<< Previous | Contents | Next >> |
Accelerated Construction Technology Transfer Toolkit
Archived: Sample Materials and Forms
Sample Project Overview
MD 97 (Georgia Avenue) at Randolph Road
Purpose
- Improve vehicular, bicyclists and pedestrian safety
- Improve Levels of Service
- Increase capacity
- Improve mobility and accessibility for the public
Need
- Inadequate capacity
- Safety for motorists, pedestrians and bicyclists
- Inefficient mobility and accessibility
- High accident location
- High Traffic Volumes
- Montgomery County priority project
Overview
- Project Costs
- Preliminary Engineering – $2.7 M (funded)
- Construction – $45.8M (unfunded)
- Right-of-Way Acquisition – $23.8 M (unfunded)
Overview
- Proposed Grade Separation
Limits:
- MD 97 From Mason Street on the south to MD 182 (Layhill Road)
Approximately 1,900 ft
- Randolph Road From 300 ft west of Judson Road to 500 ft east of Glenmont Circle
Approximately 2,200 ft
- MD 97 From Mason Street on the south to MD 182 (Layhill Road)
Overview
MD 97 (Georgia Avenue) at Randolph Road
Overview
- Proposed Grade Separation:
- Randolph Road lowered over 25 ft
- ADT:
- MD 97 – 89,250 (2025)
- Randolph Road – 52,000 (2020)
- Structures:
- (1) Structure carrying MD 97 over Randolph Road
- (4) Retaining Walls
Overview
- Major Utility Relocations:
- PEPCO (Electric) – 69,000 volts
- Verizon (Communications) – Major Communications and Fiberoptics
- Complex Maintenance of Traffic Plan:
- (7) Stages requiring detours to be built to the South to move traffic from the tunnel footprint
- Typical Sections:
- MD 97
- (3) 11'–0" lanes each direction with turning lanes
- 5'-0" outside shoulder, variable width median, sidewalks
- Randolph Road
- (2) 11'–0" lanes each way through tunnel
- On top eastbound – three lanes – lt, lt/thr, rt
- On top westbound – four lanes – two lt, lt/thr, rt
- 8'–0" Shared off street pedestrian/bicycle path
- Sidewalks
- MD 97
Overview
Typical Section – MD 97 (Georgia Ave) North of Randolph Road
Overview
- Profiles:
- MD 97 raised less than 2 ft above existing grade
- Randolph Rd depressed approximately 25 ft below existing grade
- Design Status:
- Plans are approximately 65-70% complete
- Utility Breakout Project - advance construct PEPCO/Verizon (on-going)
- (1) Year Design and (2) Year Construction after design is complete
- Right of Way Plats have been issued
- Permits required:
- Stormwater Management, ESC, DNR Roadside Tree Permit
Overview
Profile – MD 97 Northbound
Project Activities and Schedules
- Location Design Approval – 2002
- Preliminary Engineering Begins – 2003
- Milestone Reviews
- P.I. Review (30%) – January, 2004
- Semi- Final Review (65%) – November, 2004
- Right of Way Plats issued – January, 2007
- ACTT Workshop September 2007
Major Project Challenges
- Utility Relocations
- PEPCO and Verizon (Require 2 year Construction)
- Plan of Action:
- Relocate utilities from beneath the existing intersection to beneath residential streets
- Judson Road
- Sheraton Road
- Relocate utilities from beneath the existing intersection to beneath residential streets
Overview
Judson Road (Left) and Sheraton Road (Right)
Major Project Challenges
- Kensington Volunteer Fire Department (KVFD)
- Property is a total take
- Replacement site and funding for new facility under negotiations between:
- Montgomery County
- KVFD
- Prior to taking of the Existing Facility
- A new site or replacement services at existing locations must be provided prior to condemnation
Major Project Challenges
Kensington Volunteer Fire Department
Major Project Challenges
- Complex Maintenance of Traffic
- Highly urbanized and constrained area
- Properties tight in all four quadrants
- 7 Stage MOT including
- New detour roads to move traffic from footprint of intersection to allow the tunnel structure to be built
Existing Conditions – MD 97 (Georgia Avenue)
MD 97 N. of Randolph Rd Looking South (Left) MD 97 S. of Randolph Rd Looking North (Right)
<< Previous | Contents | Next >> |