Get In Stay In Get Out Stay Out (GISIGOSO) |
- Note that the philosophical approach of doing a
complete build-out initially rather than revisiting
project areas is more in tune with ACTT goals.
- From a cash flow analysis stand point, the project
can be shown to be less expensive for a 3-year
construction cycle than a 10- to 12-year period.
- Note: The NEPA process and ROW schedule need
to be in sync with construction phasing.
|
- Determine the ultimate build-out and the
optimum construction phasing for the
ultimate build-out.
- Perform a construction-schedule-based cash
flow analysis. Implementing this may require
reprioritizing the allocation of funding.
- Consider GARVEE funding: it's consistent
with GISIGOSO.
- Shorten the duration of traveler impacts.
- Avoid adverse public perception of continual
construction within a given segment.
- May need to address political requirements
to spread funds throughout the State.
- Note: There is the potential for the ACTT
workshop and findings to be used as a
demonstration that funding allocation
changes on this corridor could result in
quicker and more complete construction at a
better value overall.
|
Garrity to Meridian project overpasses |
- Construct the Black Cat and Robinson Road
overpasses before or during the construction of
the third lane project.
|
- Design overpasses for two lanes now but
expandable up to four lanes in the future.
- Obtain NEPA clearance.
- Need to re-allocate funding.
- May eliminate the need for a design
exception at these two locations.
- Enhances traveler safety.
- Will provide for more efficient/earlier
construction and reduce costs.
|
Crack and seat pavement project: Gowen
Road to Isaac's Canyon |
- Prepare a life-cycle cost comparison of the full
build-out pavement section versus the currently
planned "crack and seat with overlay" project;
this may show that it would be more cost
effective to construct the full build-out pavement
initially.
|
- May need to re-allocate funding to construct
the full pavement section initially.
|
Utilities |
- Implement SUE now, and avoid or remove utility
conflicts before construction begins where
physically possible.
- Include fiber-optic cable
relocation at the sound wall and other conflict
sites.
|
- Provide utility surveys early.
- Get utility companies on board early.
- Use SUE information for possible roadway
design changes, and identify other ways to
avoid utility conflicts.
- Hire a full-time utility coordinator to deal
with utilities issues in the corridor.
- Purchase materials early that have long lead
times for delivery.
|
Irrigation district facilities |
- Seek early involvement with the irrigation districts
to concur on necessary facility modifications and
assure adequate construction work windows.
|
- Address water quality, cost, schedule,
easement, permit and other issues as early
as possible since district canal rights can take
precedence over ITD highway needs.
|
Standardization and pre-purchasing of
materials |
- Seek early approval and acquisition of
standardized materials and supplies that can
be made available to the contractor.
- Examples
include pre-cast bridge and wall units, work zone
traffic barriers, lighting poles and fixtures, traffic
control devices, bridge rails, drainage facilities,
etc.
|
- Need justification and prior FHWA approval.
- Reduces schedule impacts for long lead-time
materials.
- Is potentially more cost effective.
- Provides maintenance efficiencies.
|
Advance construction of sound walls – Cole to
Broadway |
- Advance construction of the Cole to Broadway
sound walls to the fall of 2007 so they are in
place prior to construction on the mainline
(scheduled for the summer of 2008).
- Note:
Funding is scheduled to be available in July 2007.
|
- Resolve wall location and limits.
- Resolve conflict with fiber-optics;
accommodate the cable in a conduit
compatible with the permanent sound wall
location and construction.
- Obtain early NEPA clearance.
- Resolve and complete any ROW or easement
needs.
- Use:
- Innovative contracting to involve the
contractor early in the design completion.
- Incentives for early completion and a
reduction in impacts to the traveling public
and adjacent property owners.
- Use a standardized design concept.
- Consider pre-purchasing certain materials,
i.e., piling, wall panels.
|
Work zone access |
- Clearly define the approved access in the PS&E
documents. Allow for VE options.
- Consider A-plus-B-plus-C
bidding, where C might be the
value of the access.
|
- Clearly define the access agreement in the
bidding process so that all of the contractors
bid on the exact same project requirements.
A level bidding field needs to be maintained,
but flexibility needs to be allowed. Perhaps
the contractor could be allowed access
at certain defined points plus a potential
"break" in the fence providing access every
three (+/-) miles.
- Identify possible State-owned parcels
adjacent to the freeway for contractor
staging and access.
- Identify possible "acquisition" parcels
adjacent to the freeway.
|
Interchange footprint reviews |
- Note the interchange footprints and layouts, as
currently being used for the NEPA studies, are
very preliminary.
- Coordinate with study teams to assure that
concept designs are accounting for, and
consistent with, ROW, utility, traffic operations,
design standards and construction phasing
issues.
- Plan for an efficient transition to preliminary and
final designs.
|
- Review conceptual interchange layouts.
- Review traffic operations analysis and lane
numbers/arrangements.
- Review interchange geometry for optimal
footprint and ROW requirements.
- Consider optimized bridge width based on
traffic operations.
|