Skip to content

Case Study: NYSDOT New York Works Accelerated Bridge Program

Download Case Study as PDF

NYSDOT Works Logo
Name of Agency

New York State Department of Transportation (NYSDOT)

Location

Statewide

Project Delivery Method

Design-Bid-Build (D-B-B) and Design-Build (D-B)

Procurement Method

Low Bid (D-B-B) and Best Value (D-B)

Total Project Cost
  • $135 million for 81 bridge deck replacements in 9 bundles (D-B-B Program)
  • $84 million for 35 bridge deck replacements in 3 bundles (D-B Program)
Funding Source

Appropriated in annual funding process using existing state and federal funds

Construction Schedule

116 bridge deck replacements in 2 years

Project Description

This was a fast-paced program to replace bridge decks on 116 bridges over a period of 2 years. The goal was to get New Yorkers back to work during the slow economy in 2012 and 2013. Both D-B-B and D-B project delivery methods were used to deliver bridge bundles to complete the work.

The D-B-B projects were bundled with efforts to maximize efficiency in design and construction. Designs were proposal-only packages, meaning that they were typically produced on 8.5" x 11" paper and contained requirements for construction with minimum details. This allowed the contractors flexibility in construction. The contractor was responsible for existing survey and final deck grades. NYSDOT bridge designers stayed involved during construction to ensure that contractors' details met the requirements in the plans and NYSDOT standards. NYSDOT also gave the contractors flexibility with the order in which they worked on the bridges. Contractors became more efficient as they learned lessons from bridges constructed early in the bundle. NYSDOT incorporated lessons learned into later bundles.

The D-B projects were bundled by the zones in which they were located. These projects were typically more complex than were the D-B-B projects. The D-B projects were awarded based on best value. One of the D-B bundles in western New York covered too large of a geographical area. This led to a high bid by a joint venture team of three contractors. The bids were rejected, and the projects were designed by using D-B-B and bundled into smaller packages in closer proximity.

The New York works bridge deck replacements are a great example of efficiencies gained in design and construction using bridge bundling.

Project Website https://www.governor.ny.gov/news/governor-cuomo-announces-accelerated-road-and-bridge-projects-central-new-york-part-ny-works

Summary

Program Goals

Goal was to quickly reduce the number of bridge decks in poor condition and to keep them from becoming poor for at least a period of 10 years. Another goal was to get New Yorkers back to work, leading to a very aggressive schedule.

Bridge Selection Criteria
  • State owned.
  • Bridge deck in poor condition.
  • No right-of-way takes.
  • Minimal environmental issues.
  • Minimal utility relocations.
  • Minimal bridges involving a railroad.
  • No historic bridges.
  • Minimal roadway approach work.
  • No aesthetic considerations. Work horse bridges.
Delivery and Procurement Method
  • D-B-B, Low Bid
  • D-B, Best Value (60% Price/40% Technical Score)
Funding Sources, Financing Strategy
  • Appropriated in annual funding process with existing state and federal funds.
  • Spent $219 million in just 2 years.
Environmental, Right-of-Way, and Utility Considerations
  • Projects were within existing right-of-way.
  • Avoided locations with significant utility involvement; contractors responsible for utility relocations (D-B projects).
  • All bridges were categorical exclusions.
Risks

There was minimal risk associated with these deck replacements. Most of the risk was on the contractor. Even the D-B-B contracts had minimal details, making the contractor responsible for ensuring that the new decks were at the proper grade.

Owner Management/Quality Assurance
  • D-B-B projects put together by the Structures Design Bureau. Designers stayed involved through construction.
  • D-B projects run by NYSDOT D-B program.
  • D-B teams performed CI with QC by NYSDOT.
Stakeholder Communication

The New York Works program was so fast-paced that no advance communication was performed. All bridges were state-owned, and work was within existing right-of-way.

back to top