GTR Review Checklist for Retaining Structures
E. Retaining Structures
(See "Earth Retaining Structures" FHWA NHI-99-025)
In addition to the basic information listed in Section A, is the following information provided in the project geotechnical report?
-
*Recommended soil strength parameters and groundwater elevations for use in computing wall design lateral earth pressures and factor of safety for overturning, sliding, and external slope stability.
(Yes / No / Unknown or N/A)
-
Is it proposed to bid alternate wall designs?
(Yes / No / Unknown or N/A)
-
*Are acceptable reasons given for the choice and/or exclusion of certain wall types?
(Yes / No / Unknown or N/A)
-
*Is an analysis of the wall stability included with minimum acceptable factors of safety against overturning (F.S. = 2.0), sliding (F.S. = 1.5), and external slope stability (F.S. = 1.5)?
(Yes / No / Unknown or N/A)
-
If wall will be placed on compressible foundation soils, is estimated total, differential and time rate of settlement given?
(Yes / No / Unknown or N/A)
-
Will wall types selected for compressible foundation soils allow differential movement without distress?
(Yes / No / Unknown or N/A)
-
Are wall drainage details, including materials and compaction, provided?
(Yes / No / Unknown or N/A)
Construction Considerations
-
Are excavation requirements covered including safe slopes for open excavations or need for sheeting or shoring?
(Yes / No / Unknown or N/A)
-
Fluctuation of groundwater table?
(Yes / No / Unknown or N/A)
Top-down Construction Type Walls
(See "Manual for Design & Construction Monitoring of Soil Nail Walls", FHWA SA-96-069R and "Ground Anchors and Anchored Systems", FHWA IF-99-015)
-
*For soil nail and anchor walls are the following included in the geotechnical report?
-
Design soil parameters (φ, c, γ)
(Yes / No / Unknown or N/A)
-
Minimum bore size (soil nails)?
(Yes / No / Unknown or N/A)
-
Design pullout resistance (soil nails)?
(Yes / No / Unknown or N/A)
-
Ultimate anchor capacity (anchors)?
(Yes / No / Unknown or N/A)
-
Corrosion protection requirements?
(Yes / No / Unknown or N/A)
*A response other than (yes) or (N/A) for any of these checklist questions is cause to contact the appropriate geotechnical engineer for a clarification and/or to discuss the project.