Common pavement issues |
- Note barriers or issues common to all pavement
types:
- Clearance issues under structures – vertical.
- Lane delineation – horizontal clearance.
- Need to construct structures first!
|
|
Composite pavement |
- Utilize a concrete base with two- to three-inch
asphalt top.
- The asphalt creates a wearing
course.
|
- Higher initial cost; many inexperienced
contractors (new to area).
- Eliminates concrete
final texture.
|
JPCP |
|
- Conventional method; contractor familiarity.
|
CRC |
|
- Long process; labor intensive for reinforcement
installation.
- Higher cost; lack of experience by
owner and contractors.
- Phasing of work is an
issue.
|
Asphalt concrete pavement |
- Utilize asphalt over a granular or CRABS base.
|
- Increases maintenance over the long-term;
rutting may be an issue.
- Has shorter
construction time under traffic.
- Familiar
construction technique; provides larger
contractor pool.
|
Crack and seat |
- Break up into three- to four-foot sections and
overlay.
- For existing concrete pavement only.
|
- Faces vibration concerns for adjacent
landowners during construction; is a public
relations concern.
- Performance risk due to
reflective cracking.
- May not be a long-term
solution.
|
Rubblization of existing pavement |
- Break up existing concrete to three-inch minus
and overlay with asphalt.
- For existing concrete
pavement only.
|
- Can't run traffic during construction.
- More
expensive than crack and seat option due to
increased effort to break up concrete in place.
- A thicker overlay is required.
|
Rigid pavement over CRABS |
- Develop process for recycling existing asphalt
pavement (west of Meridian).
|
- Produces excess material – use for third lane.
- Is
a proven process in Idaho.
|
Fast track concrete |
- Use high-early-strength concrete for early
opening of the roadway to traffic.
|
- Look at special situations (critical path).
- Is
more expensive.
- There are durability concerns
(shrinkage, cracking).
- Testing is intensive.
|
Base material: permeable versus dense-graded |
- Compare asphalt-treated base (ATB), cement-treated
base (CTB) and aggregate base (AB).
|
- ATB performs well under concrete.
- CTB hasn't
performed well.
- AB is a conventional material.
- If ITD uses a permeable material, it will require
a drainage system.
|
Sub-base material |
- Consider a granular sub-base and rock cap.
|
- Granular sub-base is readily available; rock cap
is questionable.
- Contractor is familiar with
placement.
|
Edge drains |
- Install positive pavement drainage.
|
- Limit to low spots on this project.
- Maintenance
is required for long-term performance.
- Requires discharge point.
|
Material sources |
- Have sources be State- or contractor-owned.
- Look at quality and quantity of available
materials.
|
- Determine availability of acceptable material
within a reasonable haul distance.
- May face
competition with local and private projects.
|
Soil nail wall (Meridian structure) |
- Accommodate loop ramp.
- Underpin existing
abutment.
|
- Determine if loop is required.
- Consider a left-turn
signal for eastbound traffic to I-84.
- Would
be a short-term solution until the Meridian
structure is replaced.
- Determine if this is cost
effective.
- Explore alternative structure solutions.
|
Larger projects put out to bid |
- Draw in contractors with greater capacity
to speed up construction – they have more
equipment and personnel.
|
- There are a limited number of contractors for
large projects.
- Need to evaluate Associated
General Contractors of America (AGC)/political
considerations.
|
Retaining wall alternatives |
- Consider utilizing precast wall system to
accelerate construction.
|
- Requires ITD approval if not included on
standard list.
- Ease of construction is a plus. Is
readily available.
|