Table FA-4A
OVERVIEW:
Section 1101(a)(1)(B) of MAP-21 authorizes a total of $37,798,000,000 for the Federal-aid highway apportioned programs.
In FY14, the State receives a total apportionment share equal to the State's share of FY12 formula funds. The resulting total apportionment is adjusted, if necessary, to ensure that the State receives at least 95% of the dollar amount of its contributions to the Highway Account of the Highway Trust Fund. After determining the total apportioment for a State, MAP-21 divides that apportionment among the State's individual formula programs in the following manner:
Program | Statute | Method | Formulas |
---|---|---|---|
Congestion Mitigation and Air Quality Improvement Program (CMAQ) | [23 USC 104(b)(4)] | Funded in an amount equal to the State's total apportionment multiplied by the following ratio: | State's FY09 CMAQ $ State's total FY09 apportionments |
Metropolitian Planning | [23 USC 104(b)(5)] | Funded in an amount equal to the State's total apportionment multiplied by the following ratio: | State's FY09 Metro Planning $ State's total FY09 apportionments |
National Highway Performance Program (NHPP) | [23 USC 104(b)(1)] | The remainder (net of CMAQ and Metro Planning) is divided based on the following proportions: | 63.7% to NHPP |
Surface Transportation Program (STP) | [23 USC 104(b)(2)] | 29.3% to STP | |
Highway Safety Improvement Program (HSIP) | [23 USC 104(b)(3)] | 7.0% to HSIP | |
Railway Highway Crossings | [23 USC 130] | Funded with an amount set aside from the State's HSIP apportionment –
|
|
Transportation Alternatives (TA) | [§1122; 23 USC 213] | Funded via setaside from NHPP, STP, HSIP, CMAQ, & Metro Planning:
|
Source: FHWA Map-21 Fact Sheets/FHWA Notice 4510.774