Instructors
Patrick DeCorla-Souza
P3 Program Manager
Center for Innovative Finance Support

Marcel Ham
Vice President
IMG/Rebel

This is a follow-up to the second of five topical webinars to introduce P3-VALUE
- P3 Evaluation Overview (January 25, 2016)
- Value for Money Analysis (February 8, 2016)
- Value for Money Exercise Review (today)
- Project Delivery Benefit-Cost Analysis
- Risk Valuation
- Financial Viability Assessment
Exercise Objective
- Learn how to compare the Public Sector Comparator to the P3 option to determine which option delivers greater Value-for-Money (VfM) from the perspective of the procuring Agency.
- Learn how to identify key drivers in the VfM analysis.
Webinar Outline
Introduction: Project Background
Homework Exercise
A study was done previously by a state DOT to estimate Value for Money of P3 delivery for a highway project. The various inputs required for the analysis are included in the P3-VALUE 2.0 spreadsheet model.
Project Information
- 20 miles highway expansion
- From 3 lanes to 5 lanes in each direction
- 3 General Purpose Lanes (GPL)
- 2 Managed Lanes (ML)
- Costs (excluding risks and financing):
- Pre-construction & construction: $425M
- Routine O&M: $4M per year
- Major maintenance: $10M (every 8 years)
- Preconstruction start: 2015 (2 years)
- Construction start: 2017 (4 years)
- Operations start: 2021 (40 years)
Questions?
Submit a question using the chat box or hit *6 to ask your question by telephone
Questions from February 8 Webinar
- Kent Olsen: Why don't you consider DBOM as one of the delivery options in your VfM analysis?
- HPTE: How do you define the input benefit as opposed to the P3 Efficiencies inputs?
- Karen Holmes: At what point do variances in project start and completion dates make the data incomparable?
Parts A and B: Toll Concession Analysis
Toll Concession Analysis Steps
- Part A: Use the Value for Money Analysis training module to:
- Review the Public Sector Comparator (PSC)
- Review the P3 Option
- Compare PSC and P3 Option from the perspective of the Agency
- Part B: Use the Value for Money Analysis training module to test impact of a higher discount rate
Part A, Step 1: PSC Inputs
Key project information for the PSC in the input sheets of the model:
- Revenues and their timeline
- Costs and their timeline
- Build phase: Pre-construction and construction
- Operations phase: O&M plus periodic major maintenance
- Risks (to be covered in topical Webinar 4)
- Financing fees, which are the upfront costs incurred to arrange public debt
- Competitive neutrality adjustment to correct for taxation effects in the P3 option
Part A, Step 2: P3 Option Inputs
Key P3 Option inputs are:
- Revenues: PSC revenues and timeline, but adjusted to take into consideration assumed P3 differences
- Costs: PSC costs and timeline, but adjusted to take into consideration assumed P3 differences:
- Build phase: Pre-construction and construction
- Operations phase: O&M plus periodic major maintenance
- Risks: Will be covered in Webinar 4
- Financing conditions:
Part A, Step 3 and Part B
PSC vs. P3 Comparison:
Key input for the comparison is the discount rate to be applied to future cash flows:
- Discount rate for Part A: State borrowing rate (4%)
- Discount rate for Part B: Higher rate (5%)
Review of Model Inputs
Please stand by as we open the Excel file
PSC - Outputs
Costs and Revenue under Conventional Delivery
Units>> |
NPV @ 4.00% USD m |
Nominal total USD m |
| Toll revenues |
756 |
2198 |
| Toll revenues uncertainty adjustment |
(130) |
(377) |
| Pre-construction & construction costs |
(397) |
(454) |
| O&M costs |
(129) |
(363) |
| No Build O&M cost savings |
250 |
680 |
| Base variability |
(79) |
(112) |
| Pure risks |
(69) |
(121) |
| Lifecycle performance risk |
(228) |
(574) |
| Financing fees |
(3) |
(3) |
| Competitive neutrality adjustment |
- |
- |
| Total net revenues / (costs) under Conventional Delivery |
(29) |
873 |
P3 Option - Bid Calculation
- Combining all revenues, costs, risks and financing allows the concessionaire to prepare a bid
- Depending on the structure of the transaction, the bid is either a subsidy/concession fee or availability payment
Costs and Revenues to Developer under P3
Units>> |
NPV USD m |
Nominal total USD m |
| Toll revenues for private side |
298 |
2224 |
| Pre-construction & construction costs (transferred) |
(304) |
(390) |
| O&M costs (transferred) |
(43) |
(296) |
| Base variability (transferred) |
(54) |
(94) |
| Pure risks (transferred) |
(40) |
(98) |
| Net subsidy from Agency to Developer |
146 |
205 |
| Financing fees |
(2) |
(3) |
| Taxes |
- |
- |
| Total net revenues / (costs) to Developer under P3 |
0 |
1548 |
P3 Option - Agency Revenues/Costs
From the procuring Agency's perspective, the cost of P3 includes the bid as well as any retained costs or risks
P3 Output - Agency Perspective
| Costs & revenues to Agency under P3 |
NPV @ 4.00% |
Nominal total |
| Units >> |
USD m |
USD m |
| Toll revenues (for public side) |
- |
- |
| Toll revenues uncertainty adjustment (for public side) |
- |
- |
| Pre-construction & construction costs (retained) |
(39) |
(43) |
| O&M costs (retained) |
(12) |
(33) |
| No Build O&M cost savings |
259 |
691 |
| Base variability (retained) |
(7) |
(10) |
| Pure risks (retained) |
(6) |
(11) |
| Net subsidy from Agency to Developer |
(175) |
(205) |
| Total net revenues / (costs) to Agency under P3 |
19 |
389 |
Compare PSC and P3 Option
- Part A (4% discount rate):
- NPV of net revenues/cost to Agency under PSC $(29) M
- NPV of net cash flows to Agency under P3 $19 M
- NPV of difference (= VfM) $48 M
- Part B (5% discount rate):
- NPV of net revenues/cost to Agency under PSC $(63) M
- NPV of net cash flows to Agency under P3 $(18) M
- NPV of difference (= VfM) $45 M
Questions?
Submit a question using the chat box
Parts C and D: Availability Payment Concession
- Part C: Use the Value for Money Analysis training module to:
- Review the Public Sector Comparator (PSC)
- Review the P3 Option
- Compare PSC and P3 Option from the perspective of the Agency
- Part D: Use the Value for Money Analysis training module to test impact of elimination of the assumed P3 cost efficiencies
Part C, Step 1: PSC Inputs
Key project information for the PSC in the input sheets of the model are the same as for the Toll Concession option:
- Revenues and their timeline
- Costs and their timeline
- Build phase: Pre-construction and construction
- Operations phase: O&M plus periodic major maintenance
- Risks (to be covered in topical Webinar 4)
- Financing fees, which are the upfront costs incurred to arrange public debt
- Competitive neutrality adjustment to correct for taxation effects in the P3 option
Part C, Step 2: P3 Option Inputs
AP P3 Option inputs that are the same as the Toll Concession are:
- Revenues: PSC revenues and timeline, but adjusted to take into consideration assumed P3 differences
- Costs: PSC costs and timeline, but adjusted to take into consideration assumed P3 differences:
- Build phase: Pre-construction and construction
- Operations phase: O&M plus periodic major maintenance
AP P3 Option inputs that are different from the Toll Concession are:
Part C, Step 3 and Part D
Part C: Base case PSC vs. P3 Comparison:
Key input for the comparison is the discount rate to be applied to future cash flows:
- Discount rate (same as for Toll Concession): 4%
Part D: For evaluation of impact of P3 efficiencies on the PSC vs. P3 Comparison:
- Construction timing -- Eliminate early completion of P3 construction
- Construction cost -- Eliminate reduction in P3 pre-construction and construction costs
- Operations cost -- Eliminate reduction in P3 operations phase costs
Review of Model Inputs
Please stand by as we open the Excel file
PSC - AP Concession Outputs
Costs and Revenue under Conventional Delivery
Units>> |
NPV @ 4.00% USD m |
Nominal total USD m |
| Toll revenues |
756 |
2198 |
| Toll revenues uncertainty adjustment |
(130) |
(377) |
| Pre-construction & construction costs |
(397) |
(454) |
| O&M costs |
(129) |
(363) |
| No Build O&M cost savings |
250 |
680 |
| Base variability |
(79) |
(112) |
| Pure risks |
(69) |
(121) |
| Lifecycle performance risk |
(228) |
(576) |
| Financing fees |
(3) |
(3) |
| Competitive neutrality adjustment |
- |
- |
| Total net revenues / (costs) under Conventional Delivery |
(29) |
872 |
AP P3 Option - Bid Calculation
- Combining all revenues (i.e., agency upfront or milestone payments to the concessionaire), costs, risks and financing allows the concessionaire to prepare a bid
- The bid is an availability payment
AP P3 Output - Bid Calculation
Costs and Revenues to Developer under P3
Units>> |
NPV @ 7.24% USD m |
Nominal total USD m |
| Toll revenues for private side |
- |
- |
| Pre-construction & construction costs (transferred) |
(318) |
(390) |
| O&M costs (transferred) |
(57) |
(296) |
| Base variability (transferred) |
(58) |
(94) |
| Pure risks (transferred) |
(44) |
(98) |
| Availability Payment & milestone payment to Developer |
479 |
1,837 |
| Financing fees |
(3) |
(4) |
| Taxes |
- |
- |
| Total net revenues / (costs) to Developer under P3 |
0 |
955 |
AP P3 Option - Agency Perspective
From the procuring Agency's perspective, the cost of P3 includes the bid as well as any retained costs or risks
Costs and Revenues to Agency under P3
Units>> |
NPV @ 4.00% USD m |
Nominal total USD m |
| Toll revenues (for public side) |
777 |
2,224 |
| Toll revenues uncertainty adjustment (for public side) |
(133) |
(381) |
| Pre-construction & construction costs (retained) |
(39) |
(43) |
| O&M costs (retained) |
(12) |
(33) |
| No Build O&M cost savings |
259 |
691 |
| Base variability (retained) |
(7) |
(10) |
| Pure risks (retained) |
(6) |
(11) |
| Availability Payment & milestone payment to Developer |
(794) |
(1,837) |
| Total net revenues / (costs) to Agency under P3 |
45 |
600 |
Compare PSC and P3 Option
Part C (AP concession):
- NPV of net revenues/cost to Agency under PSC $(29) M
- NPV of net cash flows to Agency under P3 $45 M
- NPV of difference (= VfM) $74 M
Part D (AP concession with no early completion):
- NPV of net revenues/cost to Agency under PSC $(32) M
- NPV of net cash flows to Agency under P3 $(22) M
- NPV of difference (= VfM) $54 M
Compare PSC and P3 Option
Part D (AP concession with no early completion and no P3 build phase cost efficiencies):
- NPV of net revenues/cost to Agency under PSC $(32) M
- NPV of net cash flows to Agency under P3 $(39) M
- NPV of difference (= VfM) $(7) M
Part D (AP concession with no early completion and no P3 build and operations phase cost efficiencies):
- NPV of net revenues/cost to Agency under PSC $(32) M
- NPV of net cash flows to Agency under P3 $(52) M
- NPV of difference (= VfM) $(20) M
Questions?
Submit a question using the chat box
Webinar Summary
Webinar Recap
Intro Project Background
Parts A & B Toll Concession
Part C & D Availability Payment Concession
Recap Summary of Webinar
Upcoming P3-VALUE Training
- February 22 Project Delivery Benefit Cost Analysis
- March 7 Risk Valuation
- March 21 Financial Viability Assessment
Tool and References
Resources
FHWA's Center for Innovative Finance Support Website:
https://www.fhwa.dot.gov/ipd/
P3 Website:
https://www.fhwa.dot.gov/ipd/p3/
Questions?
Submit a question using the chat box
Contact Information
Patrick DeCorla-Souza
P3 Program Manager
Center for Innovative Finance Support
Federal Highway Administration
(202) 366-4076
Patrick.DeCorla-Souza@dot.gov