Enhanced design/construction collaboration |
- Create a win/win/win situation so that all parties
(owner, designer and contractor) are motivated to
cooperate and put forth extra effort when needed.
- Develop a partnering agreement between the
parties to define the rules and responsibilities for
cooperation.
- Foster continuous communication
through regular and frequent (periodic) meetings
among the participants.
- Enable the participants to
easily meet on an unscheduled basis to ensure that
issues can be discussed and decisions rendered
as they arise without delaying the work (ad hoc
process).
- Utilize and maximize goal-oriented
processes.
- This involves the use of "onboard
reviews," meaning that the review process will be
performed as a group effort as much as possible,
enabling all parties to work collaboratively on the
review.
- The objective is to more quickly develop
an understanding of the issues as they impact the
various participants and thus be able to quickly
come to acceptable decisions.
- Railroad issues
must be discussed and addressed very early in the
developmental process to avoid potential delays or
rework in the design.
- Environmental constraints
must be defined early to allow the design to
properly address environmental issues.
- Effective
project coordination requires the early and
continuous involvement of all relevant disciplines.
- The project manager must ensure that issues and
decisions are documented in a timely fashion.
- All
parties must have commitments for the maximum
time allowed to deliver their portion of the work,
and the project manager must ensure that these
commitments are met.
|
- Benefits: Provides participant flexibility.
Improves quality of relationships between
partners. Limits claims and reduces risk.
- Barriers: Potential of higher cost. Requires
changing of mind set. While railroad approvals
are critical for portions of the work, the railroad
does not necessarily feel the same level of
urgency since their functioning is not going to
be improved by this project.
- Challenges: Requires a well developed chain
of documentation. Need to develop means of
owner protection and risk allocation among
partners.
- Coordination: Must include railroads early in
the design process. Design and environmental
sections must work together and develop a
strong understanding of how they impact one
another. Need decision makers involved early
in the process.
|
Acceleration of project development (design
and construction) |
- Advertise project for bidding at a preliminary
stage (approximately 30 percent) of design
development – Caltrans' design sequencing
is an example of this approach.
- Have final
design and construction proceed concurrently.
- Complete final design for a portion of the
work, i.e., the foundations, as soon as possible
to enable construction to begin.
- Remaining
design activities must proceed at a fast pace to
avoid being overtaken by the construction work.
- Designer must be very responsive in evaluating
the contractor's proposals or addressing the
contractor's concerns.
- The contractor's means
and methods must be incorporated into the
design through close coordination among
the owner, designer and contractor.
- Have the
designer contracted independently with the
owner so that the owner maintains control of
the design process.(This is different from DB,
where the contractor controls the design
process.)
- Because the method of contracting
places high demand on the designer, the
contract may need to incorporate monetary
incentives for the designer to insure the desired
responsiveness.
- This method of contracting
requires a high level of partnering among the
owner, designer and contractor.
|
- Benefits: Accelerates both design and
construction. Elicits construction feedback
earlier in the design process. Encourages
innovation in design and construction.
- Barriers: Need to allocate risk among all
parties. There is limited adaptation of this
approach in the U.S. Need to determine
owner's capability to respond to the contractor's
proposals or requests as quickly as needed. (This
is a manpower issue.) Project must be bid with
a PS&E package that is not fully developed. Risk
exists for all parties, but it is the owner who
assumes the most risk – the designer has no
incentive to assume any risk. Inter-related design
or construction problems may be overlooked
at a partial stage of design; the owner may
have to redo or modify construction work after
construction has begun because unforeseen
problems require that design changes be made.
Structures that are less complex, (i.e., routine)
greatly reduce the potential for problems.
- Challenges: Need to develop pay item quantities
as much as possible at the preliminary design
(bidding) stage. Establish provisions for quantity
and bid price adjustments in case quantity
revisions occur as plans become finalized.
Must develop proper incentive programs for
both the designer and the contractor. Must
have a designer who is very responsive to the
contractor's requests for change as the design
is developed; needs to be adaptable to the fast
pace of evaluation and decision making.
|
Accelerated design development |
- Consider pre-contracting on a task order basis
for design consultation. Since the design work is
a controlling activity on the project critical path,
the process for procuring design services must
be very efficient so that valuable time is not lost
in obtaining these services.
- Schedule pre-design
bridge workshops for TS&L development.
- The conceptual design is illustrative of Pareto's Law,
which states that 20 percent of the effort will
yield 80 percent of the benefits.
- It is important
to have a strong effort with multiple sources of
input at the concept stage to guarantee that
the concept employed will be an effective and
appropriate choice.
- Utilize an accelerated design
review process with collaborative meetings.
- Minimize the design detail required of the
designer, i.e., do not require the designer to
produce reinforcing bar list sheets since the
contractor must do this as part of the normal
contract requirements.
|
- Benefits: Accelerates design process. Ensures
that the conceptual design is the most
appropriate choice through collaborative
effort. Reduces the design effort required by
eliminating redundant activities.
- Challenges: Requires buy-in by all parties.
FHWA must see the driving benefit (cost versus
convenience). Requires adapting to changes in
normal practice, i.e., minimizing or eliminating
elements of the contract plan detailing. Must
adapt to a faster design pace.
|
Prefabrication of structural components |
- Recommend prefabrication of virtually all bridge
components, including the following:
- Foundations.
- Piers.
- Abutments.
- Girders.
- Deck slabs.
- Barriers.
- Complete superstructure spans.
- Components for other structures such as
retaining walls and sound barriers can also be
prefabricated.
|
- Benefits: Allows for faster construction.
Provides potential to improve worker safety.
Minimizes impact on road users, reducing
road user costs. Reduces owner's time for
contract administration, which reduces owner's
personnel costs. Provides higher quality of
components due to fabrication in a controlled
environment.
- Barriers: Must overcome perception of
higher cost of prefabrication. Need to weigh
user benefits against higher construction
costs. Must address concern over durability
of connections between prefabricated
components and related concern over
long-term maintenance costs. Note lack
of contractor familiarity with prefabricated
construction – must address contractor
preference for conventional construction
methods due to equipment investment
and desire to maintain personnel staffing
commitments, skill sets and familiar
procedures. May also encounter designer's
lack of familiarity with some types of
prefabricated component detailing. Requires
greater degree of preliminary planning,
engineering and coordination. Market
availability for components may not be
sufficient.
|
Innovative construction methods |
- Roll in: Construct new bridge adjacent to
its final position while maintaining traffic on
the existing structure. Slide new structure
laterally into position after the existing bridge is
removed. Requires construction of temporary
substructures.
- SPMTs: Use SPMTs to quickly remove or install
entire bridge spans – they have virtually no
limit to the load they can carry because their
modular design allows flexibility in configuring
them for a particular load. (Even multiple span
continuous bridge superstructures have been
moved into position by SPMTs.) Requires an area
of adequate size near the travel way to allow the
contractor to construct the new bridge span on
temporary supports and then transport it with
the SPMTs to the bridge site.
- Longitudinal launching: Prefabricate the new
structure at one end of the bridge site and push
into position longitudinally. Eliminates the need
for falsework.
- Cranes: Use cranes in combination with other
equipment such as beam launching trusses to
minimize disruption to traffic. Note: cranes
are the most commonly used equipment for
prefabricated component erection.
|
- Benefits: Requires minimal road closure.
Improves worker safety; using SPMTs allows
the span demolition and construction crews to
perform their work in the relative safety of the
staging area away from traffic. This allows the
work to be done much closer to the ground,
minimizing the consequences if a worker
should lose balance and fall. Improves quality
of construction when work is performed away
from traffic. Improves speed of construction.
- Barriers: Increases cost due to procurement
of specialized subcontractor services. State
lacks experience in developing the appropriate
contractual provisions and procedural
requirements. There are a limited number of
specialized subcontractors with the requisite
equipment and experience, which could mean
a limited availability to perform the work or
a lack of competition to restrain price for the
work.
- Challenges: Need good geometric control to
insure that the new superstructure fits properly
with the substructure when it is moved into
position. Must coordinate traffic control.
Need to assess applicability of site and bridge
type to determine which options are viable.
Locate a feasible staging area during the
planning stage to ensure that the area will be
available to the contractor.
|
Procurement of materials |
- Pre-procure beams, steel H-piles, cement, pre-cast
components, drain pipes and manholes.
|
- Benefits: Guarantees availability of necessary
materials so that work can proceed as planned.
Guards against material price increases during
construction. Guarantees that the item or
material procured is exactly what the designer
anticipated using.
- Barriers: May necessitate owners assuming
ownership of material if is procured before the
contract is awarded. There is little or no space
to store material. Owner does not have staff to
accept, inspect and maintain material in good
condition and therefore is unable to bear the
cost of storing inventory. Material damaged
during storage becomes a loss for the owner.
Price of materials could drop after procurement
of contract. Material incompatibility with
contractor's means, methods or experience
may create a situation where the contractor
resists using it or says that it created problems,
leading to a contract claim.
- Contractor may be able to buy material at a
better price than the owner can.
|
Performance of materials |
- Use HPC for decks, overlays, girders and piers.
- Consider fiber reinforced polymers, i.e., carbon
fiber wrap.
- Utilize HPS. Consider pile type.
|
- Benefits: Provides greater durability and
thus promote greater longevity of service.
An example is the use of low permeability
concrete in bridge decks. It resists penetration
by road salts to a much greater degree
than traditional concrete and thereby
prevents corrosion of reinforcing steel and
the subsequent deterioration of the deck
concrete. Higher strength materials enable
longer spans, leading to fewer substructures.
Higher strength materials also enable shallower
spans to meet roadway vertical clearance
requirements. Lightweight concrete facilitates
construction methods by reducing the weight
of prefabricated components that must be
moved into position. Lightweight material
reduces the structure weight, reducing the size
of foundations and substructures needed.
- Barriers: Need to familiarize parties with
materials: the owner, designer and contractor
do not properly understand the material
characteristics. Owner lacks material
specifications and experience with the
material (or had a bad experience in previous
applications). State has a lack of suppliers
with experience in producing these materials.
Contractors lack experience in the proper
handling and installation of these materials.
The State faces the possibility of very high
material costs due to the unfamiliarity of the
supplier and/or contractor with these materials.
|
Economy of scale |
- Package multiple structures into a single
contract.
- Utilize a phased approach to control
the project sequencing and packaging.
- Use
standardized components and repetitive designs;
this offers benefits to both the designer and the
contractor.
|
- Benefits: Tends to lead to a lower per-unit bid
price for the work. Plus, the cost of any specialized
equipment can be distributed over a larger number of
structures. Larger contracts attract contractors with
greater equipment and manpower capacity. These
contractors may have greater experience in employing
innovative/time-saving construction methods. Smaller
contractors may still be able to perform a portion of
the work by functioning as a subcontractor to the
larger prime. Standardized components and repetitive
structure design reduce design and construction costs;
have a shorter learning curve; and can lead to faster,
better-quality construction. The contractor's familiarity
with standardized components and repetitive structures
may reduce the level of design detail required of the
designer and also reduce the amount of construction
oversight and engineering required. This leads to
fewer contract modifications and a greater ability to
stay on schedule and avoid claims. This simplifies the
coordination needed between contracts.
- Barriers: May encounter resistance from the
contracting community, i.e., the AGC; they may not
be supportive of contracts that are too large for local
association members to handle. Must have consistent
phasing throughout the corridor. Need to check
availability of funding to support a large contract,
particularly when it is performed at a fast pace.
- Challenges: Need to ensure proper phasing of the
work so that multiple structures can be package under
one contract. Need to assure that the funding is in
place to support a large contract. Must complete
all the necessary environmental studies and obtain
approvals to allow the work to proceed.
|
Temporary structures |
- Use temporary structures to maintain traffic flow
with as little interference as possible.
- Demolition
of existing structures and construction of
new ones can be accomplished in a way that
minimizes the need for multiple phases of
work.
- The temporary structure would consist
of a reusable superstructure (examples of
commercially available structures are the Acrow
or Mabey bridges) that is placed on temporary
substructures.
- The substructures may or may
not be reusable.
- Temporary foundations must
be constructed.
- Need to consider contractor
access and temporary substructure bents.
|
- Benefits: Can be used in multiple locations.
Can become the property of the State for use
in a future emergency, i.e., a bridge washout,
where quick response by the ITD is needed.
This offers a value-added component to the
use of a temporary structure. Minimizes or
eliminates the need to perform staging of
bridge work. May simplify traffic control.
Offers a safer environment for workers than
multiple phasing of construction across the
width of the bridge. Improves contractor
access to the work site.
- Barriers: May necessitate more modification
of the bridge approach. Costs more. Need
to allow additional time for the construction
of the temporary substructures. Need to look
at available ROW for temporary bridge and
approaches.
- Coordination: Must coordinate traffic control
to enable the installation and removal of the
temporary structures.
|