Skip to content

P3 VALUE 2.0 Webinars
Session 2A: Value for Money Analysis Exercise Review

February 16, 2016
Related Materials
  • Presentation: PDF  |  HTML 
  • Transcript: HTML
  • Exercise Assignment Answers: Word
  • Webinar recording: Audio

Instructors

Patrick DeCorla-Souza
P3 Program Manager
Center for Innovative Finance Support

Photo of Patrick DeCorla-Souza

Marcel Ham
Vice President
IMG/Rebel

Photo of Marcel Ham

This is a follow-up to the second of five topical webinars to introduce P3-VALUE

  • P3 Evaluation Overview (January 25, 2016)
  • Value for Money Analysis (February 8, 2016)
    • Value for Money Exercise Review (today)
  • Project Delivery Benefit-Cost Analysis
  • Risk Valuation
  • Financial Viability Assessment

Exercise Objective

  • Learn how to compare the Public Sector Comparator to the P3 option to determine which option delivers greater Value-for-Money (VfM) from the perspective of the procuring Agency.
  • Learn how to identify key drivers in the VfM analysis.

Webinar Outline

Introduction: Project Background

Homework Exercise

A study was done previously by a state DOT to estimate Value for Money of P3 delivery for a highway project. The various inputs required for the analysis are included in the P3-VALUE 2.0 spreadsheet model.

Project Information

  • 20 miles highway expansion
  • From 3 lanes to 5 lanes in each direction
    • 3 General Purpose Lanes (GPL)
    • 2 Managed Lanes (ML)
  • Costs (excluding risks and financing):
    • Pre-construction & construction: $425M
    • Routine O&M: $4M per year
    • Major maintenance: $10M (every 8 years)
  • Preconstruction start: 2015 (2 years)
  • Construction start: 2017 (4 years)
  • Operations start: 2021 (40 years)

Questions?

Submit a question using the chat box or hit *6 to ask your question by telephone

Questions from February 8 Webinar

  • Kent Olsen: Why don't you consider DBOM as one of the delivery options in your VfM analysis?
  • HPTE: How do you define the input benefit as opposed to the P3 Efficiencies inputs?
  • Karen Holmes: At what point do variances in project start and completion dates make the data incomparable?

Parts A and B: Toll Concession Analysis

Toll Concession Analysis Steps

  • Part A: Use the Value for Money Analysis training module to:
    1. Review the Public Sector Comparator (PSC)
    2. Review the P3 Option
    3. Compare PSC and P3 Option from the perspective of the Agency
  • Part B: Use the Value for Money Analysis training module to test impact of a higher discount rate

Part A, Step 1: PSC Inputs

Key project information for the PSC in the input sheets of the model:

  • Revenues and their timeline
  • Costs and their timeline
    • Build phase: Pre-construction and construction
    • Operations phase: O&M plus periodic major maintenance
  • Risks (to be covered in topical Webinar 4)
  • Financing fees, which are the upfront costs incurred to arrange public debt
  • Competitive neutrality adjustment to correct for taxation effects in the P3 option

Part A, Step 2: P3 Option Inputs

Key P3 Option inputs are:

  • Revenues: PSC revenues and timeline, but adjusted to take into consideration assumed P3 differences
  • Costs: PSC costs and timeline, but adjusted to take into consideration assumed P3 differences:
    • Build phase: Pre-construction and construction
    • Operations phase: O&M plus periodic major maintenance
  • Risks: Will be covered in Webinar 4
  • Financing conditions:
    • Equity
    • Debt

Part A, Step 3 and Part B

PSC vs. P3 Comparison:

Key input for the comparison is the discount rate to be applied to future cash flows:

  • Discount rate for Part A: State borrowing rate (4%)
  • Discount rate for Part B: Higher rate (5%)

Review of Model Inputs

Please stand by as we open the Excel file

PSC - Outputs

Costs and Revenue under Conventional Delivery
Units>>
NPV @ 4.00% USD m Nominal total USD m
Toll revenues 756 2198
Toll revenues uncertainty adjustment (130) (377)
Pre-construction & construction costs (397) (454)
O&M costs (129) (363)
No Build O&M cost savings 250 680
Base variability (79) (112)
Pure risks (69) (121)
Lifecycle performance risk (228) (574)
Financing fees (3) (3)
Competitive neutrality adjustment - -
Total net revenues / (costs) under Conventional Delivery (29) 873

P3 Option - Bid Calculation

  • Combining all revenues, costs, risks and financing allows the concessionaire to prepare a bid
  • Depending on the structure of the transaction, the bid is either a subsidy/concession fee or availability payment
Costs and Revenues to Developer under P3
Units>>
NPV USD m Nominal total USD m
Toll revenues for private side 298 2224
Pre-construction & construction costs (transferred) (304) (390)
O&M costs (transferred) (43) (296)
Base variability (transferred) (54) (94)
Pure risks (transferred) (40) (98)
Net subsidy from Agency to Developer 146 205
Financing fees (2) (3)
Taxes - -
Total net revenues / (costs) to Developer under P3 0 1548

P3 Option - Agency Revenues/Costs

From the procuring Agency's perspective, the cost of P3 includes the bid as well as any retained costs or risks

P3 Output - Agency Perspective

Costs & revenues to Agency under P3 NPV @ 4.00% Nominal total
Units >> USD m USD m
Toll revenues (for public side) - -
Toll revenues uncertainty adjustment (for public side) - -
Pre-construction & construction costs (retained) (39) (43)
O&M costs (retained) (12) (33)
No Build O&M cost savings 259 691
Base variability (retained) (7) (10)
Pure risks (retained) (6) (11)
Net subsidy from Agency to Developer (175) (205)
Total net revenues / (costs) to Agency under P3 19 389

Compare PSC and P3 Option

  • Part A (4% discount rate):
    • NPV of net revenues/cost to Agency under PSC $(29) M
    • NPV of net cash flows to Agency under P3 $19 M
    • NPV of difference (= VfM) $48 M
  • Part B (5% discount rate):
    • NPV of net revenues/cost to Agency under PSC $(63) M
    • NPV of net cash flows to Agency under P3 $(18) M
    • NPV of difference (= VfM) $45 M

Questions?

Submit a question using the chat box

Parts C and D: Availability Payment Concession

  • Part C: Use the Value for Money Analysis training module to:
    1. Review the Public Sector Comparator (PSC)
    2. Review the P3 Option
    3. Compare PSC and P3 Option from the perspective of the Agency
  • Part D: Use the Value for Money Analysis training module to test impact of elimination of the assumed P3 cost efficiencies

Part C, Step 1: PSC Inputs

Key project information for the PSC in the input sheets of the model are the same as for the Toll Concession option:

  • Revenues and their timeline
  • Costs and their timeline
    • Build phase: Pre-construction and construction
    • Operations phase: O&M plus periodic major maintenance
  • Risks (to be covered in topical Webinar 4)
  • Financing fees, which are the upfront costs incurred to arrange public debt
  • Competitive neutrality adjustment to correct for taxation effects in the P3 option

Part C, Step 2: P3 Option Inputs

AP P3 Option inputs that are the same as the Toll Concession are:

  • Revenues: PSC revenues and timeline, but adjusted to take into consideration assumed P3 differences
  • Costs: PSC costs and timeline, but adjusted to take into consideration assumed P3 differences:
    • Build phase: Pre-construction and construction
    • Operations phase: O&M plus periodic major maintenance

AP P3 Option inputs that are different from the Toll Concession are:

  • Financing conditions:
    • Equity
    • Debt

Part C, Step 3 and Part D

Part C: Base case PSC vs. P3 Comparison:

Key input for the comparison is the discount rate to be applied to future cash flows:

  • Discount rate (same as for Toll Concession): 4%

Part D: For evaluation of impact of P3 efficiencies on the PSC vs. P3 Comparison:

  1. Construction timing -- Eliminate early completion of P3 construction
  2. Construction cost -- Eliminate reduction in P3 pre-construction and construction costs
  3. Operations cost -- Eliminate reduction in P3 operations phase costs

Review of Model Inputs

Please stand by as we open the Excel file

PSC - AP Concession Outputs

Costs and Revenue under Conventional Delivery
Units>>
NPV @ 4.00% USD m Nominal total USD m
Toll revenues 756 2198
Toll revenues uncertainty adjustment (130) (377)
Pre-construction & construction costs (397) (454)
O&M costs (129) (363)
No Build O&M cost savings 250 680
Base variability (79) (112)
Pure risks (69) (121)
Lifecycle performance risk (228) (576)
Financing fees (3) (3)
Competitive neutrality adjustment - -
Total net revenues / (costs) under Conventional Delivery (29) 872

AP P3 Option - Bid Calculation

  • Combining all revenues (i.e., agency upfront or milestone payments to the concessionaire), costs, risks and financing allows the concessionaire to prepare a bid
  • The bid is an availability payment

AP P3 Output - Bid Calculation

Costs and Revenues to Developer under P3
Units>>
NPV @ 7.24% USD m Nominal total USD m
Toll revenues for private side - -
Pre-construction & construction costs (transferred) (318) (390)
O&M costs (transferred) (57) (296)
Base variability (transferred) (58) (94)
Pure risks (transferred) (44) (98)
Availability Payment & milestone payment to Developer 479 1,837
Financing fees (3) (4)
Taxes - -
Total net revenues / (costs) to Developer under P3 0 955

AP P3 Option - Agency Perspective

From the procuring Agency's perspective, the cost of P3 includes the bid as well as any retained costs or risks

Costs and Revenues to Agency under P3
Units>>
NPV @ 4.00% USD m Nominal total USD m
Toll revenues (for public side) 777 2,224
Toll revenues uncertainty adjustment (for public side) (133) (381)
Pre-construction & construction costs (retained) (39) (43)
O&M costs (retained) (12) (33)
No Build O&M cost savings 259 691
Base variability (retained) (7) (10)
Pure risks (retained) (6) (11)
Availability Payment & milestone payment to Developer (794) (1,837)
Total net revenues / (costs) to Agency under P3 45 600

Compare PSC and P3 Option

Part C (AP concession):

  • NPV of net revenues/cost to Agency under PSC $(29) M
  • NPV of net cash flows to Agency under P3 $45 M
  • NPV of difference (= VfM) $74 M

Part D (AP concession with no early completion):

  • NPV of net revenues/cost to Agency under PSC $(32) M
  • NPV of net cash flows to Agency under P3 $(22) M
  • NPV of difference (= VfM) $54 M

Compare PSC and P3 Option

Part D (AP concession with no early completion and no P3 build phase cost efficiencies):

  • NPV of net revenues/cost to Agency under PSC $(32) M
  • NPV of net cash flows to Agency under P3 $(39) M
  • NPV of difference (= VfM) $(7) M

Part D (AP concession with no early completion and no P3 build and operations phase cost efficiencies):

  • NPV of net revenues/cost to Agency under PSC $(32) M
  • NPV of net cash flows to Agency under P3 $(52) M
  • NPV of difference (= VfM) $(20) M

Questions?

Submit a question using the chat box

Webinar Summary

Webinar Recap

Intro Project Background

Parts A & B Toll Concession

Part C & D Availability Payment Concession

Recap Summary of Webinar

Upcoming P3-VALUE Training

  • February 22 Project Delivery Benefit Cost Analysis
  • March 7 Risk Valuation
  • March 21 Financial Viability Assessment

Tool and References

Resources

FHWA's Center for Innovative Finance Support Website:
https://www.fhwa.dot.gov/ipd/

P3 Website:
https://www.fhwa.dot.gov/ipd/p3/

Questions?

Submit a question using the chat box

Contact Information

Patrick DeCorla-Souza
P3 Program Manager
Center for Innovative Finance Support
Federal Highway Administration
(202) 366-4076
Patrick.DeCorla-Souza@dot.gov

back to top