acceptance letter, by allowing the DE to be responsible for preparing the environmental supporting documentation and draft decision documents, and allowing the DE to select and retain exclusive control over the consultant(s) that perform(s) environmental studies and prepare(s) the environmental documents.
B. The purposes of 23 CFR 636.109(b)(6) and 23 CFR 636.109(b)(7), which prohibit a design-builder's involvement in the NEPA decision making process, are to: (1) Insulate against conflicts of interests; (2) Ensure the integrity and objectivity of the NEPA process; and (3) Protect the public's faith in the integrity of the NEPA process.
C. In order to ensure that the purposes and requirements of 23 CFR 636.109(b)(6) and 23 CFR 636.109(b)(7), as listed in 4.1.B are protected, the following conditions must be met:
(i) DE NEPA Documentation. For each bridge, the DE will prepare and provide to PennDOT the appropriate field data, impact analyses (if required for the proposed CE), and draft NEPA documentation. The DE will use PennDOT's standard systems such as the CE Expert System, Project Path, and the Environmental Commitments and Mitigation Tracking System for the completion of the NEPA documents and to track the completion of the mitigation. These systems have a formal quality control and approval process by PennDOT.
(ii) Section 106.
(iii) Section 4(f). For Section 4(t) resources, PennDOT and/or FHWA will review and must approve any proposed 4(f) determinations including applicable checklists (i.e., Programmatic, De Minimis) and Individual Section 4(f) Evaluations.
(iv) Public Involvement. A PennDOT representative, independent of the DE, will attend all public meetings held for the individual bridges to ensure that the proceedings are properly administered and documented consistent with PennDOT's public involvement plan approved by FHWA.
(v) PennDOT NEPA Reviews. PennDOT will require the DE, in accordance with the PPA, to submit each CE or other NEPA documentation relating to CE determinations, to PennDOT for its substantive review and independent evaluation. PennDOT will evaluate the data, analyses, and documentation necessary for the NEPA decision. PennDOT also will compare the impacts identified by the DE to the results of the scoping-phase field screening PennDOT did for the bridge. PennDOT will use the standard systems such as the CE Expert System, Project Path, and the Environmental Commitments and Mitigation Tracking System for purposes of reviewing and approving the NEPA documentation and assuring the completion of required mitigation.
(vi) PennDOT/FHWA NEPA Approval. FHWA and/or PennDOT will make the final NEPA decisions in accordance with FHWA's NEPA delegation procedures and after independently evaluating the information and making independent judgments about the potential project impacts. The FHWA will provide oversight. The FHWA and PennDOT will take full responsibility for the scope and contents of the NEPA documents.
(vii) No Final Design Prior to NEPA Approval. The DE is not permitted to commence final design activities - e.g., right-of-way acquisition - until after receiving NEPA approval (which is also needed to receive Design Field View approval from PennDOT to move into Final Design).
(viii) Environmental Mitigation as a Compensation Event. PennDOT will pay for any NEPA mitigation not already pre-defined in the DE's bid proposal. This means that the DE will receive no financial benefit and bear no financial risk not already priced into its proposal related to environmental mitigation or project delays resulting from environmental findings in the NEPA process. PennDOT will compensate the DE separately for the cost of NEPA-related environmental mitigation actions. This includes final design and construction tasks such as wetland replacement, Phase III Archaeological data recovery excavations, associated interpretive materials, recordation of the historic bridge and associated historic district, and context sensitive design elements.
(ix) Elimination of Pecuniary Harm to the DE for NEPA-related decisions by the relevant agencies.
The purpose of this section is to describe the evaluation criteria that PennDOT shall use in evaluating the Experimental Features.
PennDOT will evaluate the following to measure time savings:
A. Procurement Time: FHWA and PennDOT agree there is no valid quantitative method to evaluate the anticipated procurement time and cost savings for the Project. Therefore, PennDOT will prepare a qualitative evaluation of the estimated cost and time savings for the REB compared to the delivery of the REB using PennDOT's traditional procurement process.
B. Costs and Time for Environmental Work: For each REB, PennDOT will determine the costs and time required (person hours for the work, and duration of the activities) for the DE to carry out the activities listed below in 5.2 B(i) through B(iv), and assess cost-savings and time-savings by comparing to a baseline consisting of PennDOT's active non-P3 projects and the ECBs against the cost to PennDOT for either: (a) using its staff to complete NEPA studies and NEPA documentation on a Bridge with similar environmental characteristics; or (b) selecting and contracting with a consultant to complete NEPA studies and NEPA documentation on a Replacement Bridge with similar environmental characteristics.
C. Cost of Environmental Mitigation: PennDOT will compare actual mitigation costs for the REBs to PennDOT non P3-projects of similar environmental characteristics receiving permits and approvals and the ECBs. In addition, PennDOT will interview the DE for the purpose of identifying which of the individual ECB bridges for which mitigation needs could have been changed if an alternate bridge through the benefits of the Alternate Technical Concepts or other contractor-specific means and methods would have been built but was not clue to the cost and/or time required to amend the NEPA document, permits, right-of-way plans, and other project documents.
PennDOT will evaluate the following to measure impacts to the quality and integrity of the environmental process:
A. For each REB, PennDOT shall analyze the qualitative impacts on environmental review and decision-making, both adverse and beneficial, of allowing the DE to select and control the environmental consultant or the use of DE staff, prepare the environmental documentation, and handle negotiations with permitting agencies. Impacts considered will include, at a minimum:
B. PennDOT will evaluate the accuracy and quality of the environmental documents prepared by the DE, and the consistency of the review process with NEPA and other environmental requirements. This will include, at a minimum:
C. For each Replacement Bridge, PennDOT shall analyze the effectiveness of the financial and procedural protections designed to ensure the DE will receive no financial benefit and bear no financial risk not already priced into its proposal related to environmental mitigation or project delays resulting from environmental findings in the NEPA process. As above, PennDOT shall analyze both the ECB and the REB. This shall include, as a minimum, evaluation of:
Based on all the information gathered and analyzed pursuant to Sections 5.2 and 5.3. PennDOT will assess:
A. Whether the protections used under this SEP-15 adequately insulated the environmental review process against conflicts of interest, ensured the integrity and objectivity of the NEPA process, and protected the public's faith in the integrity of the NEPA process.
B. Whether the regulations subject to the SEP-15 experiment could be amended or revoked without adverse effect on the NEPA process, including the factors listed in 5.4(A).
C. What refinements or modifications would improve outcomes should a similar SEP-15 be approved for further testing of the experimental features.
PennDOT shall prepare or commission a third-party to prepare an Annual Progress Report to be provided no later than 60 days after the first 12 months following the Notice to Proceed for the Project, and then once every 12 months thereafter until the end of construction.
The Annual Progress Report shall include the following components:
A final full evaluation report will be submitted to the Pennsylvania Division Office of the FHWA within six (6) months of the completion of construction of all REBs under the Project.
The Final Report shall include the following components:
This EDA may be amended at any time by written agreement of FHWA and PennDOT. Amendments to this EDA may include, but are not limited to, the addition or deletion of SEP-15 experimental features, modification of performance measures, and modification of reporting requirements. The FHWA Pennsylvania Division Administrator shall have the authority to amend this EDA for the FHWA, subject to the concurrence of the Office of Innovative Program Delivery.
This EDA shall be prepared in duplicate so that each signatory has an original copy.
SIGNATURE PAGE FOLLOWS
IN WITNESS THEREOF, the Parties hereto have caused this Early Development Agreement to be duly executed in duplicate as of the day and year first written above, either on one original document or via multiple counterparts through facsimile, which, when taken together, shall constitute one and the same instrument.
FEDERAL HIGHWAY ADMINISTRATION
<signature>
By: Gregory G. Nadeau
Acting Administrator
PENNSYLVANIA DEPARTMENT OF TRANSPORTATION
<signature>
By: Barry J. Schoch, P.E.
Secretary of Transportation
APPROVED AS TO FORM AND LEGALITY
<signature> <date: 11/7/2014>
Department of Transportation
Chief Counsel
<signature><date: 11/12/14>
Office of General Counsel
Deputy General Counsel
<signature><date: 12/9/14>
Office of Attorney General
Deputy Attorney General
Office of Policy and Public Private Partnerships
400 North Street
Harrisburg, PA 17120
717.787.0787
www.dot.state.pa.us
July 15, 2014
Ms. Renee Sigel
Division Administrator
Pennsylvania Division
Federal Highway Administration
228 Walnut Street, Room 508
Harrisburg,
Pennsylvania 17101-1720
Email:
renee.sigel@dot.gov
Re: Pennsylvania Department of Transportation "SEP-15" Request for Variances from 23 CFR 636.109(b)(6) and (7) in connection with the Pennsylvania Rapid Bridge Replacement Public-Private Partnership Project
Dear Division Administrator Sigel:
This letter constitutes an application to the Federal Highway Administration (FHWA) by the Pennsylvania Department of Transportation (PennDOT) for approval pursuant to "Special Experimental Project Number 15" (SEP-15) to deviate from portions of clause (6) and clause (7) of 23 CFR 636. l 09(b) regarding the involvement of a developer and consultants in preparing documentation required by the National Environmental Policy Act of 1969, as amended (NEPA). This application relates to the Pennsylvania Rapid Bridge Replacement Public-Private Partnership Project (the Project).
The Project will be the first "multi-asset" transportation project of its kind to be procured in the United States as a public-private partnership. If granted, the requested variance will enable PennDOT and FHWA to evaluate the efficiencies, if any, of using a single contractor for all phases of the Project, including the NEPA process. If shown to be an innovation of value to the Federal Aid Highway Program (and if and when duly codified by law or regulatory action), the approach may have application nationwide as a project delivery method for addressing the systemic problem of structurally deficient bridges in the United States.
PennDOT is procuring the Project in compliance with relevant federal regulations in order to quality the Project for Federal assistance. The U.S. Department of Transportation (USDOT) has made a conditional allocation of private activity bonds (PABs) for the Project in the principal amount of$l.:2 billion.
Pursuant to its authority set forth in 23 U.S.C. 502(b). FHWA established SEP-15 to encourage tests and experimentation in procurements of federal aid transportation projects. Among the specific objectives of SEP-15 is the promotion of project management flexibility, innovation, improved efficiency, and timely project implementation.
In connection with prior SEP-15 applications. FHWA has recognized that experimentation, by its nature, requires the assumption of risk and that, without the assumption of risk, the federal-aid highway program cannot receive the benefit of experimentation for which SEP-15 was established.
In Section 5 of this application, PennDOT sets forth a series of terms and conditions that eliminate, or mitigate, the risk of prejudicial actions for the Project. Such terms do not replicate the protections of clauses (6) and (7) completely, however, and deliberately so. The purpose of the experiment contemplated by this application is to evaluate whether certain limitations on the activities of design- builders and consultants can be modified to achieve efficiencies without compromising the objectives for which clauses (6) and (7) were promulgated. While it is the specific purpose of this application to deviate from FHWA policy, it should be fully understood that there is no intent to alter the required tasks associated with the NEPA process. It is on this basis that PennDOT respectfully submits this application.
The Project encompasses the design, construction. financing, and lifecycle maintenance of approximately 559 bridges (each, a Replacement Bridge) that will replace structurally deficient bridges in the Commonwealth of Pennsylvania (the Commonwealth) through a public-private transportation partnership agreement (the PPA) 1 in order to accelerate the design and construction of the Replacement Bridges. The expected time required for design and construction is approximately 3.5 years. Additional details on the Project are included in Exhibit 1 of this application.
From an environmental perspective, all Replacement Bridges included in the Project are scoped as a Categorical Exclusion (CE), and the majority of the bridges are generally classified as small bridges. Of these bridges, 376 are less than 50 feet in length, 142 are between 50 feet and 100 feet, and 41 are over 100 feet. PennDOT completed an initial screening of the Replacement Bridges and completed the initial scoping field view and scoping documentation. As a result of the scoping field views, the Replacement Bridges have been scoped as follows:
This request for a variance applies only to the "Remaining Eligible Bridges" as described in Exhibit 1.
PennDOT is requesting a variance of portions of clauses (6) and (7) of 23 CFR §636.109(b) in order to evaluate the efficiencies, if any, of a public-private partnership procurement involving bridge bundling - specifically streamlining the process and accelerating the time required to deliver a project which will result in a substantial reduction of project costs. To this end, PennDOT intends to have the Development Entity complete the required preliminary engineering, conduct NEPA studies, and prepare NEPA documentation for each of the Remaining Eligible Bridges. The Development Entity will select and contract with the consultant who completes the NEPA studies and the NEPA documentation. Clauses (6) and (7) of 23 CFR 636.109(b) are intended to prevent the developer of a project, whether in its capacity as the design-builder or a consultant, from prejudicing the NEPA analysis with respect to the Project. The requested variances are as follows:
In order to achieve the purpose of such clauses, PennDOT and FHWA, as applicable, will retain control over the design-builder's and consultant's Project deliverable by retaining full approval authority in the NEPA process consistent with the purposes of clause (6) and clause (7).3 The difference between the arrangement contemplated by this application, on the one hand, and PennDOT's current practices, on the other, is that: (i) the design-builder will participate in the preparation of the NEPA documents, and (ii) the consultant will not be directly engaged by PennDOT nor under PennDOT's exclusive control but instead engaged by PennDOT's private partner under the PPA.
The P3 Bridges Screening, Scoping, and NEPA Decision Annotated Flowchart as provided in Exhibit 2 describes the early project development actions performed by PennDOT along with the NEPA process that will be undertaken for this Project.
If permitted as an Experimental Feature and subject to the conditions described below in Section 5, the Development Entity's consultant participation in developing NEPA documentation will enable PennDOT to procure the Project under a public-private partnership procurement achieving efficiency in implementing the Project, project acceleration, and cost reductions while maintaining the objectives of clauses (6) and (7) of 23 CFR 636.109(b). The following are additional details on the benefits expected to be realized by transportation agencies and the public if the requested deviations are approved by FHWA:
As a condition of FHWA's authorization of the requested deviations, PennDOT will incorporate various controls into the Project that serve to ensure the Development Entity and its consultants perform the delegated NEPA process tasks to the quality and completeness expected and provided on PennDOT's regular projects. More specifically, PennDOT will require the Development Entity, in accordance with the PPA, to submit each categorical exclusion evaluation or other NEPA documentation to PennDOT for its substantive review and independent evaluation. PennDOT will undertake, pursuant to its Project Stewardship and Oversight Agreement with FHWA, to perform such reviews, and after independently evaluating the information will approve or disapprove each submittal of NEPA documentation in accordance with the terms of the PPA. In addition, the PPA and its Technical Provisions for the Project includes numerous safeguards to ensure that the integrity of the NEPA process is maintained.
Given the process set forth in the flowchart attached as Exhibit 2 and the above safeguards, there is no material increase in the risk that the NEPA process will be compromised when the NEPA studies and documents are completed by the same entity that completes final design and construction of the Replacement Bridges.
Critical to the success of the Experimental Feature and timely procurement of the Project is adherence by PennDOT and FHWA to a work plan and schedule that is consistent with the schedule for the procurement and execution of the PPA. PennDOT proposes the work plan and schedule for itself and FHWA set forth in Exhibit 4 of this application.
Having the Development Entity perform the preliminary engineering, the NEPA analysis and documentation, the final design, and construction for this Project as described herein will serve the following goals:
8.1 This experiment will be evaluated on a range of factors, including time savings to PennDOT, cost savings to the public, risk allocation optimization, and time savings for the completion of the Project. Specifically, PennDOT will:
8.2 To evaluate the integrity of the NEPA process, PennDOT will:
PennDOT will transmit to FHWA an interim report on the Experiment within six months after initiation of preliminary design work on the Replacement Bridges. Additional interim reports will be transmitted at a maximum 6-month interval. A final draft project report containing all finding will be transmitted within 6 months of the completion of the construction of all Replacement Bridges under the PPA. The following information will be included in the reports:
Time is of the essence in obtaining approval of the experimental elements in order for PennDOT to proceed with procurement as planned for the Project. The final RFP had been scheduled for release on July 3, 2014, and the proposals are currently due on September 29, 2014. Without approval by the end of July, PennDOT will have to undertake undesirable actions to revise the RFP so as to fully comply with the CFR.
While there are several options at hand to comply, none are favourable to the Project. PennDOT expects the Project will be delayed up to 12 months and cost impacts of up to $25 million or more are anticipated to the Commonwealth. Additionally, all available options transfer a multitude of technical tasks and managerial responsibilities back to PennDOT.
We truly appreciate the cooperation and efforts from all staffs in your office as well as your headquarters and look forward to ongoing dialog to obtain a meaningful outcome to this request.
Please feel free to contact me at (717) 787-8765 as you review our application. In addition, please do not hesitate to request PennDOT's relevant staff to meet with your team or your colleagues in Washington, D.C., in order to provide any clarifications or further explanations that you think advisable.
Sincerely yours.
<signature>
Bryan Kendro
Director
Office of Policy & Public-Private
Partnerships
Enclosures
Exhibit 1: Rapid Bridge Replacement Project: Description and Schedule
Exhibit 2: P3 Bridges Screening, Scoping, and NEPA Decision Annotated
Flow Chart
Exhibit 3: Comparison of Design Build Processes
Exhibit
4: Work Plan and Schedule for SEP-15 Variance
The Development Entity will design, build, finance and maintain the Project in return for Availability Payments and Milestone Payments.
Approximately 92 of the Replacement Bridges are referred to as the Early Completion Bridges. In the interest of supporting accelerated delivery of the Early Completion Bridges, PennDOT will assume certain responsibilities and risks with respect to the environmental clearance and permitting of the Early Completion Bridges. The Early Completion Bridges are situated in two clusters: the first cluster being located in the northeast part of the Commonwealth (PennDOT Districts 3, 4, and 5) and the second cluster being located in the southwest part of the Commonwealth (PennDOT Districts 10, 11, and 12).
The remaining 467 replacement bridges are referred to as the Remaining Eligible Bridges. The Remaining Eligible Bridges are located throughout the Commonwealth.
PennDOT conducted the following activities as part of the early project development process for each bridge:
These actions serve to ensure that the bridges selected for this project are eligible for a Categorical Exclusion Evaluation or PennDOT's Bridge and Programmatic Agreement (BRPA) and do not require an Environmental Assessment or Environmental Impact Statement. Additionally, the information in these actions provides substantial background information for the Development Entity's use in understanding the environmental features that may be encountered at the individual bridge sites.
For all bridges, PennDOT is conducting investigations of the Project Sites (scoping field views. geotechnical studies, and detour analysis). PennDOT will provide the preliminary results of such investigations to the Proposers as Disclosed Information. For the avoidance of doubt, such results constitute Disclosed Information.
The Development Entity will be responsible for coordinating and causing all Utility Adjustments necessary in order to comply with its obligations under the Project Documents.
PennDOT will be responsible for acquiring at its own expense the right of way that comprises the Project Site of each Replacement Bridge.
The time to complete the Project from Commercial Close to completion of construction is 42 months. It is expected that 99 percent of the bridges will be completed within this time frame. Inherently, this allows for about 5 bridges to extend beyond the 42-month period. The Development Entity is responsible for maintenance of the bridges for a period of 25 years after completion of the individual bridges.
EVENT | DATE |
---|---|
Issuance of First Industry Review Draft of RFP Documents | April 4, 2014 |
Issuance of Second Industry Review Draft of RFP Documents | May 16, 2014 |
Issuance of Third Industry Review Draft of RFP Documents | June 3, 2014 |
Issuance of Fou1th Industry Review Draft of RFP Documents | July 3. 2014 |
Issuance of Final Request for Proposals | End of July 2014 |
Proposal Due Date | September 29, 2014 |
Anticipated Date of Announcement of Preferred Proposer | October 31, 2014 |
Anticipated Commercial Closing Deadline | December 16, 2014 |
Completion of Construction | 42 months after Commercial Close |
End of Maintenance | 25 years after completion of construction of the individual bridge |
9.1 All Replacement Bridges Included in the Project
9.2 Early Completion Bridges
View full-size version of flow chart.
View full-size version of flow chart.
EXHIBIT 4
WORK PLAN AND SCHEDULE FOR SEP 15 VARIATION PENNDOT RAPID BRIDGE REPLACEMENT PROJECT
Last Update: July 15, 2014
Date | Activity | Responsible Party(ies) | Comments/Status |
---|---|---|---|
1. SEP 15 Process for Approval | |||
4/16/2104 | Submit Concept Paper to FHWA | PennDOT | Received feedback that submission needed more emphasis on the intent of experiment, benefits, and risks |
5/30/2014 5/31/2014 | Submit White Papers on Experimental Benefits and Risks to FHWA | PennDOT | Complete |
6/6/20l4 | Video Conference with FHWA to discuss Concept Paper | PennDOT, FHWA | Received request to provide more information on the proposed NEPA approval process along with a NEPA Process Flowchart |
6/11/2014 | Submit letter providing more information on the proposed NEPA approval process along with a NEPA Process Flowchart to FHWA | PennDOT | Complete |
6/13/2014 | Feedback to PennDOT on 6/1l/2014 letter | FHWA | Received feedback to complete and transmit the SEP 15 Application |
6/16/2014 | Submit Draft Final SEP 15 Application to "FHWA | PennDOT | Complete |
6/19/2014 | Receive feedback to Draft Final SEP 15 Application | FHWA | Received feedback |
6/20/2014 | Submit SEP 15 Application to FHWA | PennDOT | Complete |
6/26/2014 | Receive feedback on Final SEP 15 Application | FHWA | Received feedback |
7/01/2014 | Submit Revised Final SEP 15 Application | PennDOT | Complete |
7/9/2014 | Receive feedback on Revised Final SEP 15 Application | FHWA | Received feedback |
7/15/2014 | Submit Revised Final SEP 15 Application | PennDOT | |
7/25/2014 | Approve SEP 15 Application | FHWA | |
Prepare and submit Draft Early Development Agreement (EDA) to PennDOT | FHWA | ||
Conference Call to discuss Draft EDA | PennDOT, FHWA | ||
Distribute Revised Draft EDA to PennDOT | FHWA | ||
Submit final comments on Draft EDA | PennDOT | ||
Conference Call to discuss revised Draft EDA | PennDOT, FHWA | ||
Sign EDA | PennDOT, FHWA |
Federal Highway Administration
Office of the Administrator
1200 New Jersey Ave, SE
Washington, D.C. 20596
July 31, 2014
Mr. Brian Kendro
Director Office of Policy and Public-Private
Partnerships
Pennsylvania Department of Transportation
Harrisburg.
PA 17105
In Reply Refer TO: HIN
Dear Mr. Kendro:
The Federal Highway Administration (FHWA) completed its review of the Pennsylvania Department of Transportation's (PennDOT's) "Pennsylvania Rapid Bridge Replacement Public- Private Partnership (P3) Project" (The "Project") Special Experimental Project No. 15 (SEP-15) application ("Application") that was submitted to the FHWA Pennsylvania Division Office (Division Office) on July 15, 2014. The Division Office forwarded the Application to the FHW A Office of Innovative Program Delivery which coordinated the review of the proposed SEP-15 experiment with the Office of Infrastructure; Office of Planning, Environment, and Realty; Office of Chief Counsel; and the Division Office. Based on the comments provided by these offices, the SEP-15 Steering Committee recommended, and I concur, that the Project be conditionally accepted for administration under SEP-l5. The FHWA's response to the proposed experimental features for the Project is discussed below.
The FHWA's acceptance of the Project for administration under SEP-15 does not commit Federal-aid funding for the Project. Until there is formal FHWA project approval, FHWA retains the right to decline the Project ineligible for Federal-aid funds at any time during the SEP-15 process. In addition, all Federal laws, rules, and regulations shall be applicable to the Project, including, but not limited to, the requirements set forth in titles 23 and 49 of the United States Code, and titles 23 and 49 of the Code of Federal Regulations, the Uniform Act, and the National Environmental Protection Act (NEPA), except as otherwise specified herein.
The FHWA may withdraw its approval of the SEP-15 experimental features if it determines that the experimental features are not in the public interest. Prior to any such withdrawal, the FHWA will issue a written notice to PennDOT describing the FHWA's concerns and give PennDOT a reasonable period of time to address the FHWA's concerns. However, during such period of time, no further work shall be conducted based on the approval at issue until such time as FHWA determines that PennDOT has fully addressed FHWA's concerns. Upon withdrawal of approval of an experimental feature, the applicable requirements of title 23 of the United States Code and title 23 of the Code of Federal Regulations shall immediately apply.
If you wish to proceed with the Project under the SEP-15 program, the next major action will be for FHWA to work with you to draft an Early Development Agreement (EDA). The EDA will identify the specific roles of all parties, define procedures and requirements, and establish time frames and other conditions under which the experimental features will be administered.
The EDA will also identify the performance measures that will be used to evaluate the success of the Projects experimental features.
Background
The PennDOT is pursuing a P3 project to replace 559 bridges throughout the State. By bundling similar bridges into one project, PennDOT believes it can save money on design, permitting, construction, and ultimately maintenance. If PennDOT were to replace each of these bridges individually, using its traditional procurement schedule, PennDOT estimates that the process could take 10 - 15 years. However, bringing the resources of a private sector partner to bear, or Development Entity (DE), PennDOT estimates it will be able to deliver the replacement of 99 percent of the bridges in the Project in just 42 months.
The PennDOT will compensate the DE via milestone payments during construction and performance-based availability payments over the 25-35 year Public Private Agreement (PPA) contract term. By incorporating long-term financing and maintenance into the procurement, the DE is also motivated to make sure that the bridges are built to last.
This Project is a key component of PennDOT's effort to address the State's systemic backlog of almost 4,800 structurally deficient bridges. The Project will be the first P3 multi asset transportation project of its kind in the United States.
The PennDOT intends to have the DE conduct environmental studies, prepare environmental docun1entation, and con1plcte the required preliminary engineering for bridges covered by Level l or Level 2 categorical exclusion (CE), and obtain necessary permits and approvals for each bridge included in the Project. The PennDOT conducted initial screenings and scoping field reviews to make sure that the bridges selected for this Project are eligible for a Level 1 CE or Level 2 CE. This screening includes a determination that an environmental assessment or an environmental impact statement is not required under applicable Jaw.
The U.S. Department of Transportation provided PennDOT with a conditional Private Activity Bond allocation for the Project. Per the terms of this allocation, the Project must meet all applicable Federal-aid requirements.
Experimental Features
The PennDOT intends to have the DE complete the required preliminary engineering, conduct environmental review studies, prepare environmental documentation and obtain necessary permits and approvals for each bridge included in the Project. In order to allow the DE to undertake these activities, PennDOT requests two deviations from FHWA regulations:
Purpose: PennDOT requests the deviations from 23 CFR 636.l09(b)(6) and 23 CFR 636.109(b)(7) in order to evaluate the efficiencies, if any, of the proposed Project - specifically accelerating the time and reducing the costs required to deliver a project by allowing a DE to conduct the environmental review process.
Deviation from FHWA Requirement(s): FHWA's Design-Build Contracting regulations currently prohibit the DE from preparing suppo1ting documentation and draft decision documents as required for the environmental review process.
FHWA Response: The FHWA's prohibition against a design-builder's involvement in the NEPA decision making process is intended to: (l) Insulate against conflict of interests; (2) Ensure the integrity and objectivity of the NEPA process; and (3) Protect the public's faith in the integrity of the NEPA process.
The proposed experiment would allow FHWA to assess whether it should undertake a rulemaking to amend the Design-Build Contracting regulations to allow greater design-builder involvement in the preparation of environmental documents and in the control of environmental consultants where the projects have limited or no potential for significant adverse environmental effects and safeguards are in place to greatly reduce or eliminate the risk of design-builder bias in the outcome of the environmental review process.
The FHWA's acceptance of the PennDOT SEP-15 proposal is conditional and contingent on the inclusion of specific safeguards to protect the integrity of the environmental decision making process. Conditions include a requirement that PennDOT's contracting documents and the EDA contain specified mechanisms that are clearly tied lo preserving the purposes of 23 CFR 636.109(b)(6) and 636.109(b)(7). These conditions will ensure that (l) there is no material risk of bias in the environmental decision making process, (2) public officials and citizens have the necessary environmental impact information for federally funded actions before actions are taken, and (3) that the DE does not assume an unnecessary amount of risk in the event the NEPA process results in a significant change in one or more of the bridges included in the Project.
The FHWA's conditional acceptance of the PennDOT SEP-15 proposal relies on the safeguards and conditions proposed by PennDOT in its Application to preserve the purposes of 23 CFR 636.109(b)(6) and 636.109(b)(7). The safeguards and conditions are as follows:
Proposed Performance Measures and Reports
The PennDOT SEP-15 Application included proposed factors to evaluate the experimental features of the Project SEP-15. The FHWA will fully evaluate the proposed factors, listed below, for inclusion in the EDA:
The proposed initial report, periodic updates, interim reports, and a final report, described in the Application, will be reviewed during the development of the EDA and incorporated into a project timeline.
I have asked Ms. Regina McElroy. Director, Office of Innovative Program Delivery and Ms. Renee Sigel, FHWA Division Administrator for the Division Office to serve as the co-facilitators for the Project. Ms. McElroy and Ms. Sigel will establish an FHWA interdisciplinary team to work with PennDOT to develop the provision of the EDA.
Sincerely,
<signature>
Gregory G. Nadeau
Acting Administrator
1 The PPA is authorized by Act 88 (2012) of the Commonwealth (74 Pa. CS. 9101 et seq.).
2 The Bridge and Roadway Programmatic Agreement (BRPA) is an agreement between FHWA PA Division and PennDOT. The BRPA applies to a subset of projects that: (a) qualify as a CE Level 1; (b) are in the same approximate footprint: (c) modifications compared to the existing bridge do not exceed certain criteria; (d) ensure that wetland impacts do not exceed 0.05 acres: (e) have 110 adverse effects under Section 106: (f) "no conflict" or "no effect" for T&E species: and (g) do not require an individual Section4(f) evaluation.
3 Presently, PennDOT uses consultants to complete the NEPA process and documentation (which includes using the PennDOT CE Expert System)
4 Project Path is a publicly accessible tracking system for the Section 106 process, with document warehouse capability and automated notification via mail. Project Path supports consulting party consultation and public involvement.