U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Federal Highway Administration Research and Technology
Coordinating, Developing, and Delivering Highway Transportation Innovations

 
REPORT
This report is an archived publication and may contain dated technical, contact, and link information
Back to Publication List        
Publication Number:  FHWA-HRT-17-013     Date:  February 2017
Publication Number: FHWA-HRT-17-013
Date: February 2017

 

Hydraulic Performance of Shallow Foundations for The Support of Vertical-Wall Bridge Abutments

CHAPTER 1. BACKGROUND AND OBJECTIVES

Scour at the base of bridge abutments during floods is a common cause of bridge failure in the United States. Shallow abutment foundations located at or near the channel banks are considered more vulnerable than other foundations because they are closer to the streambed and can significantly constrict flood flows. These types of abutments are frequently implemented for single-span bridges, and scour countermeasures are often integrated into the design to avoid placing the foundation below local scour depth. About 80 percent of the more than 600,000 bridges over water in the U.S. national bridge inventory are single-span bridges 70 to 90 ft (21 to 28 m) in length.(1) Therefore, to protect small single-span bridge abutments built on shallow foundations from scour damage, methods for countermeasure design are needed that consider the abutment foundation and scour countermeasures as an integrated component of the bridge.

Extensive research has been conducted to determine the depth and location of the scour hole that develops around a bridge abutment. Design equations and procedures for estimating contraction scour and local abutment scour are provided in Hydraulic Engineering Circular (HEC)-18, Evaluating Scour at Bridges.(2) In recent years, risk-based design has been recommended in HEC-18. A risk-based design considers the need to provide safe and reliable waterway crossings while also taking into account the economic consequences and probability of failure.

One strategy that has emerged from this risk-based approach is the use of riprap to protect abutments, particularly for small bridges. At the time of this report, using riprap to protect abutments was the current design approach for vertical-wall abutments built on spread footings. The approach was to place the top of the foundation or footing below the depth of the sum of contraction scour and long-term degradation (LTD) referenced to the thalweg of the main channel and to provide rock riprap to protect the abutment from local scour. HEC-23, Bridge Scour and Stream Instability Countermeasures, provides guidelines for designing abutment scour countermeasures.(3)

New bridge construction techniques also increased the need for guidance for design and construction of vertical-wall abutments on shallow foundations. The Federal Highway Administration (FHWA) has promoted the use of geosynthetic reinforced soil-integrated bridge systems (GRS-IBS) founded on reinforced soil foundations (RSFs). While the study described in this report was not exclusively focused on this bridge type, an important goal was to specify appropriate application of riprap aprons for these systems and their abutment foundations.

Contraction scour occurs when a channel is narrowed by a bridge opening where the abutments constrain the flow, as shown in part A of figure 1. The flow accelerates in the contraction, increasing the bed shear stress and causing removal of bed materials. The flow depth in the contraction increases until equilibrium conditions are reached. The clear-water contraction scour equation recommended in HEC-18 is based on a development suggested by Laursen that assumes the flow transitions from uniform flow in the upstream approach section to a different uniform flow condition in the contracted section.(2,4) In Laursen’s analysis, the contraction scour depth (yc) is a function of the design discharge (Q) through the bridge opening, the pre-scour depth in the opening (y0), the median bed material size (D50), and the width of the bridge opening (W2). The contraction scour and LTD of the channel are assumed to lower the streambed across the entire channel. The local abutment scour, ys, occurs at the abutment because of the turbulence caused in the flow by the abutment.

In section A of this figure, a stream cross section between two vertical wall abutments with shallow foundations is shown. The figure defines W sub 2 as the bridge opening width, Q as the discharge, and y sub 0 as the design flow depth. It indicates a lowering of the original cross section by the sum of the contraction scour, y sub c, and the long-term degradation. The elevation at the lower extent of the abutment scour, y sub s is shown. In section B, the same cross section is shown with riprap aprons placed at the base of the abutment walls extending into the channel by a distance of W sub riprap. The figure notes that the flow field adjusts to changes in bed roughness, increasing bed shear stress on the unprotected soil because tau sub R is greater than tau sub 0. In section C, the same cross section is shown with additional scour in the unprotected part of the channel to a depth of y sub cR plus long-term degradation. Some of the rocks from the apron have fallen into the larger scour area thereby potentially undermining the foundation.
τo = average bed shear stress in contracted section without riprap before scour
τc = critical shear stress on bed for model without riprap
τR = average bed shear stress in contracted section between riprap aprons with scour at a depth of yc
WR = riprap apron width (ft (m))
ycR = maximum contraction scour depth with partial-width riprap scour countermeasures
Deg. = Degradation.
Elev. = Elevation.
Figure 1. Drawing. Effect of an abutment riprap apron on contraction scour.

 

A countermeasure against abutment scour is to place a riprap apron around the abutment to a width of WR, as shown in part B of figure 1. HEC-23 provides guidelines for minimum apron thickness and extent to protect the abutment foundation from the induced local scouring vortices.(3)

However, the introduction of this heterogeneous roughness (riprap versus native bed materials) in the bridge opening alters the flow, initially manifesting as strong secondary currents originating from the transition in surface roughness. An experimental investigation by Petersen et al. demonstrated how the generated flow turbulence laterally diffused from the rough section over the riprap apron into the smoother bed sediment section.(5)

As shown in part C of figure 1, the adjustment of the flow to the change in bed roughness leads to an increased bed shear stress, τR, on the unprotected natural bed material, leading to a deeper contraction scour depth, ycR, than would have occurred without the riprap protection. This increased depth can cause instability of the riprap apron and may ultimately cause riprap movement beginning at the apron edges.

The research study described in this report was designed to provide a more complete picture of the flow field and local bed shear stresses on heterogeneous bed roughness in the bridge opening. A series of physical and numerical simulations were conducted to achieve two main objectives: (1)quantify the change in shear stress adjacent to riprap aprons and (2) provide updated design guidance for riprap protection at vertical-wall abutments on shallow foundations in narrow contractions.

In addition to this introductory chapter, chapter 2 of this report summarizes the annotated literature search for this study. Chapter 3 describes the development of a conceptual model for the increased shear in the middle of the contracted channel (bridge) section. Chapters 4 and 5 describe the setup and results of the physical and numerical modeling, respectively. Based on the conceptual model and the results of the physical and numerical modeling, design guidance for riprap aprons for vertical-wall abutments with shallow foundations is provided in chapter 6. Chapter 7 briefly summarizes this research and presents recommendations for future research. Appendix A is an annotated review of the literature. Appendices B and C present the equilibrium scour maps from the physical experiments conducted in this study and the computational fluid dynamics (CFD) sheer stress and velocity distribution maps, respectively. Appendix D presents proposed guidance on the hydraulic requirements for shallow abutment foundations developed based on this research.

 

 

Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000
Turner-Fairbank Highway Research Center | 6300 Georgetown Pike | McLean, VA | 22101