AP | Availability Payment |
BCA | Benefit Cost Analysis |
BS | Balance Sheet |
CF | Cash Flow |
CFADS | Cash Flows Available to Debt Service |
DSCR | Debt Service Coverage Ratio |
DSRA | Debt Service Reserve Account |
GPL | General Purpose Lanes |
IRI | International Roughness Index |
IRR | Internal Rate of Return |
ML/TL | Managed Lanes or Tolled Lanes |
MMRA | Major Maintenance Reserve Account |
O&M | Operations and Maintenance |
PDBCA | Project Delivery Benefit-Cost Analysis |
P&L | Profit & Loss |
PSC | Public Sector Comparator or Conventional Delivery |
P3 | Public-Private Partnership |
V/C | Volume/Capacity Ratio |
VDF | Volume Delay Function |
WACC | Weighted Average Cost of Capital |
This section describes the use of the simplified inputs sheet. Please refer to Section 4 for a discussion of the detailed input sheets.
The simplified input sheet can be accessed through the Model Navigator. The following panel with the simplified input sheet will appear upon clicking on the Inputs button in the Model Navigator. Alternatively, users can use the usual Excel navigation features to access the simplified input sheet.
Model Navigator
This model navigator shows simplified inputs selected.
The simplified input sheet contains three input sections:
Although each of the inputs used in the simplified input sheet are also included in the detailed input sheets (see Section 4 for more details), this section provides a brief description of the relevant inputs used in the simplified input sheet.
Please note that under the simplified inputs option, no pure risk or base variability inputs or calculations are considered. As such, users should input risk- and uncertainty-adjusted costs where appropriate (see Sections 3.1.3 and 3.1.4). Furthermore, the user does not have access to the "Non Changeable Technical Inputs" described in Section 4.1.4. Other differences between the simplified inputs option and the detailed inputs will be highlighted where appropriate.
In this section, users will provide inputs regarding the project's delivery, timing, costs, and financing. Users will be required to input data for the PSC and the P3 delivery models. For the Delayed PSC delivery model, the user only needs to input start of pre-construction (see below), with all other values assumed to be equal to the PSC. Users should input data in the yellow-shaded cells. Under the simplified inputs option, all costs are expressed in millions of dollars.
For the various capital cost components under P3, the user has to indicate how much of the costs are expected to be transferred from the Agency to the P3 concessionaire.
For the various operational cost components under P3, the user has to indicate how much of the costs are expected to be transferred from the Agency to the P3 concessionaire.
Under the simplified inputs option, handback costs and the cost of non-compensated losing bids (only used in the PDBCA module) are not considered.
Under the simplified inputs option, P3-VALUE 2.2 makes the following additional financing assumptions:
The following provides sample inputs for delivery, timing, cost, and financing:
Project Configuration Inputs | PSC | P3 | |
---|---|---|---|
Facility tolled? | TRUE | ||
P3 delivery model | ///////// | Toll concession | |
Project Timing Inputs | PSC | P3 | |
Pre-construction start year | 2018 | 2018 | |
Pre-construction duration (in years) | 2 years | 2 years | |
Construction duration (in years) | 4 years | 3 years | |
Operations duration (in years) | 40 years | 41 years | |
Delayed PSC pre-construction start year | 2023 | ||
Capital Cost Inputs (Risk Adjusted)* | PSC | P3* | |
Public procurement cost (in million $) | $5.0M | $10.0M | 0% |
Private procurement cost (in million $) | $5.0M | $10.0M | 100% |
Pre-construction cost (in million $) | $25.0M | $22.5M | 100% |
Construction cost (in million $) | $400.0M | $367.5M | 100% |
Operational Cost Inputs (Risk Adjusted)* | PSC | P3* | |
Annual routine O&M cost (in million $/year) | $4.0M | $3.6M | 100% |
Major maintenance cost (in million $) | $10.0M | $9.0M | 100% |
Major maintenance frequency (in years) | 8 years | 8 years | |
No Build annual O&M cost savings (in million $/year) | $10.0M | ||
Financing Inputs | PSC | P3 | |
Subsidy/milestone payment (in million $) | $100.0M | $100.0M | |
Cost of equity (in percent) | ///////// | 12.00% | |
Gearing (in percent) | ///////// | 75.00% | |
Debt maturity (from start construction, in years) | 35 years | 30 years | |
Debt interest rate (in percent) | 4.00% | 6.00% | |
Equity bridge loan interest rate (in percent) | ///////// | 6.00% | |
Minimum required DSCR (multiple of debt service) | 1.30x | 1.30x | |
Interest rate on reserves (in percent) | 2.00% | 2.00% | |
Debt issuance/arrangement fee (in percent) | 1.00% | 1.00% | |
*P3 cost and cost share transferred to P3 concessionaire |
In this section, users will provide inputs regarding the project's projected traffic, tolls as well as other traffic characteristics.
The model enables users to input bidirectional P50 (or most likely) weekday traffic data for up to five different input years over the project analysis period. Users must provide traffic data for the No Build and Build (Managed Lanes or Tolled Lanes and General Purpose Lanes separately) for the model start year. Users may also provide up to four additional traffic data points by entering the relevant traffic data point year and forecast. If the project is a simple toll road (as opposed to a Managed Lanes facility), traffic inputs on the General Purpose Lanes (GPL) should be zero. If the project is not tolled, traffic inputs on the Managed Lanes or Tolled Lanes (ML/TL) should be zero. If the project is a managed lane project, the user will input both tolled traffic (on ML/TL) and non-tolled traffic (GPL). Please note that Build traffic (Managed Lanes or Tolled Lanes and General Purpose Lanes traffic combined) should be equal to or exceed No Build traffic.
Users are also expected to provide the annual traffic growth after the last input year. This input is used to project traffic beyond the last year of input. In the sample inputs below, "> 2050" refers to traffic growth after 2050, the last year of input in the considered example.
The following shows sample inputs for a project involving the expansion of an existing facility to accommodate managed lanes along with free GPLs. The units are thousands of vehicles per weekday.
Bidirectional P50 Traffic Inputs | Year | No Build | ML/TL | GPL |
---|---|---|---|---|
Weekday daily traffic in model start year (in thousands) | 2017 | 120k | 25k | 105k |
Weekday daily traffic in input year 2 (in thousands) | 2020 | 127k | 30k | 110k |
Weekday daily traffic in input year 3 (in thousands) | 2030 | 138k | 35k | 121k |
Weekday daily traffic in input year 4 (in thousands) | 2040 | 150k | 40k | 131k |
Weekday daily traffic in input year 5 (in thousands) | 2050 | 158k | 45k | 142k |
Annual traffic growth after last input year (in percent) | > 2050 | 0.50% | 1.00% | 0.50% |
Users will need to input the toll rates for passenger cars and trucks/buses for weekday peak, weekday off-peak and weekends, for the No-Build, ML/TL, and GPL. The following shows sample inputs.
Toll Inputs | No Build | ML/TL | GPL |
---|---|---|---|
Passenger car toll rate - Weekday peak (in dollars) | $0.00 | $4.00 | $0.00 |
Passenger car toll rate - Weekday off-peak (in dollars) | $0.00 | $2.00 | $0.00 |
Passenger car toll rate - Weekend (in dollars) | $0.00 | $2.00 | $0.00 |
Truck/bus axle toll rate - Weekday peak (in dollars) | $0.00 | $6.00 | $0.00 |
Truck/bus axle toll rate - Weekday off-peak (in dollars) | $0.00 | $4.00 | $0.00 |
Truck/bus axle toll rate - Weekend (in dollars) | $0.00 | $4.00 | $0.00 |
The following shows sample inputs for the above listed parameters.
Traffic Characteristics, Share & Speed Inputs | No Build | ML/TL | GPL |
---|---|---|---|
No. of lanes per direction | 3 lanes | 2 lanes | 3 lanes |
Unidirectional peak traffic percentage (% of total traffic) | 30% | 30% | 30% |
Weekend traffic (% of weekday traffic) | 60% | 60% | 60% |
Passenger car percentage - Peak (% of total traffic) | 95% | 100% | 95% |
Passenger car percentage - Off-peak (% of total traffic) | 90% | 100% | 90% |
Passenger car percentage - Weekend (% of total traffic) | 95% | 100% | 95% |
Highway free flow speed - Passenger car (in mph) | 65 mph | 70 mph | 70 mph |
Highway free flow speed - Truck/bus (in mph) | 60 mph | 65 mph | 65 mph |
Users will also need to provide the following ramp-up and traffic-related inputs.
The following shows sample inputs for the above listed parameters.
Ramp-Up & Other Inputs | |
---|---|
Ramp-up starting traffic (% of post-ramp up traffic) | 50% |
Ramp-up period duration (in years) | 5 years |
Toll revenue leakage (in percent) | 1.00% |
Segment length (in miles) | 20 miles |
No. of unidirectional peak hours in a day (during AM, PM or combined) | 3 hours |
No. of unidirectional off-peak hours in a day | 15 hours |
Under the simplified inputs option, P3-VALUE 2.2 assumes that the "Traffic sensitivity factor for PDBCA (applies to traffic above No Build base year traffic)" is 100% (see Section 4.2.4 for a discussion of this input). Furthermore, the model adopts the preset values for the following inputs (see Section 4 for more details):
In this section, users will provide inputs regarding the project's benefits and costs, taxation, competitive neutrality adjustment, inflation, discount rates, lifecycle performance risks and revenue uncertainty adjustment.
Under the simplified inputs option, P3-VALUE 2.2 requires the user to provide a limited number of benefit-cost-related inputs, including:
The following shows sample inputs for the above listed parameters.
Benefit Cost Inputs (Delays & Pavement Quality) | No Build | PSC | P3 |
---|---|---|---|
Average duration of construction activity (in hours) | 0.00 hours | 8.00 hours | 7.50 hours |
Average duration of O&M activity (in hours) | 4.00 hours | 3.00 hours | 2.75 hours |
Speed adjustment factor for incident delays (in percent) | 18.00% | 9.00% | 8.50% |
Pavement quality (IRI, in inch/mile) | 150 inch/mile | 140 inch/mile | 130 inch/mile |
Benefit Cost Inputs (Transit & Carpool) | No Build | ML/TL | GPL |
Additional passengers carried by transit (% of vehicles) | 2.00% | 4.00% | 1.50% |
Additional passengers carried by carpools (% of vehicles) | 2.00% | 4.00% | 1.50% |
Under the simplified inputs option, the model adopts the values from the detailed input sheets for the following inputs (see Section 4 for more details):
The following shows sample inputs for the above listed parameters.
Taxation Inputs | State | Federal |
---|---|---|
Tax rate (in percent) | 10.00% | 25.00% |
Tax considered for competitive neutrality adjustment? | TRUE | TRUE |
Competitive Neutrality Adjustment Inputs | ||
Value of construction self-insurance (% of transferred construction costs) | 0.00% | |
Value of O&M and major maintenance self-insurance (% of transferred O&M costs) | 0.00% | |
Value of credit subsidy or tax benefits under PSC delivery (in million $) | $0.0M | |
Value of credit subsidy or tax benefits under P3 delivery (in million $) | $0.0M |
Under the simplified inputs option, P3-VALUE 2.2 assumes that tax benefits due to the effects of depreciation can be passed on to the parent company ("tax pass-through), meaning that no tax losses need to be brought forward.
The following shows sample inputs for the above listed parameters.
Inflation & Discount Rate Inputs | |
---|---|
Indexation and NPV base year | 2018 |
Indexation rate for construction, operations, tolls & subsidy (in percent) | 2.00% |
Allowable share of indexed O&M component in availability payment (in percent) | 20.00% |
Indexation rate for O&M component of availability payments (in percent) | 2.00% |
Nominal discount rate (in percent, used for VfM) | 4.00% |
Real discount rate (in percent, used for BCA) | 2.00% |
The following shows sample inputs for the above listed parameters.
Lifecycle Performance Risk & Revenue Uncertainty Adjustment Inputs | |
---|---|
Lifecycle performance risk calculation method (see options below) | Option 1 |
Lifecycle performance risk aggregate premium (in million $, option 2 only) | $400.0M |
Revenue uncertainty adjustment calculation method (see options below) | Option 1 |
Delta between availability payment & toll concession WACC (in percent, option 1 only) | 1.60% |
Revenue uncertainty adjustment (% of toll revenue collection, option 2 only) | 28.00% |