U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

 
REPORT
This report is an archived publication and may contain dated technical, contact, and link information
Back to Publication List        
Publication Number:  FHWA-HRT-16-053     Date:  October 2016
Publication Number: FHWA-HRT-16-053
Date: October 2016

 

Application and Validation of Remaining Service Interval Framework for Pavements

CHAPTER 6. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS

SUMMARY

The RSI concept was developed to provide an alternative to the long-standing and confusing RSL terminology. The RSI concept does not provide an alternative to assessing the health of the network or making decisions about how to spend available funds. It simply provides a clear terminology and a logical process that will create a consistent construction event-based terminology and understanding (i.e., types of construction events and the timing of those events within the concept of LCC and/or other prioritization approaches based on streams of future construction events). An added benefit of adopting the RSI terminology is that the methodology provides a readily available way to communicate impacts of alternate budget scenarios. The RSI concept considers the complete M&R activity of the pavement system and does not simply consider the end of life as promulgated by the RSL philosophy.

While threshold values can be used to determine the time until future construction events are needed, in the original formulation of RSI, LCC optimization was recommended to determine when preservation, rehabilitation, and reconstruction are needed. During this project, an LCC algorithm was developed that finds the optimum time for treatment subject to threshold constraints based on meeting minimum LOS. This algorithm was used during the validation effort based on the MDSHA network.

Reconstruction is one cost (with the caveat that the user costs are not included), and the resulting condition is the same (new) no matter the pretreatment condition, unlike preservation and rehabilitation treatment. The threshold for reconstruction can be considered the minimum LOS and structural condition when lower-level treatments are no longer cost effective. At this time, the RSI for any treatment should remain zero, essentially reflecting that treatment is needed. This is different than RSI numerics for preservation and rehabilitation because once either of these values reach zero, non-zero values of RSI should still exist for at least one other treatment category. As the condition of the pavement continues to deteriorate beyond the minimum LOS, the RSI remains zero, signaling that treatment is still needed. As a way to improve communication of this need, the years past due can also be used in conjunction with an RSI of zero. For instance, take two pavement sections that have both exceed the reconstruction thresholds; one section has just exceeded the threshold this year, and the other section exceeded the threshold 2 years ago. Both pavement sections have an RSI of zero for all treatments, but the second pavement section could be said to be past due by 2 years. An agency should not have many pavements with an entire string of zeros representing the RSI, and therefore, each of the cases should be treated individually as needed.

As the RSI concept evolved to represent a more ideal system based on optimizing the treatment selection considering all possible treatments and treatment timings instead of being threshold driven, it is no longer an issue to consider more than one type of construction trigger. The evolution from a change in terminology to a change in approach resulted in all construction triggers (i.e., preservation, rehabilitation, or reconstruction) and minimum LOS being considered in selecting the optimum treatments. The resulting RSI numerics represent the optimum and do not focus on one type of construction trigger.

Summary Observations from Project-Level Analyses

The following observations sumarize the most important findings and conclusions from the RSI concept validation effort performed at the project level presented in chapter 4:

Summary Observations from Network-Level Analyses

The following observations sumarize the most important findings and conclusions from the RSI concept validation effort performed at the network level presented in chapter 5:

CONCLUSIONS

The results from the validation efforts presented in this report support the conclusion that the RSI represents a valid approach to determining and communicating future M&R needs of a pavement instead of defining pavement life using a single number. The results in chapter 5 showed that the remaining life is essentially not related to the time until the next pavement treatment in an optimal strategy. In addition, developing optimal strategies for pavement management at the project level (chapter 4) and network level (chapter 5) represents enhanced approaches to planning pavement M&R needs.

Based on the validation results from chapters 4 and 5, it can be concluded that optimal pavement management decisions should not be predicated on condition-based threshold values for treatments. Instead, optimal pavement management strategies may include the application of treatments well before a threshold condition is reached. Therefore, an important step toward the implementation of the RSI is the development of a procedure to determine optimal strategies for pavement M&R scheduling.

RECOMMENDATIONS

As a result of the validation and application of the RSI concept efforts at the project, network, and strategic levels, the following recommendations are provided:

 

 

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101